Andhra University Tender
To know what Andhra Pradesh government has posted about any AP etender, Bidassist helps us to get a one-stop platform where a registered bidder can have access to the details on each and every eprocurement tender. There is no need to provide the details on the AP E-procurement website i.e. https://www.apeprocurement.gov.in as BidAssist helps us find the specific etender we're looking for. BidAassist has collated each and every Eproc Andhra Pradesh Tender on its website.
Andhra University Tender
Civil And Construction
Building Construction
Opening Date31 Oct 2022
Closing Date21 Nov 2022
Tender Amount₹ 15,77,755
Costs
EMD
Refer DocumentsDocument Cost
Refer DocumentsTender Fee
₹ 1,000
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
557769Bid Award Id
ViewTender No
UE/E-PTN(5)/AU/VSP/2022-23Tender Authority
Andhra University ViewPurchaser Address
-Website
http://https://www.andhrauniversity.edu.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Construction of Annex building for soil lab;Vibrated Reinforced cement concrete nominal mix as per table 9 of is 456 using 20 mm size (SS5) hard granite machine crushed graded metal from approved quarry, including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc.., to site and cost of seignior age charges on all materials including centering, shuttering and scaffolding with wooden centering as per the approved shuttering plan, machine mixing, laying concrete, vibrating, lift charges, curing etc.., complete but excluding cost of steel and its fabrication charges for finished item of work for columns up to basement etc complete as directed
1.5
-
17127
Construction of Annex building for soil lab;Vibrated Reinforced cement concrete M30 design mix as per table 9 of is 456 using 20 mm size (SS5) hard granite machine crushed graded metal from approved quarry, including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc.., to site and cost of seignior age charges on all materials including centering, shuttering and scaffolding with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete, vibrating, lift charges, curing etc.., complete but excluding cost of steel and its fabrication charges for finished item of work for plinth beams etc complete as directed
4
-
46384
Construction of Annex building for soil lab;R.R. masonry in cement mortar (1:6) for foundations and basements etc including cost and conveyance of all materials labour etc complete as directed
12
-
47884
Construction of Annex building for soil lab;Fly ash Masonry work in cm (1:6) prop, with fly ash cement solid blocks of size 290 X 225 X 140 mm for manufacturing of fly ash solid blocks using fly ash of 80 kgs, cement of 15 kgs .gypsum of 5 kgs. And stone dust including cost and conveyance of all materials, lab our charges, seignior age charges, scaffolding and curing etc.., complete with a compressive strength not less then 50kg/ Sq cm for 14 CM thick walls in foundations and basements etc complete as directed.
1
-
7454
Construction of Annex building for soil lab;Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations and basement with initial lead in layers not exceeding 15 cm thick, conveyance of water to work site and all operational, incidental, labour charges, hire charges of T& p etc.., complete for finished item of work. (APSS NO.309 & 310)
80
-
3055
Construction of Annex building for soil lab;Vibrated Reinforced cement concrete M30 design mix as per table 9 of is 456 using 20 mm size (SS5) hard granite machine crushed graded metal from approved quarry, including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc.., to site and cost of seignior age charges on all materials including centering, shuttering and scaffolding with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete, vibrating, lift charges, curing etc.., complete but excluding cost of steel and its fabrication charges for finished item of work for columns in ground floor etc complete as directed
3.1
-
35395
Construction of Annex building for soil lab;Vibrated Reinforced cement concrete M30 design mix as per table 9 of is 456 using 20 mm size (SS5) hard granite machine crushed graded metal from approved quarry, including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc.., to site and cost of seignior age charges on all materials including centering, shuttering and scaffolding with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete, vibrating, lift charges, curing etc.., complete but excluding cost of steel and its fabrication charges for finished item of work for lintels in ground floor etc complete as directed
2
-
22480
Construction of Annex building for soil lab;Reinforced cement concrete M30 design mix as per table 9 of is 456 using 20 mm size (SS5) hard granite machine crushed graded metal from approved quarry, including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc.., to site and cost of seignior age charges on all materials including centering, shuttering and scaffolding with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete, vibrating, lift charges, curing etc.., complete but excluding cost of steel and its fabrication charges for finished item of work for sunshades 6.5 cm average thickness in ground floor etc complete as directed
10
-
10256
Construction of Annex building for soil lab;Reinforced cement concrete M30 design mix as per table 9 of is 456 using 20 mm size (SS5) hard granite machine crushed graded metal from approved quarry, including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc.., to site and cost of seignior age charges on all materials including centering, shuttering and scaffolding with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete, vibrating, lift charges, curing etc.., complete but excluding cost of steel and its fabrication charges for finished item of work for beams over 3.66 m up to 4.26 m in ground floor etc complete as directed
3.5
-
35023
Construction of Annex building for soil lab;Reinforced cement concrete M30 design mix as per table 9 of is 456 using 20 mm size (SS5) hard granite machine crushed graded metal from approved quarry, including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc.., to site and cost of seignior age charges on all materials including centering, shuttering and scaffolding with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete, vibrating, lift charges, curing etc.., complete but excluding cost of steel and its fabrication charges for finished item of work for 15 CM thick slab over 3.66 m up to 4.26in ground floor etc complete as directed
80
-
114313
Construction of Annex building for soil lab;Fly ash Masonry work in cm (1:6) prop, with fly ash cement solid blocks of size 290 X 225 X 140 mm for manufacturing of fly ash solid blocks using fly ash of 80 kgs, cement of 15 kgs .gypsum of 5 kgs. And stone dust including cost and conveyance of all materials, lab our charges, seignior age charges, scaffolding and curing etc.., complete with a compressive strength not less then 50kg/ Sq Cm for 23 CM thick walls in ground floor etc complete as directed.
15
-
106206
Construction of Annex building for soil lab;Fly ash Masonry work in cm (1:6) prop, with fly ash cement solid blocks of size 290 X 225 X 140 mm for manufacturing of fly ash solid blocks using fly ash of 80 kgs, cement of 15 kgs .gypsum of 5 kgs. And stone dust including cost and conveyance of all materials, lab our charges, seignior age charges, scaffolding and curing etc.., complete with a compressive strength not less then 50kg/ Sq Cm for 23 CM thick walls above 3.66 m up to 4.26 m in ground floor etc complete as directed.
1
-
7246
Construction of Annex building for soil lab;Supplying and fixing in position country wood doors with 35 mm thick flush shutters with necessary 100x75 mm scantlings for frames and fixed the frame in to the masonry with Z hold fasts six numbers with necessary screws not less than 50 mm length with necessary aluminum furniture 125 mm hinges 6 nos 300x16 mm Aldrop one no ,handles 100 mm, locking arrangements wind appliances etc complete for finished work as directed. (APDSS-1001&1002)
3.7
-
15105
Construction of Annex building for soil lab;Country wood panelled windows with Malasia sal or nallamaddi for frames and kamba for shutter with necessarywind appliances etc complete and fixed in to the masonry with four number Z hold fasts etc complete as directed
13
-
73193
Construction of Annex building for soil lab;Supplying and fixing in position M.S grills at 20 kg/m2 including fabrication cost of welding rods, power charges and fixing in position by screws to the frames etc complete in ground floor
13
-
26367
Construction of Annex building for soil lab;Supplying and fixing position M.S gates with 35 kg /m2 and fixed in to themasonry with necessary clamps etc complete as directed etc complete
5.2
-
18457
Construction of Annex building for soil lab;Cement concrete (1:4:8) mix using 40 mm size hard granite machine crushed metal , including cost and conveyance of materials ,machine mixing of concrete ,placing in position , curing etc complete as directed.APDSS 402
90
-
35757
Construction of Annex building for soil lab;Cement concrete (1:1.5;3) mix using 20 mm and 12.5 mm size hard granite machine crushed metal , including cost and conveyance of materials ,machine mixing of concrete ,placing in position , curing etc complete as directed. APDSS 402
1
-
5502
Construction of Annex building for soil lab;Supplying fitting and placing HYSD bar reinforcement in VRCC works complete including wastage, as per drawings and technical specifications for bars below 36 mm dia including over laps and wastage where they are not welded etc complete as directed in second floor
3200
-
213088
Construction of Annex building for soil lab;Plastering with cement mortar (1:5) 20 mm thick for vertical surfaces including cost and conveyance of all the materials like cement , sand, water etc., to site, including seignior age charges , sales & other taxes on all materials, and all operational , incidental charges on materials and including cost of all labour charges for mixing mortar, finishing ,curing as directed by the engineer-in charge etc complete as directed in ground floor .APDSS 903
10
-
3916
Construction of Annex building for soil lab;Plastering with cement mortar (1:5) 12 mm thick for vertical surfaces including cost and conveyance of all the materials like cement , sand, water etc., to site, including seignior age charges , sales & other taxes on all materials, and all operational , incidental charges on materials and including cost of all labour charges for mixing mortar, finishing ,curing as directed by the engineer-in charge etc complete as directed in ground floor .APDSS 903
165
-
62406
Construction of Annex building for soil lab;Plastering with cement mortar (1:5) 12 mm thick for vertical surfaces including cost and conveyance of all the materials like cement , sand, water etc., to site, including seignior age charges , sales & other taxes on all materials, and all operational , incidental charges on materials and including cost of all labour charges for mixing mortar, finishing ,curing as directed by the engineer-in charge over 3.66 m up to 4.26 m etc complete as directed in ground floor .APDSS 903
6
-
2316
Construction of Annex building for soil lab;Plastering with cement mortar (1:3) 12 mm thick for vertical surfaces including cost and conveyance of all the materials like cement , sand, water etc., to site, including seignior age charges , sales & other taxes on all materials, and all operational , incidental charges on materials and including cost of all labour charges for mixing mortar, finishing ,curing as directed by the engineer-in charge etc complete as directed in ground floor .APDSS 903
30
-
11711
Construction of Annex building for soil lab;Plastering with cement mortar (1:3) 12 mm thick for ceiling surfaces including cost and conveyance of all the materials like cement , sand, water etc., to site, including seignior age charges , sales & other taxes on all materials, and all operational , incidental charges on materials and including cost of all labour charges for mixing mortar, finishing ,curing as directed by the engineer-in charge over 3.66 m up to 4.26 m etc complete as directed in ground floor .APDSS 903
110
-
45626
Construction of Annex building for soil lab;Vibrated Reinforced cement concrete(1:3:6) Nominal Mix as per table 9 of is 456 using 20 mm size (SS5) hard granite machine crushed graded metal from approved quarry, including cost and conveyance of all materials like cement, fine aggregate (sand), coarse aggregate, water etc.., to site and cost of seignior age charges on all materials including centering, shuttering and scaffolding with props and steel plate as per the approved shuttering plan, machine mixing, laying concrete, vibrating, lift charges, curing etc.., complete but excluding cost of steel and its fabrication charges for finished item of work for encasement of columns in first floor with an minimum height of lap length of steel reinforcement etc complete as directed..
1
-
11302
Construction of Annex building for soil lab;Fly ash Masonry work in cm (1:6) prop, with fly ash cement solid blocks of size 290 X 225 X 140 mm for manufacturing of fly ash solid blocks using fly ash of 80 kgs, cement of 15 kgs .gypsum of 5 kgs. And stone dust including cost and conveyance of all materials, lab our charges, seignior age charges, scaffolding and curing etc.., complete with a compressive strength not less then 50kg/ Sq Cm for 23 CM thick walls in first floor etc complete as directed.
4.6
-
35134
Construction of Annex building for soil lab;Plastering with cement mortar (1:3) 12 mm thick for vertical surfaces including cost and conveyance of all the materials like cement , sand, water etc., to site, including seignior age charges , sales & other taxes on all materials, and all operational , incidental charges on materials and including cost of all labour charges for mixing mortar, finishing ,curing as directed by the engineer-in charge etc complete as directed in first floor .APDSS 903
10
-
42858
Construction of Annex building for soil lab;Plastering with cement mortar (1:5) 12 mm thick for vertical surfaces including cost and conveyance of all the materials like cement , sand, water etc., to site, including seignior age charges , sales & other taxes on all materials, and all operational , incidental charges on materials and including cost of all labour charges for mixing mortar, finishing ,curing as directed by the engineer-in charge etc complete as directed in first floor .APDSS 903
50
-
20823
Construction of Annex building for soil lab;Flooring with vitrified tiles , 1st quality 600mmx600mm and thickness at 8mm to 10 mm and size approved by the engineer- in charge, set over base coat of cement mortar (1:8) , 12 mm thick over CC bed already laid or RCC roof slab , including neat cement slurry of honey like consistency spread @3.3 kgs/m2 & jointed neatly with white cement paste to full depth mixed with pigment of matching shade, including cost of all materials like cement , sand , water etc complete including seignior age charges etc., complete for finished item of work in ground floor usinfg Rak and Khazaria (APSS NO 701 & 707)
75
-
96231
Construction of Annex building for soil lab;Painting with enamel paint to wood work two coats over one coat of wood primer paint etc.with best approved colour and brand after scraping the surfaces etc complete as directed
50
-
9864
Construction of Annex building for soil lab;Painting with enamel paint two coats over one coat of zinc oxide primer for iron work with best approved colour and brand after scraping the surfaces etc complete as directed
30
-
5710
Construction of Annex building for soil lab;Plastic emulsion Painting to new walls with 2 coats of paint of approved brand shade over a basecoat of approved cement primer grade I making 3 coats to interior and exterior surfaces to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materiel, including cost and conveyance of all materials to work site and all operational, incidental, labour charges etc complete for finished items of work as per SS 912 for internal walls for finished item of work etc complete as directed.
400
-
77901
Construction of Annex building for soil lab;Providing Anti termite treatment as per IS 6315(part-2) 2001 (pre-constructional chemical treatment measures) along the internal & external vertical faces of the columns, plinth beams, basement and top surface of the basement filling below flooring bed as per the specified procedure conforming to IS 6315 (part-2) 2001 and other relevant approved specification duly using chlorpyriphos/ lindane emulsifiable concrete 20% with 1% concentration @ 7.5 liters/sqm of the vertical surface & @ 5.0 liters/sqm of the horizontal surface of the substructure to a depth of 500 mm around columns & 300 mm deep around plinth beams, basements & floor filling area including excavation channel along the wall & rodding etc & cost & conveyance of all materials to the site, cost of labour for spraying, rodding etc complete for item of work as per the approval of the engineer-in-charge
80
-
13634
Construction of Annex building for soil lab;Providing impervious coat to exposed RCC slab surfaces to required slopes with CM(1:3)prop 20 mm thick(average) mixing with water proof compound from reputed manufactures as approved by the engineer at 1 kg for one bag of cement laid over roof slab finished smooth with a floating coat of neat cement and thread lining at regular intervals at 45cmx45cm including cost and conveyance of materials like cement, sand (screened) water proofing compound to site cost of seigniorage and all other taxes on all materials and operational ,incidental and labour charges for mixing mortar ,laying ,lifting, rendering smooth and thread lining ,cutting including rounding off junctions of wall and slab etc complete for finished item of work over ground floor slab. (APSS No.901&903)
80
-
42855
Construction of Annex building for soil lab;Supplying and fixing in positions in 100 mm dia PVC pipe Prince or Sudhakar make with 4 kg/Sq Cm etc complete as directed
20
-
5561
Construction of Annex building for soil lab;Supplying and fixing in position 100 dia PVC door bends Prince or Sudhakar make etc complete as directed
4
-
414
Construction of Annex building for soil lab;Removal of AC sheet roofing with necessary purlins etc complete and clearing awaythe materials etc completes directed
84
-
7266
Construction of Annex building for soil lab;Removal of damaged mesh and clearing away the materials etc complete as directed
35
-
3123
Construction of Annex building for soil lab;Dismantling of brick masonry and clearing away the materials etc complete as directed APDSS No 202
3.5
-
1048
Construction of Annex building for soil lab;Mazdoors engaged for removal of equipment etc
4
-
2927
Construction of Annex building for soil lab;Making grooves including surface cleaning removal of dust etc complete as directed
20
-
1750
Construction of Annex building for soil lab;Providing granolithic concrete flooring 20 mm thick with C:C (1:1:2) Proportion using 6 mm to 12 mm size hard granite machine crushed metal laid monolithically over existing bed of P.C.C including cost and conveyance of all materials to site, Labour charges like mixing of cement concrete, Laying, using lift charges etc complete.
20
-
8351