Uttar Pradesh Power Transmission Corporation Limited Tender
View complete overview of Uttarakhand UPPTCL Tender
Uttar Pradesh Power Transmission Corporation Limited - UPPTCL Tender
Electrical Generators And Transformers
Electrical and Electronics
Eprocure
Opening Date22 Oct 2022
Closing Date29 Oct 2022
Tender Amount₹ 4,81,000
Costs
EMD
₹ 5,000Document Cost
₹ 1,180Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2022_UPTCL_741683_1Bid Award Id
ViewTender No
Very Short Term E-Tender No. 34/W/ETC(B)/2022-23Tender Authority
Uttar Pradesh Power Transmission Corporation Limited ViewPurchaser Address
-Website
http://https://upenergy.in/upptcl
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
Tender Document, EMD, Tender Cost Copy of UTR No. and Pay in Slip of Transfer of Money through RTGS or NEFT, Experience etc. as per NIT
BOQ Items
... More
Shifting & Proper Stacking of all the dismantled Items i.e. Conservator Tank, Radiators, Pipe Lines, Bushings, Cooling Fans, Marshalling Box, Transformer Oil in Drums etc. of the above dismantled 63MVA Transformer at Safe Storage Place at the Substation (Approx. 100 Meter Distance).
1
-
-
... More
Shifting of Main Tank of the dismantled 63MVA Transformer from its Plinth upto 20 Meter Distance including Turning of the Tank, as Required.
1
-
-
... More
Additional Shifting of Tank of the above dismantled 63MVA Transformer upto Approx. 100 Meter Distance. (1 Job for every 5 Meter or Part thereof)
15
-
-
... More
Shifting of Main Tank of the new 63MVA Transformer to its Plinth from Place of Unloading upto 20 Meter Distance including Turning of the Tank, as Required.
1
-
-
... More
Shifting of Complete Accessories of the 63MVA Transformer including Oil in Drums and Bushings Packed in Wooden Cases / Crates from Unloading Place at the Sub Station to Erection Site in Switchyard (Approx. 50 Meter Distance).
1
-
-
... More
Complete Erection of the new 63MVA Transformer including its Radiators, Conservator Tank, Turrets, HV / LV / Neutral Bushings, Connecting Pipe Lines, Cooling Fans, OLTC Drive Mechanism Box, Marshalling Box, OTI, WTI, Capillary Tubes etc.
1
-
-
... More
Centrifuging / Dehydration of the Complete Transformer Oil Filled in the new 63MVA Transformer with due Circulation of Oil by Ultra High Vacuum Oil Filtration Plant, Un-Interrupted till the Desired BDV Value of the Oil is Achieved including Taking the BDV Values of Oil & IR Values of the Transformer Bushings, Periodically (every 2 hrs.) till the Required Value are Achieved including Attending the Oil Leakages, if any.
21000
-
-
... More
Re-Termination of old Control Cables of the Marshalling Box of alongwith Re-Glanding, Re-Ferruling etc. as per new Cable Schedule.
1
-
-
... More
Laying of Following sizes Additional / New Control Cables for Commissioning of the above new 63MVA Transformer as per Site Requirement :
-
-
-
... More
2 × 2.5 mm2
250
-
-
... More
4 × 2.5 mm2
250
-
-
... More
6 × 2.5 mm2
250
-
-
... More
Termination of Following sizes above Laid Additional / New Control Cables for Commissioning of the above 63MVA Transformer as per Site Requirement :
-
-
-
... More
2 × 2.5 mm2
2
-
-
... More
4 × 2.5 mm2
8
-
-
... More
6 × 2.5 mm2
12
-
-
... More
Making of Delta for Neutral Earthing by due Fabrication of 3 No. 3 Meter long Electrodes of 36 / 40 mm dia. M.S. Round Bar, its Piercing Under the Ground at Equal Distance of 1 Meter at 700 mm depth by Digging of Earth and Connecting all the 3 No. Electrodes with 75 mm × 10 mm size M.S. Flat and Taking out the M.S. Riser by due Cutting, Bending, Welding etc. of the M.S. Flat. (1 Job per Delta)
2
-
-
... More
Earthing of Main Tank, Marshalling Box, OLTC Drive Mechanism Box, Transformer Neutral etc. of the above 63MVA Transformer with the help of 75×10 mm / 50×6 mm size M.S. Flats, its Jointing with already Laid Earth Mat / Deltas at 2 Places with Necessary Modifications in Existing Support Structure for Earthing of the Neutral Bushing and then Painting of the Earthing Strips.
1
-
-
... More
Jumpering of the above new 63MVA Transformer as per Details below :
-
-
-
... More
Jumpering with Single ACSR Panther Conductor and associated Terminal Connectors, P.G. Clamps etc. between HV side Bushings to 132KV Jack Bus Bar Conductors including all associated Equipments in between.
1
-
-
... More
Jumpering with Twin ACSR Moose Conductor and associated Terminal Connectors, P.G. Clamps etc. between LV side Bushings to 33KV CTs including all associated Equipment in between.)
1
-
-
... More
Shifting, loading & unloading of 1 No. Transformer C&R panel from 132KV Substation Usawan to 132KV Substation Budaun.
1
-
-
... More
Dismantling of old 1 No. Transformer C&R panel by opening of all associated control cable and earthing and shifting of above from control room to store.
1
-
-
... More
Erection of new 1 No. Transformer C&R panel with necessary cable laying earthing and cable termination and shifting of above from store to site and other associated works.
1
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements