National Highways And Infrastructure Development Corporation Limited Tender
View complete overview of Manipur NHIDCL Tender
Costs
EMD
₹ 2,00,000Document Cost
₹ 5,900Tender Fee
Refer Documents
Summary
Nhidcl/manipur/dpr/nh-02/ccpur To Tipaimukh /2023
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2023_NHIDC_755430_1Bid Award Id
ViewTender No
NHIDCL/Manipur/DPR/NH-02/Ccpur to Tipaimukh /2023Tender Authority
National Highways And Infrastructure Development Corporation Limited ViewPurchaser Address
-Website
http://https://nhidcl.com/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Team Leader Cum Senior Highway Engineer (1 no)
9
-
-
Senior Bridge Engineer (1 no)
5
-
-
Highway cum Pavement Engineer (1 no)
5
-
-
Material cum Geotechnical Engineer-Geologist (1 no)
6
-
-
B. OTHER PROFESSIONALS
-
-
-
Senior Survey Engineer
7
-
-
Traffic and Safety expert
4
-
-
Environmental Specialist
3
-
-
Quantity Surveyor / Documentation Expert
6
-
-
Land Acquisition Expert
10
-
-
Utility Expert
4
-
-
Sub-Professional Staff: (To be assessed by Consultant as per requirement of assignment and one sub-professional be a fresh graduate, Minimum 7 to be deployed)
-
-
-
TBN
1
-
-
TBN
1
-
-
TBN
1
-
-
TBN
1
-
-
TBN
1
-
-
TBN
1
-
-
TBN
1
-
-
Support Staff (Fixed Rates)
-
-
-
Office Manager (1 No.)
10
-
-
Typist (1 No.)
10
-
-
Office Boy (1 No.)
10
-
-
Night Watchman (1 No.)
10
-
-
Transportation (Fixed costs)
-
-
-
The vehicles hired by the Consultants shall include the cost for rental, drivers, operation, maintenance, repairs, insurance, etc. for use of consultants (2 Vehicle for 9 months each)
20
-
-
Duty Travel to Site (Fixed Costs)
-
-
-
All Trips
1
-
-
Office Rent (Fixed Costs)
-
-
-
The rent cost includes operation & maintenance, cleaning, repairs, etc for entire duration of services.
10
-
-
Office Supplies, Utilities and Communication (Fixed Costs)
-
-
-
Office Supplies, Drafting Supplies, Computor Running Costs, Domestic and International Communication
10
-
-
Office Furniture and Equipment (Fixed costs)
-
-
-
Office Furniture and Equipment
1
-
-
Reports and Document (Fixed costs)
-
-
-
Monthly Report (3 sets per month) i.e 10*3=30
30
-
-
Inception Report & QAP
3
-
-
Environment and Social Impact Screening Report
4
-
-
Draft Feasibility Report
4
-
-
Final Feasibility Report
6
-
-
Strip Plan with L.A. Reports
6
-
-
Draft LA and Clearances I Report
4
-
-
Final LA and Clearances I Report
4
-
-
Draft Environmental Assessment report & RAP
4
-
-
Final Environmental Assessment report & RAP
6
-
-
Draft Detailed Design Report & Drawings etc.
4
-
-
Draft EMP
4
-
-
Draft Bidding Documents
4
-
-
Final Detailed Project Report with Bill of Quantities, Cost Estimates, Updated Drawings etc.
6
-
-
Final EMP
6
-
-
Final Bidding Documents
6
-
-
Draft 3(a) ,3(A) and 3(D) notification for land acquisition( 3 copies each)
9
-
-
LA & Clearances II Report
6
-
-
Survey and Investigation
-
-
-
A. Topographical Survey (Fixed Rate)
-
-
-
Complete Topographic Survey using mobile/ aerial LiDAR or equivalent/better technology for project approach area including hire charges for equipment and supply of survey teams comprising of project survey filed staff etc. inclusive of cost of materials, labourer, preparation of Drawings and their submission as per contract provision.
1
-
-
B. Investigation (Fixed cost)
-
-
-
All investigations/surveys including Road and Bridge Inventory, FWD Test and Pavement Evaluation, Roughness Survey, Axle Load Survey, Material Survey and Investigation, Sub-grade Investigation, Traffic Survey, Socio-economic & Census Survey/Studies, Land Acquisition Studies, etc.
1
-
-
Schedule B (Item rate costs)
-
-
-
Sub-soil Investigation & Other Works
-
-
-
Sub-Soil Investigation
-
-
-
a) Boring in all type of soils (other than hard rock)
2000
-
-
b) Boring in hard rock
300
-
-
Network Survey and GPR
-
-
-
Net work Survey of the existing Highways as a repository for civil work as per directions from Authority.
1
-
-
GPR Survey for detection of under ground utilities
1
-
-
Cost of supply and fixing Boundary Pillars
-
-
-
Procuring and fixing boundary pillars and its installation, complete in all respect as per IRC:25,1967: Wherever the proposed alignment follows the existing alignment, the boundary pillars shall be fixed at an interval of 200m on either side of proposed Right of Way. Wherever there is a proposal of realignment of the existing Highway and/or construction of New Bypasses, Consultant shall fix boundary pillars along the proposed alignment on the extreme boundary on either side of the project Highway at 50 m interval.
1
-
-
Land Acquisition Team including support staff and logistics/transportation
-
-
-
A. Land acquisition Team including support staff
-
-
-
Ex-Land Revenue Inspector/Officer or equivalent
8
-
-
Ex-Kanoongo/ Girdawar or equivalent
8
-
-
Ex-Patwari or equivalent
8
-
-
Typist
8
-
-
Peon
8
-
-
B. Logistics for Land acquisition Team
-
-
-
Computer including necessary peripherals (2 nos)
8
-
-
Printers (2 nos)
8
-
-
Vehicles (Bolero or equivalent) with
monthly running limit of 4000 km (1 no)
8
-
-
Grand Total (Schedule A+B)
-
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements