National Highways And Infrastructure Development Corporation Limited Tender
View complete overview of Meghalaya NHIDCL Tender
National Highways And Infrastructure Development Corporation Limited - NHIDCL Tender
Consultancy Services
Eprocure
Opening Date14 Aug 2018
Closing Date17 Oct 2018
Tender AmountRefer Documents
Costs
EMD
₹ 2,00,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Summary
Nhidcl/meghalaya/western Bypass/dpr/2018
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2018_NHIDC_372579_1Bid Award Id
ViewTender No
NHIDCL/MEGHALAYA/WESTERN BYPASS/DPR/2018Tender Authority
National Highways And Infrastructure Development Corporation Limited ViewPurchaser Address
-Website
http://https://nhidcl.com/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Senior Bridge Engineer
3
-
-
Traffic and Safety Expert
3
-
-
Material cum GeoTechnical Engineer cum Geologist
5
-
-
Senior Survey Engineer
5
-
-
Environment Specialist
2.5
-
-
Quantity Surveyor/Documentation Expert
4.5
-
-
Sub Professional Staff (To be assessed by consultant as per requirement of assignment)
-
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Support Staff (inclusive of per diem allowance)
Note: To be assessed by consultant as per requirement of assignment
-
-
-
Office Manager
8
-
-
Typist
8
-
-
Office Boy
8
-
-
Night Watchman
8
-
-
Transportation (Fixed Costs)
-
-
-
The vehicles hired by the Consultant shall include the cost For rental, drivers, operation, maintenance, repairs, insurance, etc.
8
-
-
Duty Travel to Site (Fixed Costs)
-
-
-
Trips
8
-
-
Office Rent (Fixed Costs) The rent cost includes maintenance, cleaning, repairs, etc.
-
-
-
Office Rent
8
-
-
Office Supplies, Utilities and Communication (Fixed Costs)
-
-
-
Office Supplies
8
-
-
Drafting Supplies
8
-
-
Computer Running Costs
8
-
-
Domestic and International Communication
8
-
-
Office Furniture and Equipment (Rental)
-
-
-
Office Furniture and Equipment
1
-
-
Reports and Document Printing
-
-
-
Monthly Report (3 copies per month)
24
-
-
Inception Report & QAP
3
-
-
Environment and Social Impact Screening Report
4
-
-
Draft Feasibility Report
4
-
-
Final Feasibility Report
6
-
-
Strip Plan with L.A. Reports
6
-
-
Draft LA and Clearances I Report
4
-
-
Final LA and Clearances I Report
4
-
-
Draft Environmental Assessment report& RAP
4
-
-
Final Environmental Assessment report& RAP
6
-
-
Draft Detailed Design Report & Drawings etc. Draft EMP
4
-
-
Draft Bidding Documents
4
-
-
Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings etc. Final EMP
6
-
-
Final Bidding Documents
6
-
-
Draft 3(a) ,3(A) and 3(D)& 3G notification for land acquisition (3 copies each)
9
-
-
LA & Clearances II Report
6
-
-
Survey and Investigation A. Topographical Survey (Fixed Rate)
-
-
-
Topographic Survey including hire charges for equipment (GPS, Total Station, Auto Level etc.) and supply of survey Teams comprising of project survey filed staff etc. inclusive of cost of materials, labourer and construction of BM,(satellite imaginary, aerial photogrammetry if considered necessary) etc. complete
56
-
-
Detailed topographic surveys using mobile/ aerial LiDAR or equivalent technology
56
-
-
Investigation (Fixed cost)(lumpsum)
-
-
-
Road and Bridge Inventory
1
-
-
BBD Test and Pavement Evaluation
1
-
-
Roughness Survey
1
-
-
Axle Load Survey
1
-
-
Material Survey and Investigation
1
-
-
Sub-grade Investigation
1
-
-
Traffic Survey
1
-
-
Socio-economic & Census Survey/Studies
1
-
-
Land Acquisition Studies
1
-
-
Any other investigations/surveys
1
-
-
Sub-Soil Investigation (Boring) (Rate/m)
-
-
-
a) In soil other than hard rock
1500
-
-
b) In hard rock
200
-
-
Estimate of ExpatriateConsultants (Name and position to be filled in below columns by the bidder)
-
-
-
Renumeration of Expatriate Staff including per diem allowances
-
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Moblization and Demoblization- International Airfares (Fixed Costs) (To be filled by bidders in below columns)
-
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Position
1
-
-
Moblization and Demoblization-Inland Travel in Home country (Fixed Costs)
1
-
-
Other Miscellaneous expenses (Like DA, internal travel expenses other incidentals)(Fixed Cost)
1
-
-