Supply And Construction 11 Kv Line From Lakhwar Ss To Dam Top Of Lakhwar Mpp
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_UJVN_78481_1Bid Award Id
ViewTender No
NIT No07/EE EM-II/LP/3024-25Tender Authority
Uttarakhand Jal Vidyut Nigam Limited ViewPurchaser Address
-Website
http://uktenders.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
10 KN Polymer Pin Insulator with Pin
40
-
-
... More
70 KN Polymer Disc Insulator(B&S) Type
80
-
-
... More
Disc Fitting (B&S) Dog/Racoon 70 KN
80
-
-
... More
Supplying of 11 kv HT Three Core Power Cables-Aluminium Armoured Conductor A2XFY , 3x120 sq.mm
200
-
-
... More
MS Channel 125 mm X65 mm X 6 mm (13.10 kg per metre), 3.5meter long as required.complete work in all respect.(12 No x 13.1 x 3.5=550.2 Kg for SP-72 & 55
2751
-
-
... More
MS Channel 100 mm X50 mm X 6 mm ( 9.56 kg per metre), 3.2 meter long as required.complete work in all respect.(4 No x 9.56 x 3.2=122.368 Kg for SP-33
459
-
-
... More
MS Anlgle 65x65x8mm (5.8 kg per metre), 3.5meter long for bracing as required.complete work in all respect.
853
-
-
... More
Stay Set GI for (SP-33),stay rod (16x1800 mm) with anchor plate 45cmx45cmx7.5mm complete with thimble,stay clamp,Turn buckle 20mmx60cm,strain Insulator etc. as required.complete work in all respect.
18
-
-
... More
Stay Set GI for (SP-55),stay rod ( 20x1800 mm) with anchor plate 45cmx45cmx7.5mm complete with thimble,stay clamp,Turn buckle 20mmx60cm,strain Insulator etc. as required.complete work in all respect.
8
-
-
... More
Stay wire 7/10 SWG
130
-
-
... More
Earth Wire 7/16 SWG
26
-
-
... More
ACSR Raccoon conductor
9
-
-
... More
Cross Arm Channel 100x50x6 mm V-Type 33/11 kv Line
4
-
-
... More
100 KVA Alu.Wound EE Level-2 Transformer(11/0.4kv)
1
-
-
... More
11 kv Surge/Lighting Arrester
6
-
-
... More
Work Part
-
-
-
... More
Erection of galvanised stay set in 11 KV over head lines complete with 20 mm dia X 1.8 metres long stay rod,Stay wire 7/10 SWG, anchor plate of size 450mm X 450cm X 5 mm thick, thimble, stay clamps, turn buckle ( 20 mm X 60 mm ) and 11 KV strain insulator etc in cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size ) foundation including excavation and refilling etc. as required.complete work in all respect.
26
-
-
... More
Erection of channel iron (four pole SP-55)125 mm X65 mm X 6 mm (13.10 kg per metre), 3.5 meter long for over head line conductor complete with65 mm X65 mm X 8 mm (single iron bracket welded to the channel iron and complete with 65 mm X65 mm X8 mm M.S. flat iron clamps, bolts and nuts including drilling holes for insulator pins, bolts and nuts etc and painting with primer and finish paint as required.complete work in all respect..
4
-
-
... More
Erection of channel iron (Double pole-SP-33)125 mm X65 mm X 6 mm (13.10 kg per metre), 3.5 meter long for over head line conductor complete with 65 mm X65 mm X 8 mm (single iron bracket welded to the channel iron and complete with 65 mm X65 mm X 8 mm M.S. flat iron clamps, bolts and nuts including drilling holes for insulator pins, bolts and nuts etc and painting with primer and finish paint as required.complete work in all respect.
5
-
-
... More
Erection of channel iron (Single pole-SP-33)125 mm X65 mm X 6 mm (13.10 kg per metre), 3.5 meter long for over head line conductor complete with 65 mm X65 mm X 8 mm (single iron bracket welded to the channel iron and complete with 65 mm X65 mm X 8 mm M.S. flat iron clamps, bolts and nuts including drilling holes for insulator pins, bolts and nuts etc and painting with primer and finish paint as required.complete work in all respect.
4
-
-
... More
Erection of four pole 11 Mtr. Long STP 410 SP-55 by Excavation of pit,size 1x1x2.2 meter,Lean concrete 1:3.6 (Hand mixing) stone aggregate 40 mm nominal size ),0.15 mm thick, erection of pole by skid board,rope or mechanical means,concreting in pole pit 1:2:4 (Hand mixed) RCC Grade M20 size 0.8x0.8x2.0 cum (back filling), fixing of Danger plate etc. complete in all respect .
4
-
-
... More
Erection of Double pole 09 Mtr. Long STP 410 SP-33 by Excavation of pit,size 1x1x2.2 meter,Lean concrete 1:3.6 (Hand mixing) stone aggregate 40 mm nominal size ),0.15 mm thick, erection of pole by skid board,rope or mechanical means,concreting in pole pit 1:2:4 (Hand mixed) RCC Grade M20 size 0.8x0.8x2.0 cum (back filling) complete in all respect .
5
-
-
... More
Erection of Single pole 09 Mtr. Long STP 410 SP-33 by Excavation of pit,size 1x1x2.2 meter,Lean concrete 1:3.6 (Hand mixing) stone aggregate 40 mm nominal size ),0.15 mm thick, erection of pole by skid board,rope or mechanical means,concreting in pole pit 1:2:4 (Hand mixed) RCC Grade M20 size 0.8x0.8x2.0 cum (back filling) complete in all respect .
4
-
-
... More
Dismantling of old damaged 11 kv four pole with transportation of material at store site strut embedded in cement concrete foundation etc. as required.
1
-
-
... More
Dismantling of old damaged 11 kv Double pole with transportation of material at store site strut embedded in cement concrete foundation etc. as required.
2
-
-
... More
Dismantling of old damaged span ACSR Raccon conductor,G.I. wire,Disc fitting etc.transportation of material at store site.
0.5
-
-
... More
Supplying & Making indoor cable end termination with heat shrinkable jointing kit complete with all accessories including lugs suitable for following size of 3x120 sq. mm core, A2XFY aluminium conductor cable of 11 KV grade as required .
2
-
-
... More
Supplying & Making outdoor cable end termination with heat shrinkable jointing kit complete with all accessories including lugs suitable for following size of 3x120sq. mm core, A2XFY aluminium conductor cable of 11 KV grade as required .
2
-
-
... More
Laying of one number PVC insulated and PVC sheathed / XLPE power cable of 11 KV grade of following size direct in ground in including excavation, sand cushioning, protective covering and refilling the trench etc as required FOR 3x120SQ MM CABLE
200
-
-
... More
Supply & Painting of 11 Mtr. Long STP 410 SP-55 Four Pole Stracture by applying 02 coat of paint, as given below with ready mixed paint and one coat of primer of approved make, and brand incl. preparation of surface by sand paper/emery paper, cleaning etc. for receiving fresh coat of paint.as required.complete work in all respect.
4
-
-
... More
Installation,Testing & Commisioning of 100 KVA Alu.Wound EE Level-2 Transformer(11/0.4kv)
1
-
-
... More
Supply & Painting of 09 Mtr. Long STP 410 SP-33 Double Pole Stracture by applying 02 coat of paint, as given below with ready mixed paint and one coat of primer of approved make, and brand incl. preparation of surface by sand paper/emery paper, cleaning etc. for receiving fresh coat of paint.as required.complete work in all respect.
5
-
-
... More
Supply & Painting of 09 Mtr. Long STP 410 SP-33 Single Pole Stracture by applying 02 coat of paint, as given below with ready mixed paint and one coat of primer of approved make, and brand incl. preparation of surface by sand paper/emery paper, cleaning etc. for receiving fresh coat of paint.as required.complete work in all respect.
4
-
-
... More
Supply & Fixing of (250x200)mm HT danger notice plate with clamp,nuts & bolts as required.complete work in all respect.As Per Indian Standard Code.
30
-
-
... More
Supplying and fixing Number plate on the existing modular plate & switch box excluding modular plate as required.As Per Indian Standard Code
30
-
-
... More
Erection of 11kv pin insulator (Raccon /Dog conductor ) complete with large steel head G.I. pin, nuts, washers etc.as required.complete work in all respect.
40
-
-
... More
Erection of 11kv polymer Disc insulator(B&S 70 KN) for 11 kv over head lines with galvanised insulator fitting,ball and socket type and complete with galvanised strain clamps, bolts and nuts, washers etc. as required.complete work in all respect.
80
-
-
... More
Erection of Disc Fitting (B&S) Dog/Racoon 70 KN as required.complete work in all respect.
80
-
-
... More
Supplying & Fixing of Barbed Wire as required.complete work in all respect
30
-
-
... More
Erection of Earth Wire 7/16 SWG including binding etc.as required.complete work in all respect.
60
-
-
... More
Fixing of 9 kv Surge/Lighting Arrester as required.complete work in all respect.
6
-
-
... More
Erection & Laying ,Stringing , sagging ,Jumpering of ACSR Raccon conductor for proper comletion of work as required.complete in all respect.
9
-
-
... More
Supplying & fixing of Earthing Rod MS 20x2500 mm including accessories, and providing mansonry enclosure with cover plate having locking arrangement and watering pipe etc. with charcoat/coke and salt etc. as required.complete work in all respect..
30
-
-
... More
Erection of Cross Arm with E-Brackets,clamps ,nuts & Bolt etc. as required complete work in all respect.
4
-
-
... More
Supplying & Erection of Guarding of 33/11 kv Line on road required complete work in all respect.
4
-
-
... More
Supplying & fixing of MS Clamps (Four Pole) complete work in all respect.(M S flat-50mm x8mm) (SP-55)
4
-
-
... More
Supplying & fixing of MS Clamps (Double Pole) complete work in all respect.(M S flat-50mm x8mm) (SP-33)
5
-
-
... More
Supplying & fixing of MS Clamps (Single Pole) complete work in all respect.(M S flat-50mm x8mm) (SP-33)
4
-
-
... More
Pole Protection work
-
-
-
... More
Earth work in excavation for pole protection work:- Excavation in ordinary rock using manual means including loading in a truck and carrying of excavated material to embankment site with a lift upto 1.5 m and lead upto 50 m.
102
-
-
... More
Providing concrete for plain/ reinforced concrete in open foundations complete:- P.C.C grade M 15 Base.
26
-
-
... More
Random Rubble Stone Masonry laid in 1:6 cement and sand mortar, in breast walls, retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc.
898
-
-
... More
Plain/reinforced cement concrete in substructure complete (For height upto 5 m Top concreate by M 20 Nominal mix (1:2:4)
5.2
-
-
... More
Random Rubble Stone Masonry laid Dry, in breast walls, retaining walls, etc. including supply of all material, labour, T&P and royaltiies etc. complete.
173.4
-
-