Search from over 10,000+ business opportunities that have been announced from the biggest West Bengal tenders, e tender West Bengal, WB government tenders, and the Online Tender Notices posted on West Bengal e tenders to date. Find opportunities that have come in from multiple corporations, West Bengal government departments, State PSUs, and several Private companies from the state.

Kolkata Metropolitan Development Authority - KMDA Tender

Works
Civil And Construction
Bridge Construction
Eprocure
Opening Date28 Oct 2024
Closing Date18 Nov 2024
Tender Amount₹ 3,99,98,125 
Notes
Download

Costs

Summary

08/se/c-ii/r B/kmda/ W-28 (part-vii) Of 2024-2025 (2nd Call) Date -23/10/2024

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
CONSTRUCTION OF STEEL-RCC COMPOSITE BRIDGE OF 22M LENGTH, 5.5 M CARRIAGEWAY WIDTH WITH BOTH SIDE FOOTPATH IN PLACE OF DAMAGED WOODEN BRIDGE OVER TOWN HEAD CANAL AT MIR MEHER ALI LANE AT WARD NO.57 OF KMC, PS- TANGRA.
OTHER TENDER DOCUMENTS
Report Missing Document

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Supplying Eucalyptus bullah piles at work site,including dressing and making one end pointed. 200.00 mm. av. Diameter

12728

305

3882040

... More
Coal tarring on wooden surfaces including cost of materials(a) Double coat.

8465.44

36

304755.84

... More
Supplying +Eucalyptus bullah piles at work site,including dressing and making one end pointed. i) 100.00 mm. av. Diameter runner

1504

96

144384

... More
Labour for driving Sal-bullah / Eucalyptus bullah piles by monkey in sorts of soil including hoisting and placing piles in position, protecting the pile head with iron ring and cutting and shaping heads before and after driving and including hire and labour for necessary driving appliances and all tackles. i) Bullah of diameter 200.00 mm

9780

119

1163820

... More
Labour for fitting and fixing 10 cm. to 13 cm. diameter Sal-bullah/Eucalyptus-bullah as ties and runners including necessary nails, bolts and nuts.

604

20

12442.4

... More
Taking out Sal-bullah / Eucalyptus piles from river bed or from elsewhere including carrying stacking materials in the nearest stack yard.Above 17.5 cm. and up to 25 cm. diameter

2280

14

32148

... More
Walling or roofing fitted and fixed complete with cut drum sheets including the cost of drums, cost of cutting drums and flattening the sheets and cost of necessary nails and screws.

681

348

236988

... More
Supplying empty Cement bags in good condition.

27143

3

89571.9

... More
Filling empty Cement bags with dry earth or sand, stitching the bag (cost of thread included) and carrying and placing them in position and all incidental charges complete but excluding cost of sand and gunny bags.

27143

3

95000.5

... More
Bailing out water by pump including all leads and lifts and including making all arrangements for disposal, where continuous flow or seepage of water is encountered and rating of pumps and hours of operation is specifically ascertained as per direction of the Engineer-in-charge.

14400

23

331200

... More
Hire and labour charges for staging with sal bullah for super structure of bridge (Major and Minor) including stripping off and removing clearing on completion of work as per design and drawing approved by the Engineer-in-charge.(For painting of bottom of concrete deck and temporary passage of local people during work)

3409.42

199

678474.58

... More
Earthwork in re-excavation / silt clearance in drainage channel in all kinds of soil including sludge, slush mixed with all sorts of industrial wastes and municipal garbages, polypacks, carcasses, small khatal effluents, night soil etc. by mathor labour as may be necessary and depositing the same in places as directed by the Engineer-in-charge , in such a manner, without causing much hindrance to traffic and posing health hazard and making arrangement to maintain the site in workable condition and rough dressing when dry including making arrangement of bailing out of any seepage water and removal of sand or soil blown from underneath, removal of khatal, temporary latrines, clearing and removing all kinds of semi compact masses formed by water hyacinth, jungles up to 30 cm girth, and burning them to ashes or removing outside Government land in conformity with the Municipal rules, including shoring shuttering as required, nicking out lines etc. (Measurement : Pre-work and Post-work level section. Pre- work section to be taken after removal of water hyacinth and all other floating materials etc.) (a) By manual means within an initial lead of 30 M and an initial lift of 1.50 M

600

146

87600

... More
Excavation for Structures. Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed and including trimming the sides of the trenches, leveling, dressing and ramming the bottom, and backfilling with approved material complete as per direction of the Engineer-in-Charge. I. In all sorts of soil excluding marshy soil & rocks (soft or hard) (II)by mechanical means. i) upto 3 m depth (ii) With pumping out water

120

47

5640

... More
Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand.

274.33

361

99033.13

... More
Fine Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free from earth in layers not exceeding 15 cm. including inundating each layer by profuse water and poking and ramming layer by layer complete including supply of sand. Quality of sand is to be approved by the Engineer-in-charge.

826.21

1381

1141301.71

... More
Providing Steel liner for Curbs and 8 mm thick for Steining of Wells including fabricating and settingout as per detailed drawing.

14.21

56954

809322.02

... More
Providing Bored Cast-in-situ R.C.C. pile in position as per specifications in all kinds of soil including cost of boring using drilling mud to stabilize the bore and flushing the bore of excess mud with freshly prepared drilling fluid by using pumps prior to placing concrete by tremie pipe in one continuous operation and including the cost of all materials and labour for placing of concrete and also including the cost of mobilization and hire charges of all equipment necessary for boring, welding of reinforcement cage as necessary and lowering of reinforcement cage, preparation and placing of concrete, including the cost of including the cost of concrete but excluding the cost of reinforcement and labour for bending binding etc. complete as per Drawing and Technical Specifications and removal of excavated earth with all lifts and lead upto 1000 m. Work to be executed as per IS: 2911 (Part II Sec 2). (b) Using Hydraulic piling rig, i) Pile diameter - 1000 mm.(ANALYSED)M35 concrete The rate is inclusive of cost of concrete for the length of pile above cut off level (dummy length) and cost of dismantling the same.

360

9750

3510241.2

... More
Integrity testing of Pile using Low Strain / Sonic Integrity Test / Sonic Echo Test method in accordance with IS 14893 including surface preparation of pile top by removing soil, mud, dust & chipping lean concrete lumps etc. and use of computerized equipment and high skill trained personal for conducting the test & submission of results, all complete as per direction of Engineer-incharge. a) Within 50 km. radius from Raj-Bhavan

12

696

8358

... More
Performing Vertical load test on single Pile in accordance with IS:2911(Part-IV) by hydraulic jacks on pile/piles with 1.5 times the design load including preparation of the head of piles with concrete of required strength for receiving the jacks with all ancillary arrangements for setting up gauges, construction of suitable platforms, keeping the loads and dismantling and removing all arrangement etc. complete as per IS specification and direction of Engineer-in-charge Testing load between 150 T and 200 T.

2

89600

179200

... More
Providing and laying Design Mix concrete for plain / reinforced concrete work in any part of bridge (excluding bottom plugging) with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete but excluding cost of labour and materials for formwork & reinforcement works. (a) M-15 Grade. Using concrete mixer.

27.92

4809

134267.84

... More
Cement Concrete for Reinforced Concrete in Pile Cap complete as per drawing and Technical Specification. (i) RCC Grade M35 I) With Batching Plant, Transit Mixer and Concrete Pump

174.42

5907

1030394.87

... More
Plain / Reinforced Cement Concrete in Substructure with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality, cement and water reducing admixtures, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete as per drawing and technical specification including the cost of necessary form work and staging complete as per drawing and technical specifications. RCC Grade M35 (i) Height upto 5m II) With Batching Plant, Transit Mixer and Concrete Pump(ANALYSED)

120.55

6163

743015.95

... More
Furnishing and Placing Reinforced / Pre-stressed Cement concrete in Super-structure with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality and cement and admixtures, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete as per drawing and technical specification including the cost of necessary form work and staging complete. as per drawing and technical specifications. RCC Grade M40 II) With Batching Plant, Transit Mixer and Concrete Pump (i) Height upto 5m (ANALYSED)

76.72

7074

542772.52

... More
Plain / Reinforced Cement Concrete in Substructure with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality, cement and water reducing admixtures, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete as per drawing and technical specification including the cost of necessary form work and staging complete as per drawing and technical specifications. RCC Grade M30 (i) Height upto 5m II) With Batching Plant, Transit Mixer and Concrete Pump (ANALYSED)

20.83

6039

125800.29

... More
Supplying, fitting and placing un-coated HYSD bar reinforcement in Bridge Foundation including initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of black annealed wire and cost of loading, unloading, carriage of all steel materials complete as per drawing and technical specifications and direction of Engineer-in-charge. (ANALYSED)1.5% concrete volume of pile

51.14

60201

3078728.75

... More
Supplying, fitting and placing HYSD bar reinforcement in Sub-structure including initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of black annealed wire and cost of loading, unloading, carriage of all steel materials complete as per drawing and technical specifications and direction of Engineer-in charge. (ANALYSED)

23.66

60334

1427525.39

... More
Supplying, fitting and placing HYSD bar reinforcement in Bridge Super-structure including initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of black annealed wire and cost of loading, unloading, carriage of all steel materials complete as per drawing and technical specifications.(ANALYSED)

15.06

61252

922469.73

... More
a) Supplying transporting & fabrication of welded steel girder as per approved drawing duly made up built up sections of High Tensile Plate(E350), MS Angle, Channel of different thickness including metalizing priming coat followed by finish coat of paints of total thickness of 165μm. The rate shall be inclusive of supply of all the steels, labour consumables & machinery and all other materials & accessories required for fabrication to complete in all respect with all lead, lift etc. The rate is also includes ( i) Cost of to and fro transportation between contractor's work shop & work site including all lead, lift, loading, unloading etc. (ii) Cost of inspection, testing of girders in stages by nominated inspection agency. Nomination of inspection agency for passing of fabricated members and trial assembly will be decided by Engineer-in-Charge. (iii) Cost of supplying & fixing of HSFG High strength bolts (not less than 10.9 grade). (iv) Cost of blast-cleaning the steel surface including supplying & applying of zinc phosphate primer followed by finish coat of micaceous iron oxide pigmented drying oil type paint of total thickness of 165μm. b)Assembling, erection I launching of fabricated steel girders in proper position, line, level, alignment including erection of staging and scaffolding, dismantling the same after completion of work. The rate shall be inclusive all complete in all respect with all materials, labour, tools & plants, lead and lift. This item pertains to erection of girders by contractor's own cranes I derricks staging, machineries, plants & equipment etc., wherever required to complete the job, as per approved drawing. The rate is inclusive of all stand by cranes, equipment, machineries etc. as directed by Engineer-in-charge to complete the work. In super structure(ANALYSED)

70

140755

9852858.4

... More
Supplying, fitting and fixing in position true to line and level POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface, complete assembly to be of cast steel/fabricated structural steel, metal and elastomer elements to be as per IRC: 83 part-I & II respectively and other parts conforming to BS: 5400, section 9.1 & 9.2 and clause 2006 of MoRT&H Specifications complete as per drawing and approved technical specifications.For max. Horizontal force within 25% of the max. Vertical load.

1280

339

433920

... More
Strip Seal Expansion Joint, Providing and laying of a strip seal expansion joint catering to maximum horizontal movement upto 80 mm, complete as per approved drawings and standard specifications to be installed by the manufacturer/ supplier or their authorised representative ensuring compliance to the manufacturer's instructions for installation.

17.8

10000

178000

... More
Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with reinforced cement concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer-in-Charge, all as specified. M40 grade concrete(analysed rate)

56.2

3788

212932.81

... More
Drainage Spouts in Superstructure including providing drip mouldings and also including supplying, fitting and fixing approved type of materials complete as per drawing and Technical specification vide clause no. 2705 of MoRT&H’s Specification for Road & Bridge Works.

6

783

4698

... More
First class Brick work in cement sand mortar in steining of well, pier, abutment, wing wall, parapets cross drain. H.P. culverts, guard wall etc. including curing, scaffolding, raking out joints etc. complete including cost and carriage of all materials. a) In 1:4 proportion.

25.57

5542

141733.49

... More
Plaster (to wall, floor, ceiling etc.) with composite mortar of sand, lime and cement including round off or chamfering corners as directed and raking out joints and roughening of concrete surface including throating, nosing and drip course where necessary. (i) With 1:4 cement mortar (a) 20 mm thick plaster

330

194

64020

... More
Anti Carbonation coating for protection of Concrete surface from Carbonationby with two coats 0f Single component solvent free, cold applied, pure acrylicpolymer, (Anticarbonotion coatfng) breathable,elastomeric on a water based priming coat (Total 3 (three} coats Including priming coats) having 50% elongation property, UV resistant capacity, non-toxic with asthetic view, eco friendly and low VOC (Volotile OrganiC Compound)materlal. The product complies with the requirement as laid out in as per ASTM D822.Recommended DFT(DryFilm thickness): 100 -110 microns per coat. Top coat mayhavewith 5% - 10% dilution if required and anti carb primer with 100%' dilution with approx. DFT:20 micron. Total system DFTshould not be less than 230 micron forgetting better anticarbonatlon property on concrete surface as per direction of Engineer -In.charge.

210

179

37590

... More
Granular Sub-base with Graded Material Construction of granular sub-base by providing graded material, mixing in Wet Mix Plant at OMC, carriage of mixed material to work site, spreading in uniform layers with Motor grader on prepared surface in proper grade and camber, compacting with vibratory power roller to achieve the desired density, including lighting, guarding, barricading, including cost of all materials, machinery, tools and plants and cost of quality control complete as per Clause 401 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).(ii) Grading – II

27.5

1935

53215.25

... More
Water Bound Macadam Base Course Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness,hand packing, rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber, applying and brooming requisite type of screening / binding materials to fill up the interstices of coarse aggregate, watering including lighting, guarding, barricading and making necessary earthen bundh of one metre width on each side and preparing the bed by necessary cutting or filling, including cost of all materials and hire and labour charges of all men and machinery and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). Grading-II Aggregate (53 mm to 22.4 mm) Using Stone Screening Type B (11.2 mm) , Manual Means.

27.5

2611

71816.8

... More
Prime Coat: Providing and applying primer coat with Cationic Bitumen Emulsion of approved grade conforming to IS:8887-1978 and requisite quantity on prepared surface of granular base including cleaning of road surface and spraying primer using Mechanical means including cost and carriage of bitumen emulsion and all other incidental costs of work complete as per Clause 502 of Specification for Road & Bridge Works of MoRT&H (5th Revision).(i) For WBM / WMM Surface: (with primer @ 0.70-1.0 kg/sqm)

110

28

3179

... More
Tack Coat: Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). On Granular surfaces treated with primer (Using Bitumen emulsion at the rate of 0.25 to 0.30 kg per sqm.)

110

10

1117.6

... More
Tack Coat: Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). On Bituminous Surface(with primer @ 0.25 kg/sqm)

772.2

9

7227.79

... More
Tack Coat: Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS: 8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) On Cement concrete pavement (Using Bitumen emulsion at the rate of 0.30 to 0.35 kg per sqm.)

214.05

11

2519.37

... More
Providing and laying bituminous macadam with Mobile Hot Mix Plant (Light Duty) using approved crushed aggregates of specified grading as per Table 500.4 premixed with bituminous binder, transported to site laid over a previously prepared surface at specified laying temperature by means of approved and suitable arrangements to the required grade, level and alignment and rolled with suitable power roller for break down, inter-mediate and finished rolling as per specification to achieve the desired compaction including cost and carriage of stone materials and bitumen, hire charges of machinery and equipment, cost of fuel and lubricants and wages of operational staff, quality control complete as per Specifications for Road & Bridge Works of MoRT&H (5th Revision). For Grading II, 50- 75mm thick.

33

5898

194654.46

... More
Providing and laying Mastic asphalt wearing course with paving grade bitumen meeting the requirements given in table 500-29 using approved coarse aggregate, fine aggregate, filler material and bitumen, prepared by using Mastic cooker including cost and carriage of all ingredients, cost of heating aggregates and binder, mixing in specified proportions conforming to approved Job Mix Formula and laid to required level and slope after cleaning the surface, compacting, sealing the construction joints and surface finishing conforming to specifications including providing antiskid surface with bitumen pre-coated fine-grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005 cum per 10 sqm and at an approximate spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces not less than 100°C, protruding 1 mm to 4 mm over mastic surface, including the hire charges of all tools and plants and machinery, pay of operators, cost of fuel and lubricants and all other incidental charges and quality control all complete as per Clause 516 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) 25 mm thickness

651.75

468

305390.5

... More
Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing and Clause 801 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).60 cm circular

3

3591

10773

... More
Retro-Reflectorised Traffic Signs Providing and fixing of retro- reflectorised cautionary, mandatory and informatory sign as per IRC :67 made of high intensity grade sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved drawing and Clause 801 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).60 cm equilateral triangle

3

2652

7956

... More
Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete.(a) Depth of excavation not exceeding 1,500 mm.

98.49

119

11746.9

... More
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. (i) Pakur Variety

31.31

5758

180297.38

... More
Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor)(a) 25 mm to 30 mm shuttering without staging in foundation

167.62

209

35033.21

... More
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation and upto roof of ground floor/upto 4 m. (i) Tor steel/Mild Steel I. SAIL/ TATA/RINL

2.49

54915

136518.94

... More
Applying Exterior grade Acrylic primer of approved quality and brandon plastered or cencrete surface old or new surface to receivedecorative textured (matt finish) or smooth finish acrylic exterioremulsion paint including scraping and preparing the surface throughly,complete as per manufacturer's specification and as per direction of the EIC.In Ground Floor:(b) Two Coats

330

4510

14883

... More
Protective and Decorative Acrylic exterior emulsion paint of approved quality, as per manufacturer's specification and as per direction of Engineer-in-Charge to be applied over acrylic primer as required. The rate includes cost of material, labour, scaffolding and all incidental charges but excluding the cost of primer.In Ground floor (Two Coat) b) Premium 100% Acrylic Emulsion

330

84

27720

... More
Taking out heavy iron grated door or window (jail pattern or existing) with locking arrangement after cutting out from walls and refixing the same including mending all damages.[Mending charges to be paid separately]

112

227

25424

... More
Priming one coat on steel or other metal surface with synthetic oil bound primer of approved quality including smoothening surfaces by sand papering etc.(on grill)

112

29

3248

... More
A) Painting with best quality synthetic enamel paint of approved make and brand including smoothening surface by sand papering etc. including using of approved putty etc. on the surface, if necessary :(b) On steel or other metal surface : With super gloss (hi-gloss) -(i) Two coats (with any shade except white)

112

79

8848

... More
Load test on bridge (Static load test & Dynamic Load test)

1

700000

700000

... More
Add GST @ 18% on Rs. 33561105.32 i.e. Total amount over Item No. 01 to 58

33561105.32

-

6040998.96

... More
Add Labour Welfare Cess @ 1% on Rs.39602140.28 i.e. Total amount over Item No. 01 to 59

39602104.28

-

396021.04



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements

Past Bidders
This list is curated from the bidders of the similar tenders in the past

Unlock the Tender details for free
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.