BidAssist is a very user-friendly website that lets us explore new opportunities which further helps in the growth of the business. We can get any information regarding any e-tender the Tripura government has posted on its website in a very hassle-free manner. BidAssist is designed in such a manner so as to provide information on all government tenders at one place without any inconvenience.
Public Works Department - PWD Tender
Civil And Construction
Eprocure
Opening Date12 Feb 2025
Closing Date20 Feb 2025
Tender Amount₹ 14,71,555
Costs
EMD
₹ 29,431Document Cost
₹ 1,000Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2025_CEPWD_58285_1Tender No
111/DNIT/EE/MNP/PWD(R n B)/2024-25Tender Authority
Public Works Department ViewPurchaser Address
-Website
http://tripuratenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
... More
Tack coat using hot straight run bitumen of grade VG-30 on W.B.M.
Providing and applying tack coat using hot straight run bitumen of grade VG-30, including heating the bitumen, spraying the bitumen, cleaning and preparing the existing road surface as per specifications: On W.B.M. @ 0.75 kg/ sqm.
450
55
24840
... More
20 mm thick Open-Graded Premix Carpet using Bituminous (Viscosity grade/ modified bitumen) Binder Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using Viscosity grade bitumen or emulsion to required line, grade and level to serve as wearing course on a previously prepared base , including mixing in a suitable plant, laying and rolling with a three wheel 80 - 100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C or Type D as per MoRD Technical Specification Clause 508.
Case - I : By Manual Means
(I) Bitumen of VG-30
450
336
151560
... More
Seal Coat
Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A or Type B or Type C or Type D as per MoRD Technical Specification Clause 510.
A) By Manual Means. Case - IV : Type D (premix with fine sand)
(I) Bitumen of VG-30
450
77
34695
... More
Single bamboo palasiding/walling of whole 2nd class
bamboo (Jati or Bethua) 65 to 75 mm dia and closely
packed & driven @ 150 mm c/c including fitting fixing with half bamboo kamis horizontally in three rows with cane or tying with wire complete and struts 1.5 m apart longitudinally and providing bitumen drum sheet walling fixed with nails as per drawing and MoRD technical specification Clause 1302.5.
A) Driven at least 900 mm below ground and 1200
mm above ground on average
20
1149
22988
... More
Construction of Embankment with Material Obtained from Borrow Pits
Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per MoRD Technical Specification Clause 301.5.
22.5
245
5522
... More
Excavation for Structures
A. Without dewatering.
Earthwork in excavation for structures as per drawing and MoRD technical specifications Clause 305.1 including setting out, construction of shoring & bracing, removal of stumps & other deleterious material and disposal upto a lead of 50 m, dressing of sides & bottom and backfilling in trenches with excavated suitable material. Ordinary Soil
(i) Upto 3 m depth
104.58
458
47919
... More
Filling in foundation trenches as per drawing & MoRD technical specification Clause 305.3.9, 1200.
I ) Sand filling
14.96
1168
17467
... More
Providing concrete for plain concrete (using jhama brick aggregate) in open foundations complete including formwork as per drawings & MoRD technical specifications Clauses 802, 803, 900, 1202 and 1203. (including centering, shuttering, staging etc. but excluding reinforcement) I) P.C.C grade M 10 (using jhama brick aggregate)
(i) Nominal mix 1:3:6
17.43
9099
158611
... More
Providing & laying reinforced cement concrete in superstructure as per drawings & MoRD technical specifications Clauses 800, 900, 1205.4 & 1205.5 (including centering, shuttering, staging etc. but excluding reinforcement).
R.C.C M 25
1 For height upto 5 m
3.97
13372
53061
... More
Supplying, fitting, & placing Thermo-Mechanically treated bar/ Cold twisted deformed steel bar reinforcement in superstructure complete as per drawing & MoRD technical specifications Clauses 1002, 1010 & 1202.
0.44
93234
40650
... More
Brick masonry work in cement mortar in foundation completed excluding pointing & plastering as per drawing & MoRD technical specifications Clauses 600, 1202 & 1203. Brick masonry in 1:4 cement mortar
52.26
9418
492173
... More
Plastering with cement mortar (1:4) 12 mm thick on brickwork/ C.C. work including a finishing coat of neat cement punning with 2.75 kg of cement per sqm in substructure as per MoRD technical specification Clauses 613.4 & 1204.
205.52
224
46160
... More
Providing weep holes in brick masonry/ stone masonry,
plain/ reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe or uPVC pipe (110 mm OD of 6.0 kg/cm2 pressure) extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and MoRD technical specification clauses 614, 709, 1204.3.7.
2
392
784
... More
Providing & laying filter media with jhama brick aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil & bigger size towards the wall & providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and MoRD technical specification clause 1204.3.8.
7.68
4582
35194