Global Tenders on GeM introduced something genuinely new to Indian government procurement: a formal, rules-based channel through which foreign suppliers can compete alongside domestic vendors. The evaluation process that governs how bids are compared, however, works differently from most international tendering environments, and the gaps between expectation and reality tend to show up at the pricing stage, after a bid has already been submitted.

Three evaluation mechanics account for most of these surprises: how and when the exchange rate is applied, what costs are added on top of a foreign bid before it is compared to domestic prices, and why the GT-GTC may not be the governing document for the tender at hand. Getting these right before setting a price is what separates a competitive bid from one that only looks competitive.

Temporal Risk in Currency Conversion and Normalisation

Foreign sellers quote in freely convertible foreign currencies. For price comparison, those quotes convert to INR at the State Bank of India’s selling rate for the relevant currency on the day the bid period closes.

Sellers routinely price their bids days or weeks before the closing date. The rate they are pricing against is not yet fixed. If the currency weakens between the time of pricing and the actual deadline, the INR equivalent of the quoted figure rises, with nothing about the submission itself having changed. In volatile currency periods, this is not a rounding error. It can shift a bid from competitive to uncompetitive without the seller doing anything wrong.

Extensions make this more complex. When a bid period is extended, the rate reference date moves with it to the new closing date. A seller does not keep the benefit of whatever the rate was on the original deadline. The SBI rate on the actual final day is what applies. Sellers who submitted bids early and are not watching the extension calendar can be caught off guard by a rate they never planned for. Pricing with a currency buffer and rechecking the position if an extension is announced are the standard responses.

The Landed Cost Model: From Quoted to Evaluated Price

Getting a foreign bid into INR does not make it directly comparable to a domestic supplier’s quote. Buyers are permitted under the GT-GTC to add costs onto foreign bids before running any comparison, specifically to achieve what the framework calls uniform and equitable price evaluation.

Freight, handling, insurance, customs duties, IGST, and customs clearance charges can all be loaded in GeM Global Tendering. The bid document has to state which of these apply and how they are calculated. In tenders where the full set of applicable levies lands on the foreign bid, the evaluated price can run significantly higher than the quoted price. For goods categories with high import duty and 18% IGST, the gap between the quoted figure and the evaluated figure can reach 30 to 40 per cent.

This is the mistake that catches foreign sellers most often. A company priced to match a domestic supplier at the quoting stage can lose by a wide margin once cost loading is applied. Modelling the evaluated price before finalising the quote, using the methodology the bid document specifies, is the only way to price competitively. If the methodology section is vague or missing, a pre-bid query submitted before the deadline is the mechanism to get clarity. Pricing on an assumption about what will be loaded is an avoidable risk.

Contractual Hierarchy and the Precedence of the ATC

Studying the GT-GTC before bidding means reading the second layer of a four-layer structure. The base layer is the GeM GTC. Above that sits the GT-GTC. Above that are category-level Special Terms and Conditions. At the top is the buyer’s bid-specific Additional Terms and Conditions, the ATC, which overrides the layers below it wherever they conflict.

The ATC can change EMD requirements, performance security structure, delivery terms, payment conditions, and the evaluation methodology. A seller who assumes the GT-GTC defaults carry through unchanged to a specific tender may be pricing against the wrong terms. Every GT bid document has to be read on its own. The GT-GTC is a starting reference, not a substitute for reading the actual tender.

Statutory Compliance: Ownership Thresholds and Disclosure Mandates

Every foreign seller participating in a GT must submit the Beneficial Ownership Declaration under Annexure I. It certifies that the entity is not incorporated in a country sharing a land border with India, is not a subsidiary or agent of such an entity, is not controlled by one, and does not have a beneficial owner from such a country.

The ownership definitions are precise and reach further than a casual read suggests. For companies and LLPs, holding more than 25% of shares, capital, or profits qualifies someone as a beneficial owner, as does the ability to appoint a majority of directors or control management decisions through shareholding, shareholder agreements, or voting arrangements, regardless of ownership percentage. For partnerships, the threshold is 15% of capital or profits. For trusts, the author, the trustee, and any beneficiary with 15% or more interest all fall within scope.

A false declaration terminates every contract on GeM, not just the one in play. The declaration covers transfer of technology too. Licensing or technical collaboration with a restricted country’s entity needs competent authority registration or accurate disclosure. Before the authorised signatory puts their name to Annexure I, the full ownership and control chain, including indirect holdings, needs to be traced against these definitions. Assuming compliance without doing that work is a risk with consequences that extend well beyond any single tender.

FAQs

Q1. The buyer’s bid document does not mention a cost loading methodology. What should a seller do?
A: Raise a pre-bid query before submitting. The GT-GTC requires buyers to specify how costs will be loaded, so the absence of this in the document is something the buyer needs to address. Bidding without that clarity means not knowing what the evaluated price will be. If no answer comes, that is relevant information for the decision on whether to bid at all.

Q2. A seller wants to hedge their currency exposure between bid submission and order placement. Is this allowed?
A: Nothing in the GT-GTC prohibits it, but any hedging arrangement has to be structured in compliance with FEMA and applicable RBI guidelines. Whether specific instruments are available depends on the payment terms in the bid document and the seller’s own jurisdictional constraints. This is a question for legal or financial counsel before any hedge is executed, not after.

Q3. Does the cost loading apply uniformly to all foreign bids in a tender, or can the buyer apply different rates to different sellers?
A: It has to be applied uniformly. The GT-GTC’s requirement for uniform and equitable price comparison means the same methodology applies to all foreign bids in a given tender. If a seller has grounds to believe their bid was treated differently, GeM’s grievance mechanism is the right channel to pursue it.

Q4. A transfer of technology arrangement with a restricted country ended two years ago. Does the declaration need to reflect it?
A: The declaration covers the position at the time of signing, not history. If the arrangement is genuinely terminated with no residual rights, obligations, or control remaining, the current legal position is what matters. But that assessment has to come from the entity’s legal counsel based on the current facts, not from a general assumption that termination clears the slate. The signatory should not sign without that review.

Q5. A product category carries nil basic customs duty. Does this close the gap between the quoted and evaluated prices?
A: It reduces the gap. IGST still applies in most cases unless the specific category has a full exemption. The real answer depends on the HS code and what the current tariff schedule and GST notifications say about that specific product. Category-level assumptions are not reliable here. The applicable rates need to be confirmed against current schedules before any price is finalized.