Electrical Cables And Wires
Electrical and Electronics
Electrical Works
Eprocure
Opening Date29 Aug 2024
Closing Date18 Sep 2024
Tender Amount₹ 1,12,51,000
Costs
EMD
₹ 2,26,000Document Cost
₹ 11,800Tender Fee
Refer Documents
Summary
Replacement Of Bare Conductor Lt Line By Aerial Bunch Cable On 11 Kv Gadiyanpul Feeder At Various Villages Under Edd Nainidanda On Semi-turnkey Basis
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_UPCL4_75086_1Bid Award Id
ViewTender No
E-Tender no.30/EDC(s)/2024-25Tender Authority
Uttarakhand Power Corporation Limited ViewPurchaser Address
-Website
http://https://www.upcl.org/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
3 Phase LT Distribution Box With inbuilt panel lock, Al Bus Bar RYB 25x6mm,Al Busbar N 40x6mm
22
-
-
... More
1 Phase LT Distribution Box With inbuilt panel lock, Al Bus Bar RYB 25x6mm,Al Busbar N 40x6mm
247
-
-
... More
Insulated piercing connector size 70-70/35-35 sqmm for line to line tapping
1251
-
-
... More
Insulated piercing connector size 70/35 sqmm to 25 sqmm for energising disribution box
325
-
-
... More
Dead End Clamp With I Hook.(Insulated)
249
-
-
... More
Suspension Clamp With I Hook.(Insulated)
705
-
-
... More
LT Wire Neutral Connector PG Clamp 50/25-25sqmm single bolt as per UPCL specificationfor energising distribution box
275
-
-
... More
LT Wire Neutral Connector PG Clamp 50-50/25-25sqmm single bolt as per UPCL specification for line to line tapping
875
-
-
... More
Head shink type end caps suitable for LT ABC
271
-
-
... More
Lug size 16 Sqr Mm
494
-
-
... More
Lug size 50 Sqr Mm
88
-
-
... More
1x16 sq mm XLPE insulated Al. Cable for energising the distribution boxes
988
-
-
... More
1x50 sq mm XLPE insulated Al. Cable for energising the distribution boxes
176
-
-
... More
LT AB Cable 3x35+1x25 Sqr mm
38.8
-
-
... More
LT AB Cable 1x35+1x25 Sqr mm
8.7
-
-
... More
Holding clamp for J-hook
954
-
-
... More
Mid span Joint
215
-
-
... More
Various type Nut and Bolt.
350
-
-
... More
Labour
-
-
-
... More
Cartage of ST Pole SP-21 pole from Store Centre Kotdwar/ Dehradun/ Risikesh to Work Site with Stacking site in 1Km Distance Including Loading & unloading (distance 5kms-275 kms)
-
-
-
... More
ST Pole SP-21
10
-
-
... More
ST Pole SP-10
19
-
-
... More
Head Load Cartage of ST Pole SP-21 From Road Site to work site distance approx 3.0 km By Man Power
-
-
-
... More
ST Pole SP-21
10
-
-
... More
ST Pole SP-21
19
-
-
... More
Cartage of small Line material from Store Centre Kotdwar Dehradun/ Risikesh to road Side Including loading & unloading (distance 5kms-275 kms)
20.5
-
-
... More
Head Load Cartage of Road Site to work site distance approx 3.0 km By Man Power
-
-
-
... More
LT AB Cable 3x35+1x25 Sqr Mm
38.8
-
-
... More
LT AB Cable 1x35+1x25 Sqr Mm
8.7
-
-
... More
Erection charge of ST Pole SP-21/10 pole in long span as per UPCL norms
-
-
-
... More
ST Pole SP-21
10
-
-
... More
ST Pole SP-10
19
-
-
... More
Fixing and Grouting of stay Complete Work
29
-
-
... More
Removing & Reconnection of Single phase/Three phase LT Consumer Service Connection
533
-
-
... More
Painting of poles on Top Portion
-
-
-
... More
ST Pole SP-21
315
-
-
... More
ST Pole SP-10
160
-
-
... More
Dismantling of Old ACSR weasel Conductor from existing LT line including Re Rolling cartage from worksite to JE Store after Head Load cartage from different site.
-
-
-
... More
LT line 3 Phase 4 Wire
3.5
-
-
... More
LT line 2 Phase 3 Wire
5.2
-
-
... More
LT line 1 Phase 2 Wire.
38.8
-
-
... More
Head load cartage of dismantled old ACSR Weasel Conductor from work site to road side
97.21
-
-
... More
Back cartage of dismantled old ACSR Weasel Conductor from JE Store.
97.21
-
-
... More
Laying stringing and sagging of AB cable including fixing of piercing Connector, dead end clamp with I hook, suspension clamps with I hook in all complete work.
-
-
-
... More
LT AB Cable 3x35+1x25 Sqr Mm
38.8
-
-
... More
LT AB Cable 1x35+1x25 Sqr Mm
8.7
-
-
... More
Laying and fixing of 1x16/50 sq mm XLPE insulated Al. Cable for energising the distribution boxes
1164
-
-
... More
Installation of LT Distribution Box complete work 3 phase
22
-
-
... More
Installation of LT Distribution Box complete work 1 phase
247
-
-
... More
Lopping chopping of tree Branches
47.5
-
-
... More
Fixing of Holding clamp and stay clamp
983
-
-
... More
Fixing of Nuts and Bolts
350
-
-
... More
Straightening of tilted pole
55
-
-
... More
Fixing of Al. Lugs
573
-
-
... More
Fixing of Aluminium Lugs
-
-
-
Evaluation Notes How It Works ?