Search from a plethora of business opportunities for Tamil Nadu tenders posted on the eProcurement TamilNadu website and other online and offline sources. Here, on BidAssist, you can find the best tender opportunities to boost your enterprise by finding work in Tamil Nadu government tenders, PSUs, Municipal Corporations and more. Read on to learn about the bidder registration process, DSC and more.

Military Engineer Services - MES Tender

Works
Civil And Construction
Civil Works Others
Eprocure
Opening Date26 Jun 2024
Closing Date9 Jul 2024
Tender Amount₹ 49,50,000 
Notes
Download

Costs

Summary

Repair/ Maint To Marking In Fod Lane, Touch Down Area, Threshold Area, Lca Dispersal, Centre Line, Helipad, Nlb And Repairs To Pqc, Pcc In Access Roads Area At Airfield Area

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Due to continuous Flying commitment at Sulur Station, site for execution of work will be available only on Saturday, Sunday, Holiday and non flying days as decided by the ATS authorities.

-

-

-

... More
The tenderer has to arrange his working programme accordingly.

-

-

-

... More
The tenderer has to liaise with the ATS authorities two days prior of his planned works and schedule accordingly.

-

-

-

... More
No claim on account of not giving the entire site after award of work or giving the site in piecemeal manner will not be entertained by the department at any stage.

-

-

-

... More
The quoted rates shall be deemed to be inclusive of above mentioned aspects.

-

-

-

... More
Demolition of existing un-reinforced Cement Concrete in ground floors and pavings not exceeding 15 Cm thickness complete all as specified and directed.

78

-

-

... More
Removal of excavated material to a distance exceeding 1.50 Km and not exceeding 5.00 Km and depositing where directed at a level not exceeding 1.5m above the starting point complete all as specified and as directed.

78

-

-

... More
M & L for Laying Dry lean Concrete (DLC) 100mm thick of aggregate gradation as per Table 1 of SP 49:2014 having 7 day average compressive strength not less than 7 Mpa. Minimum cement content not less than 140 Kg/Cum DLC mixed in Batching Plant, transprted to site and laid by electronic sensor paver including spreading and compacting using high amplitude tamping bars of paver (initial compction) further by double drum smooth wheeled vibratory rollers with 80-100 KN static weight to achieve minimum dry density not less than 98% of maximum Dry Density, necessary finishing etc complete all as specified and tolerances to be as per Table 900-1 of MoRTH specifications for Road and Bridge work 2013.

26

-

-

... More
Note for Item No 11 :- No price adjustment shall be applicable if excess quantity of cement than the minimum is used/ approved based on mix design in the execution of work under this item.

-

-

-

... More
M & L Pavement Quality Cement Concrete (PQC) of minimum 28 days field Flexural strength of 45Kg /Sqcm or 4.5 Mpa, aggregate gradation as per Table 3 of IRC 15-2017, coarse aggregate of clean, hard strong, dense, non-porous and durable pieces of crushed stone or gravel, fine aggregates of clean natural sand or crushed stone sand or combination of both using minimum 360 Kg/cum of cement with non-circular, virgin synthetic fibre of 12-18 mm length, specific gravity 1.34 to 1.39, UV stable, alkali resistant, with equivalent dia 15-40 micron, minimum melting temperature as 240°C and minimum tensile strength of 300 Mpa and at the rate as specified by the manufacturer. PQC laid, spread and compacted with slip-form paver of minimum 7.50m width, including curing and tining by Texturing cum Curing Machine complete all as specifed and directed. Required surface texturing to be done as specified in Clause 10.1.14 and Table 9 of IRC:15-2017.

39

-

-

... More
Note for item No 13 :- (a) Construction Joints/dummy joints and expansion joints shall be measured and paid seperately under respective items.

-

-

-

... More
(b) Deduction shall be made in computing concrete quantity for expansion joints.

-

-

-

... More
(c) Contractor shall consider 360 kg of cement per cum of concrete while quoting this item. Actual quantity of cement shall be used as per approved design mix. No price adjustment shall be applicable for excess quantity of cement content i.e beyond 360 kg as per approved design mix in execution of work

-

-

-

... More
(d) Non circular synthetic fiber shall be mixed in the " PQC" @ 0.25% of cement all as per manufacturers instructions and as directed by Engr-in-charge.

-

-

-

... More
(e) Supply only of POLYESTER TRIANGULAR/non circular synthetic fibre shall be measured and paid seperately.

-

-

-

... More
(f) Cost of brooming and belting shall be deemed to be inclusive in quoted rate.

-

-

-

... More
(g) Cost of steel formwork and testing as specified shall be deemed to included in the rate quoted by the tenderer

-

-

-

... More
(h)Maximum working temperature shall not exceed 30 degree centigrade of atmosphere.

-

-

-

... More
Supply only polyester triangular/Non circular synthetic fibre for pavement quality concrete PQC surface complete all as specified and directed.

39

-

-

... More
Suply & laying 400 micron thick HDPE sheet (Virgin Quality) water proof wrinkle free without puncture having minimum weight 39 gm/ sqm with overlap between adjucent strips and at transverse joints as minimum 300mm all as approved by GE.

26

-

-

... More
Note for Item No 23 :- Measurement shall be taken for net area and unit rate quoted shall deemed to include for over lapping.

-

-

-

... More
M & L Forming dummy/ contraction joint with an initial saw cut of 3 mm soon after the concrete has set, upto a depth of 1/3rd to 1/4th the thickness of the slab, widening the first saw cut to 6 mm and 24 mm deep by using diamond bit cutter of appropriate size, straight and smooth edges. Joint cleaned thoroughly with application of compressed air. Joint shall be made dry, vacuum cleaned and free of dirt, oil, vegetation and other debris. Application of two coats of primer with thin brush by forward and backward movement at an interval of 30 minutes before placing the backup rod and pouring the sealant. Placing of closed cell, medium density, crossed linked polyethylene foam backup rod of 8 mm dia, application of bond breaker tape on top of back up rod for complete width of the joint and filled with polyurethane based sealant complying with BS-5212, BS 4254 and EN-141875-2003 with minimum movement accommodation factor (MAF) of +/- 30% having minimum 10 year performance guarantee, applying masked tape on the edges of joints and removing the masking tape after filling of sealant as per the method specified by the manufacturer complete as specified and directed.

1

-

-

... More
M & L Forming 25 mm width expansion joint in concrete slab for full depth of PQC. Early entry saw and subsequent cutting by using diamond bit cutter of appropriate size, straight and smooth edges. Joint cleaned thoroughly with application of compressed air. Joint shall be made dry, vacuum cleaned and free of dirt, oil, vegetation and other debris. The joint then filled with pre-molded 25 mm thick compressible polyethylene closed cell type filler board as specified, thereafter application of two coats of primer with thin brush by forward and backward movement at an interval of 30 minutes before placing the backup rod and pouriing the sealant. Placing of closed cell, medium density, crossed linked polyethylene foam backup rod of 30 mm dia, over filler board and filled with polyurethane based sealant complying with BS-5212, BS 4254 and EN-141875-2003 with minimum movement accommodation factor (MAF) of +/- 30% having minimum 10 year performance guarantee, applying masked tape on the edges of joints and removing the masking tape after filling of sealant as per the method specified by the manufacturer complete as specified and directed.

1.5

-

-

... More
M & L Cutting of construction joints 25 mm deep and 10 mm wide by early saw cut using diamond bit cutter of appropriate size, straight and smooth edges. Joint cleaned thoroughly with application of compressed air. Joint shall be made dry, vacuum cleaned and free of dirt, oil, vegetation and other debris. Application of two coats of primer with thin brush by forward and backward movement at an interval of 30 minutes before placing the backup rod and pouring the sealant. Placing of closed cell, medium density, crossed linked polyethylene foam backup rod of 12 mm dia, application of bond breaker tape on top of back up rod for complete width of the joint and filled with polyurethane based sealant complying with BS-5212, BS 4254 and EN-141875-2003 with minimum movement accommodation factor (MAF) of +/- 30% having minimum 10 year performance guarantee, applying masked tape on the edges of joints and removing the masking tape after filling of sealant as per the method specified by the manufacturer complete as specified and directed.

5

-

-

... More
M & L 75mm thick plain cement concrete 1:4:8 type D2 (using 40 mm graded crushed stone aggregate) as in sub base to tiles including demolition of existing concrete and removal of debris outside MD land complete all as specified and directed .

80

-

-

... More
M&L Hardcore of gauge not exceeding 63 mm of broken stones or boulders, deposited, spread and levelled in layers not exceeding 15 cm thick, watered and rammed to a true surface complete all as specified and directed.

12

-

-

... More
M&L taking down the cover slab/ welded wire mesh/ steel channels etc of existing covered Rain water pit of size 6 meter dia, cleaning up to depth 7.5 meter removing mud/silt, vegetation growth, plants/small trees etc to ouside MD land, and refix the cover slab after cleaning of pit including repairing of cracks in cement mortar (1:3) where noticed in surface and making good complete all as specified and as directed.

2

-

-

... More
Note for item No 30 :- (a) The work to be executed in highly restricted area.

-

-

-

... More
(b) The unit rate is deemed to be included for removing of the mud/silt obtained from the rain water pit and accumulated earth of any width and depth upto 15 cm cleaning/cutting the grass with hand operated petrol/kerosene driven grass cutting machine and removing the grass waste around 1m from the outer wall of the rain water pit to outside MD land. The periodicity of cutting of grass shall be before commencement of work and after completion of repairs

-

-

-

... More
(c) The unit rate deemed to be considered for First Aid and necessary safety arrangements equipment’s to be provided by the tenderer for workman.

-

-

-

... More
(d) The tenderer shall adhere to time frame as per the user’s requirement and as per demand. The demand and the location of work will be intimated either by the rep of user/ MES rep well in advance. In case of failure to attend the demand in time penalty will be levied for each day @ Rs 500/ for non-completing the requirement till completion of work. The nature of the work related to Airfield maintenance, hence the delay is not acceptable.

-

-

-

... More
M&L in repairs welded steel wire fabric cut to length,bent to shape required and tying with and including annealed mild steel wire not less than 0.9mm dia or fixing with galvanised steel staples supplied and fixed complete to wood or steel members not excceding 4Kg/Sqm complete all as specified and directed.

400

-

-

... More
M & L cutting, removing damage portion of concrete surface in square/ rectangular shape for depth of 20 to 30mm thick, cleaning the surface with wire brush or cloth and removing the dirt including the wetness and dampness by means of dryer and supply and laying geo polymer based "Geo Krete - of Make eco materials or equivalent in Fosroc chemicals/ Tiki Tar/ M/s STP Limited/sika india pvt ltd rapid setting curing free semi levelling structural mortar of single compound activated by water for quick construction & levelled the surface to match with existing surface all as per manufacturer’s instructions as specified & directed. The geopolymer based water impermeable concrete resurfacing mortar shall have compressive strength of 15 M Pa in 2 hours and 50 M Pa in 28 days without any water curing and curing compounds having a water penetration of less than 2 MM when tested as per DIN 1048 and RCPT valve of less than 800 coloumbs when tested as per ASTM C 1202.

15

-

-

... More
Note for Item No 36 :- The tenderer shall take into consideration the following points while quoting rate for above item:-

-

-

-

... More
(a) The rate deemed to be included for making good to disturbed portion around the area where material are applied.

-

-

-

... More
(b) Material shall be procured from the authorised manufacturer only.

-

-

-

... More
(c) The work shall be carried out through authorized and qualified applicators of the manufactor only in presence of departmental rep.

-

-

-

... More
M&L Carrying out skid resistance test (SRT) on flexible and rigid pavement by using british pendulum SRT device and the test shall be carried out in grid pattern of 5m x 5m. The reading shall be taken on dry surface and wet surface condition at each point of surface, five reading shall be taken on each point and average shall be considered. Approximate area is 150000 sqm. Frequency of test shall be decided by air force authorities. Test standard and test procedure are mentioned in airport service manual, to find out the coeffcient of friction of runway before and after the treatment. The report shall be prepared and to be submitted duly recommendation with remedial measures in five copies alongwith photographs.

1

-

-

... More
Note for item No 41:- The T&P like british pendulum SRT device and manpower required to execute above job shall be arranged by the contractor and no extra cost will be paid for the same.

-

-

-

... More
M & L 100mm thick, plain cement concrete (1:2:4), type B-1 (using 20 mm graded mechanically crushed stone aggregates), as in hardstanding including making joints at 3.00 metre intervals and at each corner, the joint shall be filled with mastic filling (to full depth) comprising of one part heated hot blown bitumen 85/25 & two parts heated sand (by volume), surface finished even and smooth without using extra cement, including demolition of existing concrete and removal of debris out of MD land complete all as specified and as directed. Note :- The concrete shall be laid at a stretch not exceeding 3 metre in length and width of joint shall not be more than 12 mm.

70

-

-

... More
M & L remove the existing damaged filled sealing compound including polyethylene rod by raking end using blow lamp and cleaning of expansion/construction/dummy joints of concrete pavement free from dust and applying masking tape on edge of joint to prevent accidental spillage of sealant on top surfaces to give a neat finish to the sealant,provision of polyethethylene backup, rod 25-35mm dia in expansion joint and sealed with 10-12 mm thick polyurethane based sealing compund confirming to BS 5212-1990 or equivalent of approved colour after application of suitable primer and removing the masking tape after the sealant filling etc complete all as specified and as per manufacturers instructions. Note :- The size of the joint is 20 to 30 mm wide for expansion joint.

30

-

-

... More
M & L remove the existing damaged filled sealing compound including polyethylene rod by raking end using blow lamp and cleaning of expansion/construction/dummy joints of concrete pavement free from dust and applying masking tape on edge of joint to prevent accidental spillage of sealant on top surfaces to give a neat finish to the sealant,provision of polyethethylene backup, rod 10-15mm dia in any type of joint and sealed with 10-12 mm thick polyurethane based sealing compund confirming to BS 5212-1990 or equivalent of approved colour after application of suitable primer and removing the masking tape after the sealant filling etc complete all as specified and as per manufacturers instructions. Note :- The size of the joint is 8 to 12 mm wide for any type of joint.

35

-

-

... More
Note for item No 44 & 45 :- (a) The existing sealant compound shall be taken out completely using blow lamp and joint shall be cleaned with wire brush and loose particles dust etc shall be removed by using hand pump before applying primer.

-

-

-

... More
(b) Any spillage of material during filling over the slab shall be removed and cleaned by contractor and any damage accrued to the concrete slab will be made good by the contractor without any extra cost to the department.

-

-

-

... More
M&L Retro Reflective tape in any pattern, shape/number/letters on old existing boards after cleaning including removing of existing letters/tape complete all as specified and directed.

10

-

-

... More
M&L Applying one coat of white wash on walls /concrete pavement surface including preparation of old surfaces all as specified and as directed.

5200

-

-

... More
Note for item No 49 :- White wash shall be carried out two or more times at an interval as required by air force authorities at ORA 05 & 23 END only. Payment of each coat shall be measured and paid seperately.

-

-

-

... More
M&L applying two coats of water based road marking paint such as lines, dashes, arrows, letters, boxes etc on roads, pavements and the like including preparation of surfaces by brushes/ mechanical grinder/sand papers, making surface rough to hold paint exceeding 10 cm wide all as specified and as directed.

50

-

-

... More
M & L applying one coat of water based paint of black colour on runway/taxiway/apron or other airfield markings of any size and length on runway/taxiway/apron or other airfield markings of any size and length including letters and numeral markings with suitable mechanical pavement marking machine, including removal of existing complete painted area and cleaning of the area by means of wire brushes/ mechanically complete and removal and surfaces not exceeding 10 cm wide where directed and all as specified and as directed.

150

-

-

... More
M & L applying two coats of water based paint of yellow/orange colour on runway/taxiway/apron or other airfield markings of any size and length including letters and numeral markings with suitable spray machine , including removal of existing complete luminious paint area and cleaning of the area by means of wire brushes/ mechanically complete and removal where directed and all as specified and as directed.

1500

-

-

... More
Note for item No 51 to 53 :- (i) The cost for using spraying machine including necessary DG Set required to operate machines used for scraping / removal of existing paint deemed to be inclusive in the above quoted rate.

-

-

-

... More
(ii) During weekdays site will be available for approximate 4 to 5 hours due to aircraft movements such as landing/takeoff.

-

-

-

... More
(iii) During weekend days site will be available for 5 to 6 hours. Contractor shall consider the above points while quoting the rate and no extra payment shall be claim by the contractor on account of this.

-

-

-

... More
M&L Filling the pit holes in concrete surfaces of size n exc 15mm in dia and 20mm in deep by using a mixture of quartz sand No 9 -450 parts by weight, Hardner Hy 140-50 parts by weight and araldite GY 257-100 parts by weight to form a hard paste and filling the pit holes after cleaning the dust particles with blower and applying primer coat with epoxy resin of mix with formulation of 100 parts of araldite GYZ 57 and 50 parts of hardner Hy 840 by weight and ramming with hammer to make a uniform surface to match with the existing concrete surfaces all as specified and as directed.

34

-

-

... More
Note for item No 57 :- (a) Contractor shall provide 02 Nos of skilled manpower to execute the job on as required basis all as per directed by Engineer in charge.

-

-

-

... More
(b) A pucca register shall be maintained by the contractor and signature of Engr -in-charge and air force authorities to be obtained daily to authenticate the presence of labourers. payment will be made on day basis. This register will form part of RAR/final bill for making the payment.

-

-

-

... More
(c) The contractor shall adhere to time frame as per the user's requirement and as per demand. The demand and the location of work will be intimated either by rep of User/ MES rep well in advance. Incase of failure to attend the demand in time penalty will be levied @ Rs. 500/- per day for non completing the requirement till completion of work. Note that this penalty is exclusively other than condition 56 of IAFW-2249 and shall be treated as interim condition of the contract.

-

-

-

... More
(d) The nature of work is related to Runway Maintenance. Hence no delay is acceptable.

-

-

-

... More
(e) The decision of the Accepting Officer in this regards shall be final and binding.

-

-

-

... More
M & L Preparing of old black top surfaces by brushing with wire brushes for removing caked mud etc, sweeping with brooms and finally fanning the cleaned surfaces using air blowers to remove all loose dirt etc complete and applying cold Polymer Modified bitumen Emulsion (PME) Rejuvenator by spraying with machine of total liquid PME 1.00 Ltr per sqm (undiluted) for two coats with mineral filler as recommended by manufacturer of PME (after diluting with water), each coat diluted in the ratio 1:1 (PME : Water) and ensure uniform finish of PME on Runway surface. PME shall be applied using mechanically operated pump with compressor and nozzle arrangement at uniform pressure and rate, all as per manufacturer instruction and all as specified and as directed by Engineer-in-charge.

6300

-

-

... More
Note for item No 63 :- The tenderer shall take into consideration for following points while quoting rate for above item:-

-

-

-

... More
(a) Due care shall be taken for friction parameters during application of PME as per ICAO standard and friction test shall be carried out on newly PME applied surface by using continous friction testing machine.

-

-

-

... More
(b) Friction parameters shall be between 0.3-0.6 after application of PME. It will be the responsibility of the tenderer to arrange portable skid resistance Tester (PSTR) and carry out necessary testing as directed without any extra cost to Govt

-

-

-

... More
(c) Material shall be procured from the authorised manufacturer only.

-

-

-

... More
(d) The work shall be carried out through authorized and qualified applicators of the manufacturer only in presence of departmental and user representative.

-

-

-

... More
(e) Two year warranty of material performance and application performance shall be obtained by the tenderer from the authorized manufacturer of PME and the same shall be submitted to GE on completion of work as specified . Warranty includes the fact that the structure will remain water tight and no further cracks will be formed, excluding damage caused by natural calamities. Permeability test (ASTM D 2434) to be conducted on the surface prior and after to application of treatment.

-

-

-

... More
(f) A sum of 2% of the quoted amount shall be retained out of the final bill amount as security deposit and the same shall be released to the contractor after satisfactory expiry of two years performance guarantee period. A performance guarantee certificate for two years also shall be submitted by the tenderer to GE on completion of work as specified.

-

-

-

... More
(g) care shall be taken to fill gaps/cracks up-to 3mm size with mineral filler as per manufacturer's instructions.

-

-

-

... More
(h) Mineral filler (fibrous cum quartz powder) shall be added as per manufacturers instruction.

-

-

-

... More
(i) Any number of trials patches of dimensions 15m x 15m at selected places for application of PME as directed by the GE will be undertaken before commencement of treatment. Qty will be measured and paid under the relevant items of first coat and second coat of PME showing the changes. Friction parameters permeability parameters to ensure Zero porosity penetration of PME after application of both coats and micro textures will be determined through relevant testing method as directed by GE.

-

-

-

... More
(j) Electric supply shall be arranged by the tenderer at its own arrangements and rate is deemed to be inclusive.

-

-

-

... More
(k) The tenderer shall adhere to time frame as per the user's requirement and as per demand. The demand and the location of work will be intimated to the tenderer either by rep of User/ MES rep well in advance. In case of failure to attend the demand in in time, penalty will be levied for each day @ Rs. 1000/-per day for non completing the requirement till completion of work. This penalty is exclusively other than condition 56 of IAFW-2249 and shall be treated as interim condition of the contract.

-

-

-

... More
(l) The decision of the Accepting Officer in this regard shall be final and binding.

-

-

-

... More
(m) The nature of work is related to Flight safety. Hence no delay is acceptable.

-

-

-

... More
(n) minus price adjustment shall be applicable if quantity of PME using less than specified and the rate shall be worked out based on paid voucher and market enquiry.

-

-

-

... More
(o) plus price adjustment shall be not applicable if quantity of PME Applied more than specified as per surface conditon is required.

-

-

-

... More
M & L Preparing of old black top surfaces by brushing with wire brushes for removing caked mud etc, sweeping with brooms and finally fanning the cleaned surface using air blowers to remove all loose dirt etc complete and applying of slurry seal containing cold Polymer Modified Emulsion (PME), fine aggregate, mineral fillers, water and spraying the material (slurry seal) having average thickness of 6 mm as per site condition, should be designed such that the initial setting time should be of 2-3 hours but not more than 4 hours and ensure uniform finish of area complete all as per manufacturer’s instructions and all as specified and as directed by Engineer-in-Charge. The mixing of PME and specially designed filler should be mixed in the ratio 2.5 : 1 (filler : PME) to form slurry and should be done mechanically by high power agitator 90 RPM.

450

-

-

... More
Note for item No 80 :- The tenderer shall take into consideration for following points while quoting rate for above item:-

-

-

-

... More
(a) Due care shall be taken for friction parameters during application of PME as per ICAO standard and friction test shall be carried out on newly PME applied surface by using continous friction testing machine.

-

-

-

... More
(b) Friction parameters shall be between 0.3-0.6 after application of PME. It will be the responsibility of the contractor to arrange portable skid resistance Tester (PSTR) and carry out necessary testing as directed without any extra cost to Govt.

-

-

-

... More
(c) Material shall be procured from the authorised manufacturer only.

-

-

-

... More
(d) The work shall be carried out through authorized and qualified applicators of the manufactor only in presence of departmental and user representative.

-

-

-

... More
(e) Manufacturer should have sucessfully completed the similar work at defence airfield.

-

-

-

... More
(f) Two year warranty of material performance and application performance shall be obtained by the contractor from the authorized manufacturer of PME and the same shall be submitted to GE on completion of work as specified . Warranty includes the fact that the structure will remain water tight and no further cracks will be formed, excluding damage caused by natural calamities. Permeability test (ASTM D 2434) to be conducted on the surface prior and after to application of treatment.

-

-

-

... More
(g) A sum of 2% of the quoted amount shall be retained out of the final bill amount as security deposit and the same shall be released to the contractor after satisfactory expiry of two years performance guarantee period. A performance guarantee certificate for two years shall be submitted by the contractor to GE on completion of work as specified.

-

-

-

... More
(i) Electric supply shall be arranged by the contractor at its own arrangements and rate deemed to be inclusive.

-

-

-

... More
(j) Trial patch of 10 Sqm shall be carried out by the contractor on runway and approval of same to be taken from GE before execution of complete qty.

-

-

-

... More
(k) The contractor shall adhere to time frame as per the user's requirement and as per demand. The demand and the location of work will be intimated to the contractor either by rep of User/ MES rep well in advance. Incase of failure to attend the demand in in time, penalty will be levied for each day @ Rs. 1000/- for non completing the requirement till completion of work. Note that this penalty is exclusively other than condition 56 of IAFW-2249 and shall be treated as interim condition of the contract.

-

-

-

... More
(l) The decision of the Accepting Officer in this regard shall be final and binding.

-

-

-

... More
(j) The nature of work is related to Flight safety. Hence no delay is acceptable.

-

-

-

... More
(k) Minus price adjustmen shall be applicable if quantity of PME using less as specified and shall be work out based on paid voucher and market enquire.

-

-

-

... More
(l) plus price adjustment shall be not applicable if quantity of PME Applied more as specified as per surface conditon is required.

-

-

-

... More
Surface dressing not exc 15 cm deep in soft/loose soil all as specified and as directed.

7000

-

-

... More
M & L Levelling of runway shoulders with grader mechanical machine and rolling of surface with road roller of capacity 8-10 tonne, including removal of boulders and other materials obtained from area and all as specified and directed.

5000

-

-

... More
Note for Item No 97 :- (a) The contractor shall adhere to time frame as per the user's requirment and as per demand. The demand and the location of work will be intimated either by rep of User/ MES rep well in advance.

-

-

-

... More
(b) Incase of failure to attend the demand in time penalty will be levied for each day @ Rs 1000/- for non completing the requirment till completion of work. Note that this penalty is exclusively other than condition 56 of IAFW-2249 and shall be treated as interim condition of the contract.

-

-

-

... More
(c) The decision of Accepting Officer in this regard shall be final & binding.

-

-

-

... More
(d) The nature of work is related to Air Field maintenance. Hence delay is not acceptable.

-

-

-

... More
M & L rolIing and consolidating formation surfaces in cutting/ filling to the required gradient and camber including filling in depression and hollow, watering, leveling etc., complete using tandem vibratory/ power roller exceeding 8 tonne and not exceeding 12 tonne capacity all as specified and as directed.

50

-

-

... More
Note for Item No 102 :- Rolling and consolidation the formation surfaces to the required gradient and camber under optimum moisture conditions to achieve at least 98% of maximum dry density determined using modified proctor density determination method as per relevant IS code.

-

-

-

... More
M & L moorum/red bajri filling including spreading and levelling in layers not exceeding 15 cm thick, spread, levelled and rammed Including watering and rolled to true surfaces with 8 to 12 Ton capacity power roller to achieve compaction of 98% modified proctor density complete all as specified.

25

-

-

... More
Note for Item No 104:- (i) Moorum/red bajri required shall be brought from outside MD land

-

-

-

... More
(ii) Compaction of moorum filling shall be carried out under optimum moisture conditions up to the standard proctor density not less than 98 percent.

-

-

-

... More
(iii) Measurements shall be taken after consolidation earth and 5% deduction shall be made for payments.

-

-

-

... More
M & L Applying one coat of water based road marking paint such as lines, dashes, arrows, letters, boxes etc on roads, pavements and the like including complete removal of existing surfaces by brushes/ mechanical grinder/sand papers, making surface rough to hold paint exceeding 10 cm wide all as specified and as directed using mechanical pavement marking machine including necessary DG Set required to operate the machine. Complete scraping / removal of existing paint deemed to be inclusive in the above quoted rate.

8370

-

-

... More
Note for item No 108 :- (i) The cost for using spraying machine including necessary DG Set required to operate machines used for scraping / removal of existing paint deemed to be inclusive in the above quoted rate.

-

-

-

... More
(ii) During weekdays site will be available for approximate 4 to 5 hours due to aircraft movements such as landing/takeoff.

-

-

-

... More
(iii) During weekend days site will be available for 5 to 6 hours. Contractor shall consider the above points while quoting the rate and no extra payment shall be claim by the contractor on account of this.

-

-

-

... More
M&L Chipping out neatly and cutting of existing loose concrete of crack at Runway/taxi track/Pavement by using saw cutter, Cutting of crack portion shall not be less than 100 mm wide and 25 mm deep and clearing of all loose material with air blower/sand blaster and the portion applying proprietory primer on surface to obtain tack and finally filled by Elastomeric concrete mix shall be prepared as per manufacturer instruction to obtain true surface and finally set the surface with hand tools complete all as specified and directed. Make:-M /s Fosroc Chemicals - Patchroc Chemicals, M/s STP Limited- ShaliPatch.and M/s Choksey Chemicals Pvt Ltd. -Flex 0 patch.

8

-

-

... More
Note for item No 112 :- The tenderer shall take into consideration the following points while quoting rate for above item:-

-

-

-

... More
(a) Providing masking tape at joints/ on edge of cut portion and necessary formwork required if any at spalled joints edge to prevent accidental spillage of concrete on top surfaces to give a neat finish. The quoted rate is deemed to be inclusive of this provision.

-

-

-

... More
(b) The rate is deemed to be included for making good the distrubed portion of joint filling around the area where material are applied.

-

-

-

... More
(c) Material shall be procured from the authorised manufacturer only.

-

-

-

... More
(d) The work shall be carried out through authorized and qualified applicators of the manufacturer only in presence of departmental and user representative.

-

-

-

... More
M&L repairs to runway cracks by using 'RUNPHALT' bitumen tubing/ rope for filling of cracks on the runway width of crack 5mm to 7mm with the help of screw driver pushing it inside the crack then apply direct flame 20-30 second through torch method complete all as per manufacturers instruction and as directed by Engineer-in-Charge. Make:- M/s Srijan System PVT Ltd or equivalent as approved by GE

350

-

-

... More
M&L repairs to runway cracks by using 'RUNPHALT' bitumen tubing/ rope for filling of cracks on the runway width of crack 8mm to 10mm with the help of screw driver pushing it inside the crack then apply direct flame 20-30 second through torch method complete all as per manufacturers instruction and as directed by Engineer-in-Charge Make:- M/s Srijan System PVT Ltd or equivalent as approved by GE

300

-

-

... More
M & L hot applied thermoplastic compound exc 10 CM width and 2.5mm thick (excluding thickness of glass beads ) and providing selecting glass beads @ 250gm per sqm as per IRC-135, finished surface to be levelled uniform and free from streaks and holes including cleaning of surface to remove all loose dirt etc. complete all as specified & directed.

200

-

-

... More
M & L removing grass/vegetation cutting bushes leaves soil or any other waste material debris along the runway sides and surrounding area of Air field of any size in width and depth and removing the debris to a distance exceeding 5 Km outside MD land periphery of the airfield all as specified and directed.

8

-

-

... More
Note for Item no 121:- The tenderer shall take into consider the following points while quoting rates for the above item. (a) Grass cutting shall be used by mechanical earth moving machineries with junbgle jim attachment as and when required and as directed. (b) One skilled jungle jim tractor operator to be provided by the contractor as and when required. (c) POL for jungle jim tractor to be brone by the contractor. (d) For 1 day Min 8 hours to be operated.

-

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.