Howrah Improvement Trust Tender
Search from over 10,000+ business opportunities that have been announced from the biggest West Bengal tenders, e tender West Bengal, WB government tenders, and the Online Tender Notices posted on West Bengal e tenders to date. Find opportunities that have come in from multiple corporations, West Bengal government departments, State PSUs, and several Private companies from the state.
Howrah Improvement Trust - HIT Tender
Eprocure
Opening Date11 Sep 2018
Closing Date25 Sep 2018
Tender Amount₹ 35,78,565 This is an estimated amount, exact amount may vary.
Costs
EMD
₹ 71,600Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2018_HIT_189469_7Bid Award Id
ViewTender No
HIT/CE/7/2018-19Tender Authority
Howrah Improvement Trust ViewPurchaser Address
-Website
http://wbtenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Ordinary Cement concrete (mix 1:2:4) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement,if any, in ground floor as per relevant IS codes.
a) Pakur Variety
45
-
5150.9
... More
Single Brick Flat soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand.
600
-
355
... More
Brick work with first class bricks in cement motar (1:4).
In foundation and plinth.
155
-
5483
... More
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. For works in foundation and upto roof of ground floor/upto 4 m
Tor steel/Mild Steel Other than
SAIL/ TATA/RINL
2
-
55629
... More
Ordinary cement concrete (Mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement, if any. In Ground Floor as per relevant IS codes.
Pakur Variety in Ground Floor
35
-
5707.99
... More
Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor) 25 mm to 30 mm shuttering without staging in foundation
350
-
209
... More
Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] With 1:4 cement mortar 15 mm thick plaster
950
-
156
... More
Neat cement punning about 1.5mm thick in wall dado, window sills, floor, drain etc.
950
-
34
... More
Artificial stone in floor, dado, staircase etc with cement concrete (1:2:4) with stone chips, laid in panels as directed with topping made with ordinary or white cement (as necessary) and marble dust in proportion (1:2) including smooth finishing and rounding off corners including raking out joints or roughening of concrete surface and application of cement slurry before flooring works using cement @ 1.75 kg/sq.m all complete including all materials and labour. 25 mm. thick
210
-
259
... More
Providing construction Joint at Concrete road with 12mm thick Thermokal Board in position including cutting to requisite size and shape all complete as per direction of Engineer -in -Charge.
6
-
114.84
... More
Supplying Eucalyptus-bullah piles at work site, including dressing and making one end pointed.
125 mm diameter
3900
-
145
... More
Coal tarring on wooden surfaces including cost of materials.
Double coat.
1900
-
36
... More
Labour for driving Sal-bullah / Eucalyptus bullah piles by monkey in sorts of soil including hoisting and placing piles in position, protecting the pile head with iron ring and cutting and shaping heads before and after driving and including hire and labour for necessary driving appliances and all tackles.
125 mm diameter
3000
-
92
... More
Labour for fitting and fixing 10 cm to 13 cm diameter Eucalyptus-ballah as tiles and runners including necessary nails, bolts and nuts.
210
-
20.6
... More
Supplying empty Cement bags in good condition.
4800
-
330
... More
Filling empty Cement bags with dry earth or sand, stitching the bag (cost of thread included) and carrying and placing them in position and all incidental charges complete but excluding cost of sand and gunny bags.
4800
-
350
... More
Supplying fitting, fixing Darma mat in flowing or stagnant water or in dry
areas with 16 SWG GI wire as per direction of the Engineerr-in-charge
Where boats are not necessary
125
-
171
... More
Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm.including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work) With earth obtained from excavation of foundation.
400
-
7754
... More
Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal /Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge
30
-
166
... More
Bailing out water by pump including all leads and lifts and including making all arrangements for disposal, where continuous flow or seepage of water is encountered and rating of pumps and hours of operation is specifically ascertained as per direction of the Engineer-in-charge.
500
-
23
... More
Add 12% GST on item no 1 to 23
1
-
380024.67
... More
Add 01% Cess on item no 1 to 23
1
-
31668.72