Uttarakhand Power Corporation Limited Tender

View complete overview of Uttarakhand UPCL Tender

Uttarakhand Power Corporation Limited - UPCL Tender

Works
Civil And Construction
Civil Works Others
Eprocure
Opening Date21 Aug 2023
Closing Date11 Sep 2023
Tender AmountRefer Documents 
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Earth wire Clamp with nut and bolt for SP- 55

4

-

-

... More
PP & Clamp with nut and bolts

8

-

-

... More
Brasing Clamp with nut and bolts

4

-

-

... More
Labour Charge: Cartage of 8 MVA Power Transformer

-

-

-

... More
Transportation of 8 MVA T/F from Store to Site by truck with the help of 2 No. of crane at safe place..

1

-

-

... More
Shifting of 08 MVA power T/F

-

-

-

... More
Unloading of 8 MVA T/F at 33/11KV S/S Chilkia Ramnagar with all accessories like conservator tank, Radiators etc with the help of 2 No. of crane at safe place.

1

-

-

... More
Shifting and mounting of 08 MVA power T/F with accessories from safe place in S/S to the plinth with help of crane and truck.

1

-

-

... More
Errection Work of 8 MVA Power Transformer

-

-

-

... More
11KV ( 300 Sq.mm ) XLPE Cable Cartage from store centre to Chikia site

100

-

-

... More
Cartage charges for RAIL 3.5 M X 2 Nos.

170

-

-

... More
Assembling of T/F fitting , i.e. radiators and conservator tanks etc. with main tank.

1

-

-

... More
11KV ( 300 Sq.mm )Cable Laying in Trunch

100

-

-

... More
Control Cable ( 4 x 2.5 ) sq. mm) Laying.

100

-

-

... More
Making of 11KV Cable Loop in Trunch

2

-

-

... More
Making of 11KV Cable termination I/D and O/D

2

-

-

... More
Demolish the wall to enter the Power Transformer ( 3x5x .23 ) = 3.45 cum

3.54

-

-

... More
Reconstruct the wall after work ( 0.23 x 3 x 5 ) =3.45 cum

3.45

-

-

... More
12 mm thick plaster in 1:6 mortar (3x5) x 2= 30 Sqm.

30

-

-

... More
Painting work exterior cement paint on boundary wall ( 160 x 3 ) = 480 Sqm.

480

-

-

... More
Making of control cable trunch 150 mm below the ground level by 75 x 2 mm PVC Pipe (cost of pvc pipe include)

40

-

-

... More
Special Earthing Work

-

-

-

... More
Laying and moulding of M S Earth strip and GI Earth strip

210

-

-

... More
Welding of G I Earth strip with yard equipment complete welding work including enty corosion paint on welded area

1

-

-

... More
Driving the earth electrode in earth pit

50

-

-

... More
Fixing of Neutral earthing with T/F and body earthing (Diagonial) by electric arc welding in proper way.

1

-

-

... More
New 11 kv VCB Panels and Transformer (N) Earth work by digging mannualy 12 feet below the ground level for chemical earth system and connect with GI Strip (50X6mm) and making of chamber with cover on it.

2

-

-

... More
Fencing work

-

-

-

... More
Dismentling of palefencing after cutting by cutter or electric welding machine for yard extention work

20

-

-

... More
Cartage of MS Angle and Channel and other small material

3993.6

-

-

... More
Grouting of pale fencing support angle ( 65x65x6)

36

-

-

... More
Providing and assembling of pale fencing 2.5 meter in height with horigentle angle 3 nos.(35x5)and support angle (35x5) at every 3 meter distance along with one no. gate.

30

-

-

... More
Making of palefencing toe wall foundation with 1:6 brick work 1st step (0.45x0.15x 60 Rm)= 4.05cum + 2nd step (0.35x0.15x 60 ) = 3.15 + 4.05= 7.2 cum

7.2

-

-

... More
RCC work1:1.5:3 on Toe wall plinth beam (0.23x0.15x 60)= 2.07 cum

2.07

-

-

... More
Mild steel or iron work in plinth work such as rainforced concreat Qty.of steel 1.5% of RCC Qty. ( 2.07m3x1.5/100x7850)= 244 kg

244

-

-

... More
Centering and shuttering for plinth beam (0.25x 60) x2= 30 Sqm.

30

-

-

... More
Making of palefencing toe wall super structure with 1:4 brick work (0.23x0. 45x 60 Rm)= 6.21cum

6.21

-

-

... More
12 mm thick plaster in 1:6 mortar (0.90+0.45+0.23)=1.6x60= 96 Sqm.

96

-

-

... More
Fixing of fencing on toe wall by electric welding after addeting aditional angle to increase the height ( 60x2.5)= 150 Sqm.

150

-

-

... More
Painting work on Pale fancing after removing rust by amry paper then applying two coats of industrial paint (Green) ( 30 x 2.5 ) x 2 = 150 Sqm.

150

-

-

... More
Excavation of Earth Turfing Work

-

-

-

... More
Cutting and uprooting of grass and wild bushed plants in yard. 320 Sqm

320

-

-

... More
Final desposal,dressing,leveling of each with proper ramming and compecting complete in all labor / T&P.

320

-

-

... More
Fine sand filling in yard to maintain its height ( 320 x 0.70) = 224 cum

224

-

-

... More
Laying of 1:6:12 cement concreat in flooring of yard 100 mm thick including cost of material and labor etc.proper complete. 320 + 95=415 (415x0.1)= 41.5 cum

41.5

-

-

... More
Spreding and leveling of 15-25 mm grit single for making yard bed including cost of stone grit ,labor,T&P work etc. ( 320 - 20 ) = 300 x 0.1 = 30 cum

30

-

-

... More
Fencing work

-

-

-

... More
Excavation of earth 0.8 m deep width ( 1 m X 33 RM) (33 X 1 X 0.8) = 26.4 cum

26.4

-

-

... More
PCC Work ( 1:4:8 ) in trunch base ( 33 x 0.1 )= 3.3 cum

3.3

-

-

... More
Super structure brick work in 1:4 ratio ( 33 x.23x.9)x2 = 13.662 cum

13.66

-

-

... More
DPC Work on top side 1:3:6 (33 x 0.23x0.05)x2 = 0.759 cum

0.76

-

-

... More
Fabrication cutting and grouting of M S Angle on Top side of trunch ( 33 x 2 ) 66 Meters

66

-

-

... More
Cost of M S Angle ( 40x3 ) 33x2= 66 m x 1.8 kg = 118.8 kg + 13.2 kg support angle = 132 kg

132

-

-

... More
12 mm thick plaster in 1:6 mortar ( 33 x 0.9 ) x 2= 59.4 Sqm.

59.4

-

-

... More
Making of control cable trunch cover with 1:2:4 cement concreat and fixing of 8 mm steel bar in (35x5) angle frame size (0.45x0.6)Sqm.33 Rm/0.6Rm= 55 Nos.

55

-

-

... More
Excavation of 11 kv out going cable

90

-

-

... More
Laying of out going 11kv XLPE Cable in open trunch .

90

-

-

... More
Construction of Transformer Plienth

-

-

-

... More
Excavation of earth 1 m deep (4 X 4 X 1) = 16 cum

16

-

-

... More
PCC Work ( 1:4:8 ) in Plienth base ( 16 x 0.1 )= 1.6 cum

1.6

-

-

... More
Super structure brick work in 1:4 ratio ( 16 x0.15x.1.5) = 3.6 cum

3.6

-

-

... More
Laying the 1 : 3 : 6 CC in Transformer plienth ( 4 x 4 x1.5 ) = 24 cum

24

-

-

... More
Inseart the steel bar nett 12mm three layer in plienth

270

-

-

... More
12 mm thick plaster in 1:6 mortar (16 x .5 )= 8 Sqm.

8

-

-

... More
Cuting work of Rail by gas cutter for fixing on the top of Transformer plienth

2

-

-

... More
Erection of 33 KV CT Structure

-

-

-

... More
Cartage of 33 kv CT from store centre to site

1

-

-

... More
Fabrication of 33 kv CT Structure

1

-

-

... More
Excavation of earth for CT Structure ( 4x1x.3 ) = 1.2 cum

1.2

-

-

... More
Erection charges of CT Structure

1

-

-

... More
Grouting of CT Structure 1:3:6 (4x1x.6 ) = 2.4 cum

2.4

-

-

... More
Painting work on ct structure with one coat primer and two coats of alluminium paint

1

-

-

... More
Installtion charges of CT with control cable

1

-

-

... More
Installation work of 33 KV VCB Structure

-

-

-

... More
Cartage work of 33 KV VCB Loading and unloading by Hydra

1

-

-

... More
Cartage work of 33 KV VCB Control pannel , Loading and unloading by Hydra

1

-

-

... More
Erection work of 33 KV VCB Structure by Hydra

1

-

-

... More
Excavation of earth for VCB Structure (4x1x.3)=1.2 cum

1.2

-

-

... More
Grouting of VCB Structure 1:3:6 (4x1x.6 ) = 2.4 cum

2.4

-

-

... More
Making connection VCB to control panel

1

-

-

... More
Laying charges of control cable

100

-

-

... More
Erection of 33 KV Bus Isolator Structure

-

-

-

... More
Fabrication of 33 kv CT Structure

1

-

-

... More
Excavation of earth for Isolator Structure ( 4x1x.3 ) = 1.2 cum

1.2

-

-

... More
Grouting of Isolator Structure 1:3:6 (4x1x.6 ) = 2.4 cum

2.4

-

-

... More
Erection work of 33 KV Isolator Structure

1

-

-

... More
Assembling and fixing of equipment including proper setting leveling adjusting of Isolator

1

-

-

... More
Painting work on Bus Isolator structure with one coat primer and two coats of alluminium paint

1

-

-

... More
Erection of 33 KV Post Insulator Structure

-

-

-

... More
Fabrication of 33 kv Post Insulator Structure

1

-

-

... More
Excavation of earth for Post Insulator Structure ( 4x1x.3 ) = 1.2 cum

1.2

-

-

... More
Erection charges of Post Insulator Structure

1

-

-

... More
Grouting of Post Insulator Structure 1:3:6 (4x1x.6 ) = 2.4 cum

2.4

-

-

... More
Painting work on Post Insulator structure with one coat primer and two coats of alluminium paint

1

-

-

... More
Installtion charges of Post Insulator

1

-

-

... More
Cartage of 11 kv Pannels

3

-

-

... More
Cartage of S P - 55 Pole

3

-

-

... More
Errection of SP - 55 Double Pole

1

-

-

... More
Errection of SP - 55 Single Pole

1

-

-

... More
Installetion of HT PRMC

1

-

-

... More
Errection of 11 kv stey set

3

-

-

... More
Errection of earthing rod

2

-

-

... More
Laying of Dog conductor in HT Line

0.05

-

-

... More
11 KV VCB Panel Installation work

-

-

-

... More
Shifting work of 11 kv VCB from out side of control room to in control room trunch by menpower.

3

-

-

... More
Grouting work of 11 kv vcb including alignment and leveling and connecting busbar with each vcb.

3

-

-

... More
Testing work of 11 kv VCB with wiring and energigation complete work in all respect

3

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.