Uttarakhand Power Corporation Limited Tender
View complete overview of Uttarakhand UPCL Tender
Uttarakhand Power Corporation Limited - UPCL Tender
Electrical and Electronics
Electrical Works
Eprocure
Opening Date24 Jul 2024
Closing Date8 Aug 2024
Tender Amount₹ 73,77,000
Costs
EMD
₹ 1,50,000Document Cost
₹ 5,900Tender Fee
Refer Documents
Summary
Construciton Of 33 Kv Circuit And Extension Of Yard Under Edsd Tanakpur
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_UPCL3_73895_1Bid Award Id
ViewTender No
21/2024-25/EDC(CH)Tender Authority
Uttarakhand Power Corporation Limited ViewPurchaser Address
-Website
http://uktenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
General Conditions for bidder
BOQ Items
... More
Stay Clamp for SP33 with Nut & Bolt.
18
-
-
... More
33 KV isolator Connector Clamp for Panther with Nut & Bolt.
18
-
-
... More
33 KV CT Clamp for Panther with Nut & Bolt.
6
-
-
... More
Bracing Clamp for St SP33 top with Nut & Bolt.
24
-
-
... More
Earthing Wire Clamp for SP-33 with Nut & Bolt.
14
-
-
... More
T Clamp for 33 KV isolator (Panther)
18
-
-
... More
Stya Clamp D/E for SP33 With Nut & Bolt.
5
-
-
... More
GI Pipe 6 Metr long
4
-
-
... More
PG Clamp for Panther
24
-
-
... More
Top Channel Clamp for SP-33 with Nut & bolt.
42
-
-
... More
Panther to Panther C Type Wedge connector -D
60
-
-
... More
33 KV HS Cable end T/K3x400 Sq.mm O/D
8
-
-
... More
24V battery Set.
1
-
-
... More
24 V battery Charger
1
-
-
... More
Al. Crimping type Lugs 400SQ.mm
12
-
-
... More
GI Strip 50x6mm
60
-
-
... More
Annexure-B (Work)
-
-
-
... More
Excavation for foundation
12.5
-
-
... More
Cleaning, dressing & Labling switch Yard.
192
-
-
... More
Excavation of Trench in all Soil
3.75
-
-
... More
Brick Work in 1:4 Ratio.
240
-
-
... More
Construction of returing wall & plinth
63
-
-
... More
Filling of soil for leveling of yard.
8
-
-
... More
Erection of earthing rod
8
-
-
... More
Fabrication of Steel /MS Channel and angle etc. as pe site requirement.
2595
-
-
... More
Fixing of GI pipe
24
-
-
... More
Excavation of earth for stay pit of size 0.6x0.6x1.2 Mtr. In all rype of soil including proper dressing o sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as directed complete work.
4.32
-
-
... More
Erection of 33 KV Stay Set.
10
-
-
... More
Grouting of stay in size 0.6x0.6x.03 in CC ration 1:4:8 (1 Cement: 4 graded stone 20mm nominal size : 8 coarse sand) block including cost of Cement, sand and stone ballast back filling of soil and boulders in pit and ramming and proepr alignment, leveling as per RESSPO manual.
1.08
-
-
... More
Excavatin of earth for pole pit of size 0.9x0.6x1/6 of full length of pole for erection of pole in all type of soil includign proper dressing of sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as drected complete work.
14.58
-
-
... More
Erection of following Single support pole SP-33 in proper level and slignment alongwith fixing of all accessories, like top channel & clamps as per RESPO construction manual.
8
-
-
... More
Erection of SP-33 double support pole in proper level and alignment alongwith fixing of all accessories, like top channel, X-bracing & clamps as per RESSPO construciton manual.
1
-
-
... More
Erection of SP-33 four pole support in proper level and alignment alongwith fixing of all accessories, lke top channel, X bracing & clamps as per RESSPO construction manual (labour charges) for 11 KV/ 33 KV.
2
-
-
... More
Grouting of pole in size 0.45x0.45x1/9 of the support in CC ration 1:4:8 (1 cement : 4 graded store 20mm nominal size :8 Coarse sand) block including cost of cement, sand and store ballast back filling of soil and boulders in pit and ramming and proper alignment, leveling as per RESSPO manual.
3.65
-
-
... More
Muffing of poles size 0.45 cmx 0.60 cm radious with CC 1:3:6 (1 cement :3 Coarse sand:6 graded stone 10mm nominal size) block size 45 cm height from ground leve including cost of cement, stone and sand etc.
18
-
-
... More
Painting of Yard
1
-
-
... More
Laying of U/G LT Cable in trnch.
550
-
-
... More
Laying of U/G 33 KV Cable in Trnch.
500
-
-
... More
Erection of bracket in 33 KV line
12
-
-
... More
Laying of HT line in Panther Conductor as phase wire with G.I. earth wire complete including fixing of all accessories in 03 Nos. conductor in aparallel with ninding and jumpering as per profile and sagging chart.
0.21
-
-
... More
Cartage of ST pole SP33 from store centre to nearest construction site store with loading, unloading at both point and proper stacing, distance slab 21 to 50 Km.
18
-
-
... More
Cartage of other material (other tan poles) by vehicle from store center to nearest construction site store including loading and unlading at both end. Distance slab 21 to 50 Km.
120
-
-
... More
Headload Cartage of SP-33 Pole from work site store to work site Lead distance 0 to 01 Km.
18
-
-
... More
Headload Cartage of small material from work site store to work site Lead distance 0 to 01 Km.
120
-
-
... More
Road Cutting and repairing
8
-
-
... More
Turfing in switch Yard area.
1
-
-
... More
Providing and fixing of fencing for CSS.
25
-
-
... More
Dismantle of Fan Structure Complete work.
1
-
-
... More
Installation of J/Kit 33 KV 3x400 O/D
8
-
-
... More
Installation / Fixing of 33 KV Isolator
1
-
-
... More
Making of Trench Cover
15
-
-
... More
Earthing of structure using GI Strip
2
-
-
... More
Erection of line isolator structure
2
-
-
... More
Mannual digging of cable trnch upto 1MT
0.5
-
-
... More
Erection of Bus isolator structure
1
-
-
... More
Loping and Chopping- Route clearence by cutting of tree branches/ proning, loping and chopping of tree.
3
-
-
Evaluation Notes How It Works ?
Potential Partner