West Bengal Transport Corporation Limited Tender
Search from over 10,000+ business opportunities that have been announced from the biggest West Bengal tenders, e tender West Bengal, WB government tenders, and the Online Tender Notices posted on West Bengal e tenders to date. Find opportunities that have come in from multiple corporations, West Bengal government departments, State PSUs, and several Private companies from the state.
West Bengal Transport Corporation Limited - WBTCL Tender
Civil And Construction
Building Construction
Eprocure
Opening Date11 Nov 2024
Closing Date2 Dec 2024
Tender Amount₹ 2,00,000
Costs
EMD
₹ 4,000Document Cost
₹ 1,000Tender Fee
Refer Documents
Summary
Wbtc/jmd/nit- 534/2024-25 (2nd Call)
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_CTC_767951_1Tender No
WBTC/JMD/NIT- 534/2024-25 (2nd call)Tender Authority
West Bengal Transport Corporation Limited ViewPurchaser Address
-Website
http://http://calcuttatramways.com/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Cleaning of moss, mud from the surface of the roof/shed at any height as per specific direction of Engineer-in-charge and removing the same beyond the compound and cleaning the site in all respect.
1
8
8
Making scaffolding without staging, including hire charge of bamboo, Ballah etc. and all materials required suitable to undertake the jobs for which scaffolding is being made and when will be directed by the Engineer-in-charge.
-
-
-
a) Upto 3.0 M height
1
18
18
b) Above 6.0 m upto 10.0 M
1
24
24
c) Above 10.0 m
1
30
30
Making scaffolding with staging intermediately as will be required, suitable to undertake the job for which the scaffolding with staging is being made including hire charge of bamboo, Ballah and all staging materials etc. planks, G. I. sheets etc. required dismantling of scaffolding as and when will be directed by the Engineer-in-charge.
-
-
-
a) Upto 6.0 M height
1
25
25
b) Above 6.0 m upto 10.0 M
1
30
30
c) Above 10.0 m
1
39
39
Supplying tarpaulin of approved making and fitting, fixing the same for covering the opening the verandah, door, windows etc. as per requirement, design and direction of engineer-in-charge fitted complete in frame work with bolts, hooks etc. including supply of cord pulley block, stiffening the canvas as per requirements and mending good damages.
1
231
231
M. S. works in frame for umbrella made of round or square bars and frame work of M. S. Flat with the bars properly fixed to the flat bar frame work by welding etc. with or without flat bar stiffener and fixed with necessary screws etc. and supplying 1.5 mm thick m. S. sheet fitted and fixed on face of umbrella frame work with point welding at not more than 150mm apart complete in all respect as per decision and drawing and direction of Engineer-in-charge including cost of all labours, materials, tools and plants as required.
1
14000
14000
Hire charges of welding sets along with welder and helper as per direction of Engineer-in-charge including cost of all tools and plants require for such welding works but excluding the cost of materials.
1
1500
1500
Supply of electric for welding works.
1
5
5.5
Supply fitting and fixing 16 mm Fan hook after cutting concrete if required including mending good damages as per direction of engineer-in-charge.
1
56
56
Taking out carefully existing broken glass panes from roof shed sky light opening at any height (including necessary scaffolding)and fixing the same in position as directed, supplying putty and rails as necessary stacking the scrap materials as directed.
1
55
55
Supplying canvas of approved make and fittings, fixing the same for covering the opening and direction of Engineer-in-charge fitted complete in frame work with bolts, hooks etc. including supply of cord, pulley, block. Stitching the canvas as per requirements and mending good damages.
1
55
55
Labour for laying departmentally supplied Tarfelt and cold adhesive on roof (concrete or sheeted slopped etc.) making proper slope as per direction of Engineer-in-charge.
1
40
40
Labour for chilchaling the heap zones by cutting and leveling the existing surface to smooth grade and camber as per direction of Engineer-in-charge and removing the same within a lead of 75 M as directed.
1
9
9
Labour for stone-set pavements with joints set close in cement mortar (4:1) excluding the cost of stone-sets but including the cost of carriage thereof within a lead of 150 M. when lead with 12mm thick. Cement mortar (4:1) on the under bed. (including cost thereof) 125mm / 100mm thick pavement. stone set to be supplied by department.
1
209
209
Labour for taking out stone-sets (size 280 X 125 X 100 mm) from damaged pavement (in cement mortar) removing mortar from surface of the stone-sets and stacking the stone-sets as directed within a lead of 75 M.
1
3
3.5
Taking out carefully existing broken glass pens from wooden/
steel window at any height and stacking the scrap properly as directed excluding scaffolding / staging.
1
15
15
Hire charges of gas cutter sets transportation of the same to and fro, including supply of oxyacetylene gas and all tools and plants required for cutting M. S. structural frame etc. and as per direction of Engineer-in-charge.
1
1800
1800
Supply of Sika Latex.
1
360
360
Supplying, fitting, fixing Aluminium sheet having 1.00 mm thickness (20 g) of approved quality.
1
433
433.63
Labour for M. S. structural works in roof trusses etc. with departmentally applied simple rolled structural members ( channel, joist, angles, tees, flats, tubes etc.) connected to one another with gusset plate, cleats, riveted, bolted or welded etc. as per design or direction, complete including fabrication, hoisting and erection with supply of nuts, bolts, jointing materials, carriage, tools and plants complete as directed.
1
1800
1800
Supply of Iron dust of approved quality.
1
42
42
Making valley / eves gutter by departmentally supplied sheets (G. I. / C. R. upto 20 Kg.) to proper shape to match with existing one.
1
75
75
Renewing by supplying fitting and fixing galvanized Iron sheet valley gutter made of 20 Kg sheet with perimeter 0.91 approx. and with 2.25 mm lap each way including upplying of necessary bolts, nuts etc. complete as directed.
1
1445
1445
Labour for Roof Shed cleaning.
1
12
12
Labour for chipping of floor.
1
16
16
Applying of monasur (cold adhesive) on roof for crack seating and stopping leakage and sand spreading over it by supplying sand
1
15
15
Labour charges for taking out old damaged tarfelt from G.C.I. sheet roof or R.C.C. roof slab at any height including removal of the same within the 75m. distances from job site
1
15
15
Supplying, Fitting & Fixing 20 mm thick Buggus Board made with bituminous materials.
1
45
45.79
Clearing the Marble Floor applying Acid, cutting with hand grinder machine, sealing the joint properly with white cement, finishing the top surface wing acid/wax complete in all respect as per direction of Engineer-in-charge at site.
1
57
57.94
Covering the office furniture like chair, table, almirah, rack and other utility, office documents etc. with polythene sheet before starting the painting works on ceiling and walls, removing the same after completion of works, cleaning all furnitures dust free as per direction of Engineer-in-charge at site.
1
24
24
Hire charges for J.C.B., provision to be made with boom & bucket only at both side including supply of fuel etc., operator, 8 hours continuous duty to be done as per instruction of Engineer-in-charge at site.
1
7200
7200
Supplying, fitting and fixing of glow shine board on wall as specified below, made with the following materials :
I. G.I. plain sheet (0.5 mm thick) work at the four end side and back side II. 3 mm thick polyvinyl sheet.
III. Internal electrical wiring including providing 3 nos. tube fittings of 1.20m length with necessary chockes, starters etc. complete in all respects.
IV. Transportation charges of glow shine board from factory to job site including loading / unloading etc.
V. Cost of fitting charges on wall with M.S. clamps, brackets, etc. as directed by Engineer-in-charge at site. VI. Electrical connection made with aluminum cable 2 core 4 mm2 from nearest power point to board as available within job site. VII. Timer.
1
6843
6843.36
Barricading with old G.C.I. sheet and bamboo frame structure, G.C.I. Sheet to be supplied by department and bamboo to be supplied by Contractor, bamboo spacing vertically 1.2 m apart and also horizontally 1.2 m apart, nailing properly at each intersection point. G.C.I. sheet to be fixed with screw, complete as per direction of Engineer-in-charge at site.
1
320
320
Fabrication & Erection of MS net with 6 mm dia plain rod @ 50 mm c/c spacing in both ways, frame work to be made with 19 mm X 6 mm size. MS Flat in Four sides. 19 mm X 6 mm size MS Flat stiffner to be provided @ 1.00 m spacing in both direction, continous welding to be made in every intersection point, logs and wall clamp to be provided as per direction of Engineer-in-charge at site complete in all respect.
1
1254
1254
Hire charges for Hydra/Crane, provision to be made with boom & bucket only at both side including supply of fuel etc., operator, 8 hours continuous duty to be done as per instruction of Engineer-in-charge at site.
1
8500
8500
Special Note to Tenderer : THE "PERCENTAGE EXCESS" OR "AT PAR" OR "PERCENTAGE LESS" as will be quoted by the tenderer for Part B schedule will be automatically applied for Part A schedule (PC Schedule) also.
-
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements
Past BiddersThis list is curated from the bidders of the similar tenders in the past
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%