Public Works Department Tender
View complete overview of Uttarakhand PWD Tender
Public Works Department - PWD Tender
Eprocure
Opening Date6 Feb 2019
Closing Date12 Feb 2019
Tender Amount₹ 2,00,00,000
Costs
EMD
₹ 4,00,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2019_pwd_15283_1Bid Award Id
ViewTender No
158/Nivida-Bag/2019 Dtd 30/01/2019Tender Authority
Public Works Department ViewPurchaser Address
-
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Random Rubble Masonary laid dry in breast wall,retaining wall, parapets,scupper etc. Including supply of all materials,labour,t & p& royality etc,required for proper complition of work.(As per PWD Uttarakhand specifications)
1468.8
-
-
... More
H.P stone filling in back of wallls including cost of all materials ,royality.t&p etc. complete.
382.19
-
-
... More
Random Rubble stone masonary in Coolie walling including supply of all material,labour, T&P etc. required for proper completion of the work.(As per PWD Uttarakhand specifications)
123.84
-
-
... More
Construction of 1 m span scupper of RR 1:6 abutment ,RCC slab as per attached drawing including supply of all material, labour, T&P etc. required for proper completion of the work.
139
-
-
... More
WBM Grading 1 Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, stone screening/binding materials to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 1 as per Technical Specification Clause 404. By Manual Means
217.87
-
-
... More
Construction of Plum concrete Parapets with 60% cement concrete & 40% plum (approved stone of maximum size 200mm) as per standarad drawing & as per direction of engineer-in-Charge.
220
-
-
... More
Surface Drains in SoilConstruction of unlined surface drains of average cross-sectional area 0.40sqm in soil to specified lines, grades, levels and dimensions. Excavated materialto be used in embankment with a lift upto 3m and lead of 50 m (average lead 25m) as per Technical Specification Clause 307. Manual Means
3990
-
-
... More
Ordinary Kilometer Stone (Precast)
4
-
-
... More
200 m stone (precast)
18
-
-
... More
(Muck Disposal) Removal of unsuitable soil with disposal up to 1000 m .removal of unsuitable soil including exacavation compaction ground supporting embankment subgrade replacementby suitable soil ,which shall be paid separately as per clause 303.5.2 as per technical specifications clause 302.3.11
17687.95
-
-
... More
Providing and laying of wire crates 3.00x1.50x1.50 in size with GI wire
conforming to IS: 280 & IS:4826 in 150mm x 150mm mesh laid with stone
boulders. as per direction of Engineer-in- charge. (As per PWD Uttarakhand specifications) GI wire 10 gauge BWG
1102.5
-
-