Uttarakhand Jal Sansthan Tender

View complete overview of Uttarakhand UJS Tender

Uttarakhand Jal Sansthan - UJS Tender

Works
Civil And Construction
Eprocure
Opening Date5 Oct 2024
Closing Date25 Oct 2024
Tender AmountRefer Documents 
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Granular courses

185.2

-

-

... More
Dismantling Brick / Tile work (In cement mortar)

2.88

-

-

... More
Providing of all materials, labour, T&P etc required for diverting and blocking of existing sewer line for execution of work and removing after completion of work.including supply of all materials labour T&P etc required for the proper completion of the work.

92

-

-

... More
Excavation of earth below G.L. by manually or by mechanical means for laying of Sewers, Man-Holes, Gully Pits, Chambers etc. in soil including extra excavation below inverts, trimming & dressing of sides, levelling and back filling of trenches by excavated earth in 20 cm layers,watering and ramming the same including removal of surplus earth or other dismantled material up to a distance of 50 meters from the center of trenches and cleaning of site properly after completion of the work. Excavation by mechanical means shall be restricted upto 90 cm above invert levels at every point of excavation. Excavation from invert levels to 90 cm above shall be done by manually only. excavation in Soil mixed with morum,shingle & kankar etc. using of any specials T&P, if required. 0m to 1.5m BGL

1746.32

-

-

... More
1.5m to 3.0m BGL

357.59

-

-

... More
Supply & Laying - Jointing of following dia. R.C.C. S&S pipes with rubber gaskets to the site of work, lowering the same into trenches below ground level true to alignment, making the joints with rubber gaskets and with necessary spun yarn soaked in bitumen jointing with 1:2 cement mortar in coarse sand including cost of all jointing materials and testing etc. complete but excluding excavation and backfilling of trenches upto ground level. 150mm dia NP-3 Class Pipe, 0 to 1.50m BGL

1018

-

-

... More
150mm dia NP-3 Class Pipe, 1.50 to 3.0m BGL

130

-

-

... More
200mm dia NP-3 Class Pipe, 1.50 to 3.0m BGL

312

-

-

... More
Constructing Brick Masonry Manhole of various dia and depth as per IS :4111 par1( latest amendment) in FPS brick class designation M-100 in Cement Mortar 1:5 (1 cement : 5 coarse sand) including inside and outside 15mm thick plastering in cement mortar 1:3(1 cement : 3 coarse sand) finished with a floating coat of neat cement inside only. The work includes excavation, dewatering, planking, strutting etc. refilling, disposal of surplus earth with all lift and lead of 50m, Including construction of concrete base with PCC 1:4:8 (1 cement : 1 coarse sand : 4 stone aggregate 40mm nominal size), preparation of channel up to the height of'the'pipe and benching in PCC 1:2:4 (1 cement : 2 coarse sand : 4 stone aggregate 20mm nominal size) including neat cement finished, suitable connection of inlet & outlet pipes, testing (water tightness} of manhole, curing etc. complete as per specification and drawing and as per entire satisfaction of Engineer-in-Charge (the depth of manhole will be measured from the invert of the pipe to top of the manhole cover). 900mm internal diameter at bottom,0.90-1.65m depths

63

-

-

... More
1200 mm internal diameter at bottom ,1.65-2.30m depths

6

-

-

... More
Deduction in the depth of the manhole to regulate payments for variation of actual depth of manholes in following sizes. 900mm dia ,0.90-1.65m depths

28.95

-

-

... More
1200 mm dia ,1.65-2.30m depths

2.7

-

-

... More
1:4:8 ( 1cement : 4 c/sand , : 8 gradde stone aggregate 40 mm nominal size. (for restoraion of ramp, stair steps, Drain etc.)

15.8

-

-

... More
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) (for restoration of ramp, stair steps, Drain etc.)

15.8

-

-

... More
Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and technical specifications Clauses 600, 1202 & 1203 in Cement mortar 1:4 (1 cement : 4 coarse sand) (for drain, Stair steps etc)

35.42

-

-

... More
Disposal of surplus earth ,sullage, damaged pipes etc from working site to suitable place,carrying back for refilling of trenches after laying and jointing the pipes upto max distance 60 m one side,disposal of excavated earth from site to suitable place upto max distance 4 km one side including providing of all material, labour, T&P etc., complete required for proper completion of work as per instruction of Engineer in charge.

781.65

-

-

... More
Barricating in two rows and necessary diversion of path and where as necessary with the help of ballies, ropes, flage, signal and light signal caution boards etc.upto a height of 1.8 m as per requirement including supply of all material, T&P etc. complete.

1524

-

-

... More
Shifting of Household sewer Domestic connection including supply of all material ,Labour,T&P etc Required for the proper completion of the work.

114

-

-

... More
Shifting /Repairing of Household water connection coming in the alignment of sewer line/manhole chambers including excavation ,refilling,supply of all material,pipes,specialsetc for sizes 15 to 20 mm,65mm,80mm,100 mm,150mm making good complete as per entire satisfaction of Engineer in charge. (Damaged during work)

114

-

-

... More
Special Cleaning of manhole chambers Including dewatering, lifting of grit,sullage, mud,garbage, etc.and its disposal including all cost of barricating,labour ,T&P etc required complete for proper completion of work. Manhole chamber depth Upto 1.50 mtr

79

-

-

... More
Manhole chamber depth Upto 3.0 mtr

16

-

-

... More
Plain/reinforced cement concrete in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans 1204 for repair work RCC 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) (for repairing work)

63

-

-

... More
Qty of steel in item no 15.1( 1.5% by weight of RCC)

4945.5

-

-

... More
Provision for crossing sewers through existing drains coming across the alignment of sewer including making it good after laying the pipe.

6

-

-

... More
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per Technical Specification Clause 401. For Grading III Material

253.74

-

-

... More
Road Restoration work with PCC 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size)

132.79

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.