Public Health Engineering Department Tender
Search from over 10,000+ business opportunities that have been announced from the biggest West Bengal tenders, e tender West Bengal, WB government tenders, and the Online Tender Notices posted on West Bengal e tenders to date. Find opportunities that have come in from multiple corporations, West Bengal government departments, State PSUs, and several Private companies from the state.
Public Health Engineering Department - PHED Tender
Civil And Construction
Pipe Line Project
Eprocure
Opening Date15 Feb 2024
Closing Date4 Mar 2024
Tender Amount₹ 45,63,678
Costs
EMD
₹ 91,274Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_PHED_667387_2Bid Award Id
ViewTender No
WBPHE_69_ND_23_24_GR_I_TO_IIITender Authority
Public Health Engineering Department ViewPurchaser Address
-Website
http://https://wbphed.gov.in/en/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Earth work in filling in compound, tank, low land, ditches etc. with good earth, in layers not exceeding 150 mm. including breaking clods and consolidating
the same by ramming and dressing complete. (Payment will be made on profile measurement before and after the work)With carried earth arranged by the contractor within a radius exceeding 3 km. but not exceeding 5 km. including the cost of carried earth.
500
209790
419.58
... More
Supplying, laying, fiting, fixing and jointing of UPVC pipes conforming to IS:4985-2000 with latest revision and amendments, if any, with necessary UPVC/CI specials, CIDF sluice valves, as per relevant I.S. specification including labour charges for earth work in excavation in any kind of soil including mixed soil with boulder ,road sub-grade and its flanks but excluding moorum and laterite or sand stonehard arock including cutting of brick payment without damaging the existing telephone/electrical cable line etc.(in case of damage of any type of cable line during excavation, necessary damaged charges as applicable by the respaective authority will be borne by the agency in his own cost.
Loading, unloading, carrying of pipes, specials, valves from the local store to work site and lowering laying of pipes specials valves carefully in trenches maintaining proper levels and alignment, jointing the pipe and specials including supplying of good quality/approved brand solvent cement (as per IS:14182-1994 including cost of all fabricated PVC fitting i.e. tees,bend, reducers, adopter etc.as per IS:101-1988 and making flange joints including supplying required quantity of nuts, bolts and rubber insertion (CIDF sluice valves will be supplied by the department free of cost) as required at site by adopting suitable method so as to facilate the maintenance of pipe line locally as per conventional method including back filling the trenches with good earth obtained from excavation of trenches including consolidation with watering in layer not exceeding 150mm thk. with maintaining an average depth of cushion of 1.10mtr. from the top of pipe line including making interconnection with distribution pipes etc. all complete as per drawing direction and satisfaction of the E.I.C. (A) Pressure Rating : Class-III (ii) Laying of pipe line including cost of pipe & fittings/specials but excluding cost of valves. For UPVC pipe
-
-
-
... More
75 mm(OD)
7500
1935000
258
... More
90 mm (OD)
1500
513000
342
... More
Filling the pipe line with water, testing hydraulically as per I.S 3114-1965 (Article-6) in section of a length not exceeding 500mtr. for head of pressure as per specification including supplying installing and fixing all equipments such as diesel pump set, blank flange, pressure gauge, valve, pressure pump and all other tools and plants including drilling topping and plugging of necessary holes to pipes, blocking ends providing temporary thrust block and subsequent blocking of holes and other jointing materials and dismantling and removal of the same including disposal of water etc. all complete as per specification and direction of EIC. The rate is inclusive of cost of requisite water to be arranged by the contractor (Recovery rate of water @ Rs.10.00/m3 , if contractor used water from deptt. source).
-
-
-
... More
75 mm(OD)
7500
23625
3.15
... More
90 mm(OD)
1500
5400
3.6
... More
Cleaning thoroughly the inner surface of pipe line including specials and valves by flushing with water and subsequently disinfection of the same pipe line by flushing again with water containing bleaching powder resulting in residual chlorine not less than 15mg/ltrs. after 24hrs. of such filling including laboratory testing of water samples obtain from the disinfested pipe line and disposal of water from the pipe line after completion of the work. The rates including of cost of requisite water to be arranged by the contractor) (The rate of water @Rs. 10/m3 may be recovered, if the contractor used water from deptt. source).
-
-
-
... More
75 mm(OD)
7500
5175
0.69
... More
90 mm(OD)
1500
1320
0.88
... More
(A) Filling in foundation or plinth by fine sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity)
a) Do- by fine sand
100
95183
951.83
... More
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes. Pakur variety. (Ref: p-24, it-4a PWD SOR) 3rd Corrigenda
45
252522
5611.62
... More
Close Bamboo Walling made of 65mm to 75mm dia. bamboos (in single line) driven about half-length into the ground side by side, with stout stays at an interval of 1m, 3nos. of half split bamboo runner of same dia fitted and fixed with nails etc. complete as per direction. (Measurement to be taken along the length of piling after finishing the works).
with bamboos of length upto 2.00m
800
358400
448
... More
Add GST @ 18.0%
1
689261
689261.61
... More
Add cess @ 1.0 %
1
45184
45184.93