Uttarakhand Power Corporation Limited Tender
View complete overview of Uttarakhand UPCL Tender
Uttarakhand Power Corporation Limited - UPCL Tender
Electrical and Electronics
Eprocure
Opening Date14 Oct 2024
Closing Date28 Oct 2024
Tender Amount₹ 1,98,24,694
Costs
EMD
₹ 3,97,000Document Cost
₹ 11,800Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_UPCL4_76969_1Bid Award Id
ViewTender No
39/EDCC/2024-25Tender Authority
Uttarakhand Power Corporation Limited ViewPurchaser Address
-Website
http://uktenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
Technical Specifications
BOQ Items
11KV 90 KN Tension clamp with Bail and IPC (section Pole)
231
-
-
11 KV Pin Insulator (Polymeric Type)
84
-
-
11KV Suspension ties on every Pin Insulator.
693
-
-
11Kv IPC for CC to CC Connection in every Section Pole
18
-
-
11Kv IPC for CC to Bare Connection at both end and Taping
15
-
-
11Kv Mid Span Jointing kit at every 500Mt. Cable drum
9
-
-
Supply IPC with Aluminium bail for earthing
9
-
-
Supply of Holding Clamp for Stay with N&B.
22
-
-
Supply of Holding Clamp for SP-23/SP-33 with N&B.
32
-
-
Labour
-
-
-
Cartage of Poles from store centre to nearest road site with loading, unloading at both points. (Loading, unloading plus carriage per poles) (0 to 100 km)
-
-
-
ST Pole SP-23 (Bottom Portion Hot dip)
21
-
-
ST Pole SP-33 (Bottom Portion Hot dip)
11
-
-
Small Material
3.2
-
-
Head load Cartage of the following poles from road side to construction site (rates are per pole /Km including loading/unloading at both points) (0 to 1 KM)
-
-
-
ST Pole SP-23 (Bottom Portion Hot dip)
21
-
-
ST Pole SP-33 (Bottom Portion Hot dip)
11
-
-
Small Material
3.2
-
-
Excavation of earth and erection of ST pole SP 23 single support with CC Complete
21
-
-
Excavation of earth and erection of ST pole SP 33 single support with CC Complete
11
-
-
Muffing of SP 23/33 pole
32
-
-
Erection of stay set complete
22
-
-
Erection of Earthing Rod 20X2500mm
32
-
-
Fabrication of MS channel and angle
320
-
-
Removing of old conductor with opening of existing, jumpering and making of bundle with carriage from pit size of store including loading/ unloading complete work
25226
-
-
Laying, spreading, stringing and sagging of 11KV AAAC AL-59 (99 sqmm) Covered conductor (SS4240813 & SS4240814) EN 50397-1:2006 the conductor shall be stranded, round, non compacted and water tight. Non compacted shall be comply with all the requirement of EN 50397-1.2006. The stranded conductor shall be longitudionally water blocked by means of a water blocking material the semi conducting screen inner insulation and outer insulation should be extruted in one step. The outer covering insulation shall be UV stabilized tracking resistant black XLPE Capacity 300 amp
25226
-
-
Fixing of MVCC accessories
-
-
-
11 KV 90KN tension clamp with bail and IPC
231
-
-
11 KV Suspension ties
693
-
-
11 KV IPC for CC to CC Connection
18
-
-
11 KV IPC for CC to Bare connection
15
-
-
11 kV Mid Span Jointing kit
9
-
-
Fixing of IPC with Aluminium bail for earthing
9
-
-
Back carriage of material from site to store (0-100 Kms) including manual shifting
1
-
-
Looping Chopping of tree branches for route clearance
32
-
-
Fixing of Aluminium Lugs
-
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements