Civil And Construction
Electrical and Electronics
Water Storage And Supply
Electrical Works
Eprocure
Opening Date6 Sep 2024
Closing Date21 Sep 2024
Tender AmountRefer Documents
Costs
EMD
₹ 75,000Document Cost
₹ 1,180Tender Fee
Refer Documents
Summary
Construction Of Ht/lt Line/sub-station And L.t. Extension Work For Giving New Connection As Per Uerc Regulation Under 33/11 Kv S/s Kichha And Pulbhatta Under Edsd, Kichha
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_UPCL3_75423_1Bid Award Id
ViewTender No
EDC(USN)19/2024-25Tender Authority
Uttarakhand Power Corporation Limited ViewPurchaser Address
-Website
http://https://www.upcl.org/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
General Instruction for bidders
BOQ Items
Excavation of earth for stay pit of size 0.6x0.6x1.2 mtr in all types of soil including proper dressing of sides and ramming of bottom including getting out the excavated soil and disposal of surplus excavated soil as directed complete work
80
-
-
Fixing,tightening and nozzling of stay with pole and stay rod on required tension as per drawing/manual in LT line
30
-
-
Fixing,tightening and nozzling of stay with pole and stay rod on required tension as per drawing/manual in 11 KV Line
50
-
-
Grouting of Stay in size 0.6x0.6x0.3 in CC ratio 1:4:8 (1 cement : 4 graded stone 20mm nominal size : 8 coarse sand ) block includ ing cost of Cement,sand and stone ballast back filling of soil and boulders in pit and ramming and proper alignment, leveling as per RESSPO Manual.
80
-
-
Excavation of earth for pole pit of size 0.9x0.6x1/6 of full length of pole for erection of pole in all types of soil including prop er dressing of sides and ramming of bottom including etting out the excavated soil and disposal of surplus excavated soil as directed complete work
258
-
-
Erection of PCC single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual
166
-
-
Erection of SP-23 single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual
2
-
-
Erection of SP-33 single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual
4
-
-
Erection of SP-55 single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual
8
-
-
Erection of SP-72 single support pole in proper level and alignment along with fixing of all accessories like top channel,& clamps as per RESPO manual
2
-
-
Erection of PCC double support pole in proper level and alignment along with fixing of all accessories like top channel, X bracings & clamps as per RESPO manual
27
-
-
Erection of SP-23 double support pole in proper level and alignment along with fixing of all accessories like top channel, X bracings & clamps as per RESPO manual
2
-
-
Erection of SP-33 double support pole in proper level and alignment along with fixing of all accessories like top channel, X bracings& clamps as per RESPO manual
3
-
-
Erection of Sp-55 double support pole in proper level and alignment along with fixing of all accessories like top channel, X bracings & clamps as per RESPO manual
6
-
-
Muffing of poles size 0.45x0.60 cm radius with 1:3:6(1 cement:3 coarse sand :graded stone 10 mm nominal size) block size 45 cm height from ground level including cost of cement,stone and sand etc.
38
-
-
Dismantling of Transformers from double pole /plinth including opening of all connections, circuts & earthing strip etc. (25 KVA)
6
-
-
Dismantling of Transformers from double pole /plinth including opening of all connections, circuts & earthing strip etc. (63 KVA)
5
-
-
Dismantling of Transformers from double pole /plinth including opening of all connections, circuts & earthing strip etc. (100 KVA)
2
-
-
Installation of 33/11 KV Metering cubical in the Metering room with grouting and making all connection
4
-
-
Loading, unloading & carriage of LT PRMC from Store to pit site & Installation on the double pole with the help of Nut Bolt & Clamp and making to pass LT cable from T/F to PRMC.
8
-
-
Laying and erection of L.T. PVC Cable including crimping of lugs of size 1x70,120, 150 Sq.mm. (Including all cost of material)
320
-
-
Digging of trench of size 0.60x0.15 x 1.5 mtr. and laying of underground 11 KV XLPE cable with making of brick housing and filling of sand including filling of earth with ramming. & repairing of road including cost of cement sand and stone blast
300
-
-
Installation / mounting of new 100 KVA Tranformer on pole structure and fixing of channel / angle etc. and making all connections of Ht and LT side and its complete commissioning.
15
-
-
Installation / mounting of new 63 KVA Tranformer on pole structure and fixing of channel / angle etc. and making all connections of Ht and LT side and its complete commissioning.
20
-
-
Installation / mounting of new 25 KVA Tranformer on pole structure and fixing of channel / angle etc. and making all connections of Ht and LT side and its complete commissioning.
32
-
-
Mounting & Fixing of Fuse sets on double pole structures including making of connections complete work
60
-
-
Fixing of triangular type bracket on 11 KV line
10
-
-
Laying, Spreading, Stringing and sagging of 11 KV / 33 KV line in 3 phase (3 Phase 3 wire) of ACSR Weasel as phase wire with G.I. earth wire complete including fixing of all accessories in 3 Nos. conductor in parallel with binding and jumpering as per profile and profile and sagging chart.
3
-
-
Laying, Spreading, Stringing and sagging of 11 KV / 33 KV line in 3 phase (3 Phase 3 wire) of ACSR Rabbit as phase wire with G.I. earth wire complete including fixing of all accessories in 3 Nos. conductor in parallel with binding and jumpering as per profile and profile and sagging chart.
1
-
-
Laying, Spreading, Stringing and sagging of 11 KV / 33 KV line in 3 phase (3 Phase 3 wire) of ACSR Dog as phase wire with G.I. earth wire complete including fixing of all accessories in 3 Nos. conductor in parallel with binding and jumpering as per profile and pro file and sagging chart.
1
-
-
Laying, Spreading, Stringing and sagging of L.T. Lines of ACSR Weasel as phase wire(3 phase 4 wire) with G.I. earth wire complete wi th binding and jumpering as per RESSPO Specn
2
-
-
Laying, Spreading, Stringing and sagging of L.T. Lines of ACSR Weasel as phase wire(2 phase 3 wire) with G.I. earth wire complete wi th binding and jumpering as per RESSPO Specn
1
-
-
Laying, Spreading, Stringing and sagging of L.T. Lines of ACSR Weasel as phase wire(1 phase 2 wire) with G.I. earth wire complete wi th binding and jumpering as per RESSPO Specn
2
-
-
Route cleareance by cutting of tree branches / proning, loping and chopping of trees for L.T., 11 & 33 KV line.
5
-
-
T-off Connection Complete 11 KV line
15
-
-
Laying,Sagging & binding of AB cable of size 120 sqmm.(Only for cable,additional provisions to be made for matching accessories inst allation,case of any network modification i.e additionalpole etc. and for actual connection,disonnection as per site condition.
350
-
-
Making of section pole for existing LT/HT/33KV line complete in all respect.
6
-
-
Jointing and fixing of cable jointing kit indoor/outdoor 11 KV XLPE heat shrinkable cable boxes
8
-
-
Cartage of PCC Poles from store centre to construction site with loading, unloading at both points and proper stacking.(Distance 21- 50 Km)
200
-
-
Cartage of ST pole SP-21/23 Poles from store centre to construction site with loading, unloading at both points and proper stacking. (Distance 21-50 Km)
6
-
-
Cartage of ST pole SP-33 Poles from store centre to construction site with loading, unloading at both points and proper stacking.(Distance 21-50 Km)
10
-
-
Cartage of ST pole SP-55 Poles from store centre to construction site with loading, unloading at both points and proper stacking.(Distance 21-50 Km)
20
-
-
Cartage of ST pole SP-72 Poles from store centre to construction site with loading, unloading at both points and proper stacking. (Distance 21-50 Km)
2
-
-
Cartage of other material (other than poles) by vehicle from Store Center to nearest construction site Store including loading and unloading at both ends (distance 21-50 Km)
80
-
-
Cartage of the 16/25 KVA transformer from store center to construction site with loading and unloading at both points. (Distance 21-50 Km)
32
-
-
Cartage of the 63 KVA transformer from store center to construction site with loading and unloading at both points. (Distance 21-50 K m)
20
-
-
Cartage of the 100 KVA transformer from store center to construction site with loading and unloading at both points. (Distance 21-50 Km)
15
-
-
Cartage of the 33 KV VCB,feeder panels(O/D),T/F Control panel from store center to construction site with loading and unloading at both points. (Distance 21-50 Km)
4
-
-
Headload cartage of PCC Pole from road to site (distance 0-1 Km)
200
-
-
Headload cartage of SP-21/23 Pole from road to site (distance 1-3 Km)
6
-
-
Headload cartage of SP-33 Pole from road to site (distance 0-1 Km)
10
-
-
Headload cartage of SP-55 Pole from road to site (distance 0-1 Km)
20
-
-
Headload cartage of SP-72 Pole from road to site (distance 0-1 Km)
2
-
-
Head load cartage of small material(distance 0-1 Km)
80
-
-
Head load cartage of small material(distance 1-3 Km)
4
-
-
Headload cartage of 25 KVA transformer from road to site(distance 0-1 Km)
32
-
-
Headload cartage of 63 KVA transformer from road to site(distance 0-1 Km)
20
-
-
Headload cartage of 100 KVA transformer from road to site(distance 0-1 Km)
15
-
-
DIGGING OF PIT FOR MAKING TRENCH 0.6X0.15X1.5 MTR FT DEPTH, INCLUDING BRICK AND SAND WORK INCLUDING BACK FILLING AS PER RESPO
300
-
-
LAYING STRINGING AND SAGGING OF LT AB CABLE 3X70+1X50 SQMM
300
-
-
Digging of Pit through Hammer at CC, DAMAR Road
10
-
-
Transportation Charges of 25 KVA including packing, forwarding, loading, unloading, stacking and transit insurance.
2
-
-
Transportation Charges of 63 KVA including packing, forwarding, loading, unloading, stacking and transit insurance.
2
-
-
Transportation Charges of 100 KVA including packing, forwarding, loading, unloading, stacking and transit insurance.
1
-
-
Annexure-B (SUPPLY ITEMS)
-
-
-
MS Nut & Bolt off size
40
-
-
F CLAMP
55
-
-
X ARM CLAMP FOR PCC POLE WITH N/B
55
-
-
X ARM CLAMP FOR ST POLE SP-55 WITH N/B
20
-
-
LT CLAMP FOR PCC POLE WITH N&B
180
-
-
LT CLAMP WITH N&B ST POLE SP-55
32
-
-
STAY CLAMP FOR ST POLE WITH NUT BOLT
20
-
-
DOUBLE POLE CLAMPS WITH N/B FOR PCC POLE
100
-
-
DOUBLE POLE CLAMPS WITH N/B FOR SP-55
32
-
-
STAY CLAMP WITH N&B PCC POLE 8.5 MTR
70
-
-
STAY INSULATOR 75x90 MM
100
-
-
SHACKLE INSULATOR 75X90 MM WITH NUT BOLT
200
-
-
Supply of insulated Piercing connector body molded from high quality mechanical climate and UV resistant glass reinforced polyamide, hot dipped galvanized bolts & contact teeth ABC size 120 Sqmm to 95 Sqmm TYCO/RPG/3M Make.
4
-
-
Supply of insulated Piercing connector body molded from high quality mechanical climate and UV resistant glass reinforced polyamide, hot dipped galvanized bolts & contact teeth ABC size 95 Sqmm to 35 Sqmm TYCO/RPG/3M Make.
4
-
-
Supply of SMC Three Phase L.T. Distribution Box with inbuilt panal lock, Al bus bar RYB 25x6mm., Al Busbar N. 40x6mm. for connection of L.T. consumer (Sintex/RMC make or other ISO reputed company) with Panel Lock with key) (As per drawing attached)
1
-
-
Crimping type Al. Lug (25-100) SQ.MM
50
-
-
MS Flat 40x6 MM
120
-
-