Telangana State Southern Power Distribution Company Limited Tender

For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.

Telangana State Southern Power Distribution Company Limited - TSSPDCL Tender

Opening Date23 Aug 2021
Closing Date25 Sep 2021
Tender Amount₹ 41,18,543 
This is an estimated amount, exact amount may vary.
Notes
Download

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Narsingi stretch III;Dismantle of Three Phase DTRs 100 KVA

1

-

955

... More
Narsingi stretch III;Dismantling of DTR plinth (Column type)

1

-

1575

... More
Narsingi stretch III;Painting of sub-station structures with two coats of Aluminium paint using Aluminium paint 1st grade containing 3.6 kg of Aluminium paste for 18 liters of thinner 1st coat is to be applied before erection of sub-station structures and 2nd coat after stringing and half round welding including cost of paint, cost of brushes, labour charges etc., complete - Labour charges for painting including scratching and cleaning of Substation structures of 2nd coat of Aluminium

0.45

-

216.9

... More
Narsingi stretch III;Painting of sub-station structures with two coats of Aluminium paint using Aluminium paint 1st grade containing 3.6 kg of Aluminium paste for 18 liters of thinner 1st coat is to be applied before erection of sub-station structures and 2nd coat after stringing and half round welding including cost of paint, cost of brushes, labour charges etc., complete- Supply of material cost for Second coat of 1st Grade Aluminium Paint, brushes, etc.

0.45

-

581.85

... More
Narsingi stretch III;Painting of sub-station structures with two coats of Aluminium paint using Aluminium paint 1st grade containing 3.6 kg of Aluminium paste for 18 liters of thinner 1st coat is to be applied before erection of sub-station structures and 2nd coat after stringing and half round welding including cost of paint, cost of brushes, labour charges etc., complete. -Labour charges for painting including scratching and cleaning of Substation structures of 1st coat of Aluminium

0.45

-

382.95

... More
Narsingi stretch III;Painting of sub-station structures with two coats of Aluminium paint using Aluminium paint 1st grade containing 3.6 kg of Aluminium paste for 18 liters of thinner 1st coat is to be applied before erection of sub-station structures and 2nd coat after stringing and half round welding including cost of paint, cost of brushes, labour charges etc., complete. - Supply of material cost for First coat of 1st Grade Aluminium Paint, brushes etc.

0.45

-

981.45

... More
Narsingi stretch III;Fabrication of Main and Auxiliary structures with welding using raw steel such as RS joist, M.S.Angles, Plates, Channels, including the supply and fabrication of 6mm base plate to the RS-Joist poles excluding cost of Mild Steel and transport charges to substation site, including erection.

0.45

-

1541.7

... More
Narsingi stretch III;Mass concreting of supports erected with CC (1:4:8) using 40 mm, HB G metal including the cost of metal, sand, Cement and curing etc.- Including the cost of cement

1.05

-

5418

... More
Narsingi stretch III;Earth work excavation of pits in hard rock requiring blasting.

1.05

-

833.7

... More
Narsingi stretch III;Erection of pole in position, aligning and setting to work, fixing of cross arms and top clamps, earthing of supports, back filling with earth and stones properly ramming including transport of materials from road side to location excluding pit excavation - Box pole 9/10/11 Mtr

1

-

2048

... More
Narsingi stretch III;Erection of 11KV HG Fuse set complete

1

-

660

... More
Narsingi stretch III;Erection of 11KV 200A TT type AB Switch including fixing of cross angles and alignment complete

1

-

1405

... More
Narsingi stretch III;Supply of CI earth pipe 100 mm dia, 2.75 mt long thickness 10mm with flange as per specication

3

-

10458

... More
Narsingi stretch III;Excavation of earth pit, putting cast iron pipe with flange on one end of nominal dia 100mm and 2.75 meters long in side the pit including supply and fixing RCC collars 0.75 meter dia (OD), 50mm thick and 0.60meters long in side the pit, backfill the pit

3

-

5790

... More
Narsingi stretch III;RCC Column type DTR Plinth of size 1'X1'X10',topslab 4'x4'x6" & beam size 4'X8'X8"

1

-

23144

... More
Narsingi stretch III;Erection of DTR's including loading and Unloading DTR on the Structure/Plinth etc - Erection of 3 Phase DTRs 63,75 & 100 KVA

1

-

1650

... More
Narsingi stretch III;Painting of sub-station structures with two coats of Aluminium paint using Aluminium paint 1st grade containing 3.6 kg of Aluminium paste for 18 liters of thinner 1st coat is to be applied before erection of sub-station structures and 2nd coat after stringing and half round welding including cost of paint, cost of brushes, labour charges etc., complete - Labour charges for painting including scratching and cleaning of Substation structures of 2nd coat of Aluminium

2.6

-

1253.2

... More
Narsingi stretch III;Painting of sub-station structures with two coats of Aluminium paint using Aluminium paint 1st grade containing 3.6 kg of Aluminium paste for 18 liters of thinner 1st coat is to be applied before erection of sub-station structures and 2nd coat after stringing and half round welding including cost of paint, cost of brushes, labour charges etc., complete- Supply of material cost for Second coat of 1st Grade Aluminium Paint, brushes, etc.

2.6

-

3361.8

... More
Narsingi stretch III;Painting of sub-station structures with two coats of Aluminium paint using Aluminium paint 1st grade containing 3.6 kg of Aluminium paste for 18 liters of thinner 1st coat is to be applied before erection of sub-station structures and 2nd coat after stringing and half round welding including cost of paint, cost of brushes, labour charges etc., complete. -Labour charges for painting including scratching and cleaning of Substation structures of 1st coat of Aluminium

2.6

-

2212.6

... More
Narsingi stretch III;Painting of sub-station structures with two coats of Aluminium paint using Aluminium paint 1st grade containing 3.6 kg of Aluminium paste for 18 liters of thinner 1st coat is to be applied before erection of sub-station structures and 2nd coat after stringing and half round welding including cost of paint, cost of brushes, labour charges etc., complete. - Supply of material cost for First coat of 1st Grade Aluminium Paint, brushes etc.

2.6

-

5670.6

... More
Narsingi stretch III;Fabrication of Main and Auxiliary structures with welding using raw steel such as RS joist, M.S.Angles, Plates, Channels, including the supply and fabrication of 6mm base plate to the RS-Joist poles excluding cost of Mild Steel and transport charges to substation site, including erection

2.6

-

8907.6

... More
Narsingi stretch III;Formatn of Horiz Cut point for 11KV line

5

-

5595

... More
Narsingi stretch III;Formation of 11kvline vertical cutpoint

5

-

9990

... More
Narsingi stretch III;Transport of conductor drums, cable drums, fragile material such as kiosks, VCBs, control panels, current transformers, boosters, lightning arrestors, insulators, transformers, meters (which are less in weight and occupy more space) (excluding of loading unloading) - Above 30 Km and upto 50 Km with Lorry for each trip

1

-

4287

... More
Narsingi stretch III;UNLOADING of Conductor drums

2

-

194

... More
Narsingi stretch III;LOADING of Conductor drums

2

-

404

... More
Narsingi stretch III;S-GI Bolts & Nuts,Washers etc.,

75

-

7050

... More
Narsingi stretch III;S-Earthing GI flat 25x3 mm incl material

25

-

2100

... More
Narsingi stretch III;Erection of 11KV 400/200A Conventional type AB Switch including fixing of cross angles and alignment complete

1

-

1598

... More
Narsingi stretch III;Dismantlingof 11 KVAB Switch 400/200 A con

1

-

785

... More
Narsingi stretch III;Dismantling of 11kV 34/ 55 Sqmm SC

0.6

-

2039.4

... More
Narsingi stretch III;Dismantling of 11KV 34/55 sqmm SC

0.6

-

2039.4

... More
Narsingi stretch III;Dismantling of Damaged Poles, not required and available in the middle of roads, transporting to stock point etc.-Dism of 9.1M PSCC Pole

17

-

14365

... More
Narsingi stretch III;Mass concreting of supports erected with CC (1:4:8) using 40 mm, HB G metal including the cost of metal, sand, Cement and curing etc. - Including the cost of cement

4.4

-

22704

... More
Narsingi stretch III;Earth work excavation of pits in hard murram/rock boulders

9.68

-

11616

... More
Narsingi stretch III;Earth work excavation of pits in hard rock requiring blasting.

8.8

-

6987.2

... More
Narsingi stretch III;Erection of pole in position, aligning and setting to work, fixing of cross arms and top clamps, earthing of supports, back filling with earth and stones properly ramming including transport of materials from road side to location excluding pit excavation - 11 Mtrs PSCC poles

21

-

71001

... More
Narsingi stretch III;Paving out and stringing of conductor by providing temporary stays, tensioning, sagging correctly, fixing strain points, transferring to pin points binding, keeping stifner, rectification of poles, guys and jumpering etc., including transport of material from road side to location. - 55 Sqmm Single Circuit (3 Conductors)

0.85

-

6348.65

... More
Narsingi stretch III;Paving out and stringing of conductor by providing temporary stays, tensioning, sagging correctly, fixing strain points, transferring to pin points binding, keeping stifner, rectification of poles, guys and jumpering etc., including transport of material from road side to location. - 55 Sqmm Single Circuit (3 Conductors)

0.85

-

6348.65

... More
Narsingi stretch III;Supply-GI Bolts & Nuts,Washers etc.,

4705.75

-

442340.5

... More
Narsingi stretch III;Supply of M+3 Tower stub Material Galvanized

7.5

-

571305.9

... More
Narsingi stretch III;Transport of conductor drums, cable drums, fragile material such as kiosks, VCBs, control panels, current transformers, boosters, lightning arrestors, insulators, transformers, meters (which are less in weight and occupy more space) (excluding of loading unloading) - Above 10 Km and upto 20 Km with Lorry for each trip

1

-

3235

... More
Narsingi stretch III;UNLOADING of ACSR conductor scrap

0.72

-

353.52

... More
Narsingi stretch III;LOADING of ACSR conductor scrap

0.72

-

353.52

... More
Narsingi stretch III;Horizontal Cut point for 33 KV line

5

-

8780

... More
Narsingi stretch III;Formation of 33kvline vertical cutpoint

5

-

15680

... More
Narsingi stretch III;Transport of iron materials such as R.S. Joists, Rail Poles, fabricated supports, steel, iron, flat, M.S. Channels etc., by lorries. (excluding of loading & unloading ) - Upto 10 KM

17.05

-

5677.65

... More
Narsingi stretch III;UNLOADING of MS Scrap

17.05

-

9854.9

... More
Narsingi stretch III;LOADING of MS Scrap

17.05

-

9854.9

... More
Narsingi stretch III;Drilling of Holes in Hard rock upto a depth of 3.3 Mtr hard rock blasting is not possible for 4 Nos. Tower legs

20

-

286000

... More
Narsingi stretch III;Earth work excavation of pits in hard murram/rock boulders

38.02

-

45619.2

... More
Narsingi stretch III;Erection of Extension of 3Mtrs for M+3 - Galvanized

28

-

137760

... More
Narsingi stretch III;Supply of material for Extension of 3Mtrs for M+3 - Galvanized

3

-

77670

... More
Narsingi stretch III;Erection of M+3 Tower - Galvanized

28

-

1772652

... More
Narsingi stretch III;Supply of M+3 Tower - Galvanized

3

-

383100

... More
Narsingi stretch III;Transport of conductor drums, cable drums, fragile material such as kiosks, VCBs, control panels, current transformers, boosters, lightning arrestors, insulators, transformers, meters (which are less in weight and occupy more space) (excluding of loading unloading) - Above 30 Km and upto 50 Km with Lorry for each trip

2

-

8574

... More
Narsingi stretch III;UNLOADING of Conductor drums

3

-

291

... More
Narsingi stretch III;LOADING of Conductor drums

3

-

606

... More
Narsingi stretch III;survey line&cabl inc peg mark&tree clear

0.85

-

425

... More
Narsingi stretch III;Supply-GI Bolts & Nuts,Washers etc.,

50

-

4700

... More
Narsingi stretch III;Dismantling of M type tower

17

-

58055

... More
Narsingi stretch III;Dismantling of 100 Sqmm conductor SC

0.6

-

3894

... More
Narsingi stretch III;Dismantling of 100 Sqmm Conductor DC.

0.6

-

5560.8

... More
Narsingi stretch III;Paving out and stringing of conductor by providing temporary stays, tensioning, sagging correctly, fixing strain points, transferring to pin points binding, keeping stifner, rectification of poles, guys and jumpering etc., including transport of material from road side to location. - 100 Sqmm Single Circuit (6 Conductors)

0.85

-

17325.55

... More
Narsingi stretch III;Paving out and stringing of conductor by providing temporary stays, tensioning, sagging correctly, fixing strain points, transferring to pin points binding, keeping stifner, rectification of poles, guys and jumpering etc., including transport of material from road side to location. - 100 Sqmm Single Circuit (3 Conductors)

0.85

-

11547.25



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.