Search from over 10,000+ business opportunities that have been announced from the biggest West Bengal tenders, e tender West Bengal, WB government tenders, and the Online Tender Notices posted on West Bengal e tenders to date. Find opportunities that have come in from multiple corporations, West Bengal government departments, State PSUs, and several Private companies from the state.
Howrah Improvement Trust - HIT Tender
Eprocure
Opening Date29 Aug 2019
Closing Date13 Sep 2019
Tender Amount₹ 40,77,305
Costs
EMD
₹ 81,600Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2019_HIT_240816_3Bid Award Id
ViewTender No
HIT/CE/4B/2019-20Tender Authority
Howrah Improvement Trust ViewPurchaser Address
-Website
http://wbtenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Controlled Cement concrete with well graded stone chips (20 mm nominal size) excluding shuttering and einforcement with complete design of concrete as per IS : 456 and elevant special publications, submission of job mix formula after preliminary mix design after testing of concrete cubes as per direction of Engineer-in charge. Consumption of cement will not be less than 300 Kg of cement with Super plasticiser per cubic meter of controlled concrete but actual consumption will be determined on the basis of preliminary test and job mix foumula. In ground floor and foundation.[using concrete mixture] M 25 Grade (i) Pakur Variety
75
-
6284.24
... More
Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels urved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor) (c) Steel shuttering or 9 to 12 mm thick approved quality ply board shuttering in any concrete work
1170
-
368
... More
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawingand direction
Tor steel/Mild Steel I. SAIL/ TATA/RINL
13.1
-
67972.88
... More
Applying epoxy based reactive joining agent for joining the old concrete with fresh concrete to be applied within anufacturer's specified time as permanufacturers specification. (0.4 Kg / m² of concrete surface).
165
-
309
... More
Hire and labour charges for 75 mm dia bamboo railing on Jhau/Eucalyptus or other approved timber posts 1.4 m above G.L. and 0.60 m below G. including tying strongly with coir ropes and boring holes for posts in any soil/ concrete surface/ Bituminious surface packing the sides etc including cost of carriage of all materials and labour complete including cost of restoration to the damages of the ground to its original condition as per direction of Engineer in charge after removing the barricade. (a) 75mm. dia bamboo railing & 125mm. Dia Jhau/Eucalyptus/other approved timber posts @ 1.60m apart (ii) Railing with 3 rows.
400
-
49
... More
Hire and labour charges for coir rope fencing 25 mm dia rope single on 120 m dia bamboo posts 1.40 m above G.L and 600 mm below G.L 1.50 m apart including digging holes complete
100
-
17
... More
Labour for propping up overhead members as a precautionary measure against falling as directed with necessary lanks, Eucalyptus props, packing nails, wire ropes, iron wires etc. including hire charges of all materials fitting, fixing dismantling and removing the props etc and all ancillary works in this connection complete.
1800
-
55
... More
Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor), With 1:4 cement mortar 15mm thick plaster
1418
-
160
... More
Applying Exterior grade Acrylic primer of approved quality and brand on plastered or cencrete surface old or new surface to receive decorative textured (matt finish) or smooth finish acrylic exterior emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer's specification and as per direction of the
EIC. Two Coats.
1745
-
4510
... More
Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer's specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer. Super Protective
1745
-
97
... More
Making one set of scaffolding only for replacing glass panels painting etc (a) upto 3.90 mtr... ...
Total area of elevation scaffolding =2*13.30*3.5=93.10 Sqm,Now as per the rule mensioned below no of set of scaffolding={93.10/(19+1)}=4.66 ~ 5 Nos [ One set for original Scaffolding & 19 set for shifting the original scaffolding]
(This item should be executed only after prior approval of the Engineer-incharge).
Firstly, one number to be paid and then labour rate for shifting up to further nineteenth (19) times @ 10% each time to be considered. If necessary further after twenty times of total use, another one number new and labour rate for shifting to be considered accordingly.
5
-
279
... More
For Each SET shifting
95
-
27.9
... More
Staging beyond 4 m in any floor (Mode of measurement: area in plan x mean height of staging upto soffit of shuttering above initial 4m
579
-
61
... More
Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed.
276
-
19
... More
Cleaning the exposed corroded Reinforcement as well as worn out concrete by sand blasting with air compressor including all materials , hire
charges of machineries and labour etc. all complete as per technical specification and direction of the Engineer-in-Charge.
52
-
604
... More
Removing corroded worn out portion of reinforcement (when the area of bar is damaged by more than 25%) by cutting and replacing the same by a new plain round bar of requisite diameter by binding with required lap / welding with old bar, including cost of reinforcement, complete in all respect including removing unserviceable materials from site as per direction of the Engineer - in - charge. Note : Payment on weight (Kg.) of new reinforcement.
395
-
87
... More
Providing anti-corrosive protective coating to inhibit the corrosion to HYSD reinforcements including two coats of anti-corrosive coatings of consumption as per manufacturer's specification, cleaning etc. complete as per the direction of the
Engineer-in-Charge
26
-
506
... More
Epoxy bonding of new concrete to old concrete
415
-
517
... More
Patching of damaged concrete surface with polymer concrete (25 mm nominal thick) and curing compounds, initiator and promoter, available in present formulations, to be applied as per instructions of manufacturer and as approved by the Engineer.
177
-
1391
... More
Providing and inserting nipples with approved fixing compound…..
70
-
102
... More
Sealing of crack/porous concrete by injecting (B) Epoxy Grout
17.5
-
882
... More
Labour for Chipping of concrete surface before taking up Plastering work.
345
-
21
... More
Guniting concrete surface with cement mortar (25 mm nominal thick) applied with compressor after cleaning surface and spraying with epoxy complete as per Technical specification.
345
-
912
... More
Brick work with 1st class bricks in cement mortar (1:4)
(a) In foundation and plinth For repairing of Side Guard wall portion
1.5
-
5560
... More
Neat cement punning about 1.5mm thick in wall, dado, window sills, floor, drain etc
10
-
34
... More
Supplying, fitting & fixing UPVC pipes A- Type and fittings conforming to IS:13592-1992 with all necessary clamps nails, including making holes in walls, floor etc. cutting trenches in any soil through masonry concrete structures etc if necessary and mending good damages including joining with jointing materails (Spun Yarn, Valamoid/Bitumen/M-Seal etc) complete. (i) 110 mm Dia
7
-
251
... More
Upvc Shoe (ii) 110 mm. Dia.
For Water drainage from desk slab
2
-
111
... More
Bend 87.5 degree
(ii) 110 mm. Dia.
For Water drainage from desk slab
2
-
160
... More
Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc.
22
-
29
... More
Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary :
(b) On steel or other metal surface :
With super gloss (hi-gloss) -
(iv) Two coats (with any shade except white)
11
-
79
... More
Add GST @12% of 3604406.93
1
-
3604406.93
... More
Add CESS@1% of 4036935.76