Tamil Nadu Transmission Corporation Limited Tender
Search from a plethora of business opportunities for Tamil Nadu tenders posted on the eProcurement TamilNadu website and other online and offline sources. Here, on BidAssist, you can find the best tender opportunities to boost your enterprise by finding work in Tamil Nadu government tenders, PSUs, Municipal Corporations and more. Read on to learn about the bidder registration process, DSC and more.
Tamil Nadu Transmission Corporation Limited - TANTRANSCO Tender
Eprocure
Opening Date14 Jul 2018
Closing Date19 Jul 2018
Tender AmountRefer Documents
Costs
EMD
₹ 42,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2018_EB_98879_1Bid Award Id
ViewTender No
GCC 130 GL 067 2018-19Tender Authority
Tamil Nadu Transmission Corporation Limited ViewPurchaser Address
-Website
http://tntenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Earthwork excavation in MR and DMR not requiring blasting.
231
-
-
Earthwork excavation in MR and DMR requiring blasting.
116
-
-
Earthwork excavtion in hard rock measured in solid including blasting and stacking
58
-
-
Removal of HR by wedging and chiselling
58
-
-
Transporting and fixing of stub and cleat with supply of template and assembling at site and shifting the template from loc to loc including cost of all materials for stub and cleat and template ,labour, fabrication charges etc complete. (Stub and cleat only supplied by department) For KCR Tower
4
-
-
Transporting and fixing of stub and cleat with supply of template and assembling at site and shifting the template from loc to loc including cost of all materials for stub and cleat and template ,labour, fabrication charges etc complete. (Stub and cleat only supplied by department) For HCR Tower
1
-
-
Transporting and fixing of stub and cleat with supply of template and assembling at site and shifting the template from loc to loc including cost of all materials for stub and cleat and template ,labour, fabrication charges etc complete. (Stub and cleat only supplied by department) ForLSR Tower
2
-
-
PCC1:3: 6 using 20mm metal for foundation concrete with out form work including cost of all materials, lead, lift ,frustum box , etc complete .
21
-
-
PCC 1:2:4 using 20mm metal for chimney concrete with steel frustum box and chimney box including cost of all materials, lead, lift ,frustum box ,chimney box, etc complete .
123
-
-
Providing steel reinforcement for RCC works including cost of steel rod binding wire and placing in postion of the steel reinforcement all materials, lead and lift etc., complete.
8200
-
-
RCC 1:1.5:3 mix using 20mm graded hard machine broken granite stone, foundation and chimney concrete with steel frustum box and chimney box including cost of all materials, curing, all labour charges, lead, lift, etc. complete. ( excluding cost of steel reinforcement.)
79
-
-
Refilling with the excavated earth other than sand including watering consolidation in 150mm layers and forming platform with excess earth in the leg of the tower etc complete. KCR tower
4
-
-
Refilling with the excavated earth other than sand including watering consolidation in 150mm layers and forming platform with excess earth in the leg of the tower etc complete. HCR tower
1
-
-
Refilling with the excavated earth other than sand including watering consolidation in 150mm layers and forming platform with excess earth in the leg of the tower etc complete. LSR tower
2
-
-
supply & Providing pipe type earthing including necessary excavation for fixing 3m long 25mm dia GI "B" class pipe and refilling with excavated earth mixed with soft charcoal and connect the earthstrip with the leg of the stub including all cost of materials, lead, lift etc complete.
5
-
-
Removal of surplus earth in a low lying area to a average distance of 200m by head load.
223
-
-
Dewatering charges during excavation and concreting with 3/5 HP Diesal motor with Pump including hire charges, labour,fuel,oil,transport etc complete
2
-
-
Providing shoring and shuttering in foundation using wooden planks and scantling including all cost of materials, labour, lead, lift etc complete.
2
-
-
Transport and erection of GI tower angles including cost of materials, T &P,labour, lead, lift etc complete.as per approved drawing and specification
55
-
-
Fabrication, supply of hot dip galvanized Tower parts, as per relevant IS spaecification and erection including Cost of materials, sorting out of tower parts, transport of tower parts rectification of defective member it any including providing correct holes and cutting of angle wherever necessary, patch painting tightening of bolts and nuts punching, lead lift, etc., including T & Ps. Any defect that are pointed out by operation wing of TANTRANSCO before taking over of line should be rectified by free of cost.
0.5
-
-
Supply and fixing of hot dipped glavanised iron Bolt and Nut, packing washers,Spring washers, conforming to IS 2427/1988, and IS 387 part XIII of latest issue including cost of materials, lead,lifts,etc,complete.
20
-
-
Labour charges for transporting and hoisting of 7 units of 90 KN single suspension Disc insulators with supply and fixing of SS fittings for panther and U bolt including all cost of labour,lead, lift, T & P etc complete (With out PA rod for panther)
18
-
-
Labour charges for transporting and hoisting of 8 units of 120 KN single Tension Disc insulators with supply and fixing of ST fittings for panther,S.B damper with all allied hardwares including all cost of labour,lead, lift, T & P etc complete
30
-
-
Labour charges for transporting and hoisting of 9 units of 120 KN Double suspension insulators with supply & fixing of DT fittings for panther with supply of SB damper with all allied hardwares including all cost of labour,lead, lift, T & P etc complete
6
-
-
Labour charges for transport of 3 Nos of Panther conductor from department store,supply and fixing of panther conductor hardwares(ie.SB damper, Dshackle, U bolt,MSJ for panther etc ),paying out, jointing,rough sagging, tensioning, clipping, providing vibration dambers at tension locations including jumber connections, providing trussals at various intervals for avoiding damages of conductor including transport charges, loading, unloading, lead, lift, labour and cost of T&P etc complete(single span )
6
-
-
Labour charges for transport of 3 Nos of Panther conductor from department store,supply and fixing of panther conductor hardwares(ie.SB damper, Dshackle, U bolt,MSJ for panther etc ),paying out, jointing,rough sagging, tensioning, clipping, providing vibration dambers at tension locations including jumber connections, providing trussals at various intervals for avoiding damages of conductor including transport charges, loading, unloading, lead, lift, labour and cost of T&P etc complete(single span WithRailway LC)
1
-
-
Labour charges for transport of 7/3.55mm GI earthwire from Department store supply and fixing of GI earthwire hardwares(ie ST fittings,SS fittings, D shackle, U bolt etc) wherever required, paving out, jointing,rough sagging, tensioning,including jumber connection transport charges, loading,unloading ,lead, lift, cost of T&P, etc complete. ( single Span )
6
-
-
Labour charges for transport of 7/3.55mm GI earthwire from Department store supply and fixing of GI earthwire hardwares(ie ST fittings,SS fittings, D shackle, U bolt etc) wherever required, paving out, jointing,rough sagging, tensioning,including jumber connection transport charges, loading,unloading ,lead, lift, cost of T&P, etc complete. ( single Span with railway LC )
1
-
-
PCC 1:2:4 using 20mm metal for muffing coping concrete with form work including cost of all materials,labour, lead, lift,etc complete .
5
-
-
Plastering with CM 1:3,12 mm thick for muffing coping concrete including cost of all materials,labour,lead,lift etc complete
34
-
-
Supply transport,Labour charges for fixing of number plates, danger board,phase plate including all cost of materials,labour transport,lead, lift,etc complete
14
-
-
Supply,fabrication and fixing of name board with 18 gauge plate including cost of materials, labour for writing name of the line etc complete
3
-
-
Painting with two coats of anticorrosive paint over tower leg at a height of 45cm including all cost of materials,labour, lead lift etc complete
7
-
-
Providing temporary guys wherever necessary including excavation,buryingout of anchor forstaywire,tightening,dismantling the same after completion of works including cost of allmaterials,lead,lift,labour etc complete.
6
-
-
Lowering the HT/LT Line during stringing of power conductor and earthwire after restringing the same in original position including labour,lead ,lift etc complete
5
-
-
Labour charges for removal of large trees
50
-
-
Labour charges for removal of Small tree
50
-
-
Providing full welding of all bolts and nuts in the erected towers from ground level to the cross arm bottom level in the tower including painting of bolts and nuts with two coats of best quality of cold galvanised paint having atleast 90% zinc content and approved by the Engineer at site including cost of paint and all other materials, hire charges for diesel generator and welding transformer, all labour, transport charges etc complete.
9200
-
-
Clearing juliflora jungle with uprooting including all cost of labour, lead, lift etc complete.
5300
-
-
Providing trussels for major and minor road crossing including cost of all materials,labour, lead lift etc. Complete.
10
-
-
Providing Railway crossing earthing arrangements for tower including necessary excavationby augar borewell for fixing 3m long 75mm dia GI "C" class pipe,60cm dia with 5cm shell thick of RCC collar and refilling with excavated earth mixed with salt, charcoal and connect the earthstrip with the leg of the stub and fixing the GI barbed wire for anticlaimbing device to the required height as per instructionof site engineer and approved drawing for earthing including cost all materials,labour,lead,lift etc complete.
2
-
-