Pey Jal Nigam Uttarakhand Tender
View complete overview of Uttarakhand Pey Jal Nigam Uttarakhand Tender
Pey Jal Nigam Uttarakhand Tender
Civil And Construction
Consultancy Services
Civil And Architectural Services
Eprocure
Opening Date30 Sep 2024
Closing Date14 Oct 2024
Tender AmountRefer Documents
Costs
EMD
₹ 1,42,000Document Cost
₹ 4,720Tender Fee
Refer Documents
Summary
Supply Installation Testing And Commissioning Of Pumping Plants And Other E And M Appurtenant Works Including Survey Design Checking Of Designs Of Pumping Plants Etc Complete Under Bairaom Dhatigoan Mvs Pumping Water Supply Cheme Of Jjm Block Barakot
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_MDPEY_76472_1Bid Award Id
ViewTender No
1172/G-7/27 Dated 24.09-2024Tender Authority
Pey Jal Nigam Uttarakhand ViewPurchaser Address
-Website
http://http://peyjal.uk.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Supply of Control Panel as Per Specification
1
-
-
POWER WIRING & JOINTING MATERAIAL - 1 Set
(a) 6 mm2 3 core submersible cable - 80Mtr
(b) 25mm2 3.5 core Aluminium Armoured cable - 50Mtr. (c) Jointing material i.e. lugs, tapes etc. - 1 Set (d) Earthing Material - Complete double earthing materials such as earth plate, earth strips. coal salt etc. required as per IE rules
1
-
-
Supply of Main piping and valves as per specification.
1
-
-
Supply of pressure Gauges and compound gauge with fittings as per specification
1
-
-
Supply of Tools.
1
-
-
Supply of Rubber Insulation sheet 1mt. x 2mt.x 0.025
2
-
-
Supply of 63Amp. TPN Main Switch
1
-
-
Supply of of 30KVA 3 phase 415Volt 50 Hz AC cu. Wound automatic voltage regulator (compact) servo controlled stablizer (380- 440 V) with all accessories as per spacification .
1
-
-
Installation, Commissioning & Testing of pumping plant.
1
-
-
Painting
1
-
-
Testing of pumps at manufacture workes and site
1
-
-
Trial Run & Maintenance for six Months
6
-
-
Carting of pumping plant upto site Stage-1st
1
-
-
INTERNAL & EXTERNAL ELECTRIFICATION WORKS STAGE 1st
1
-
-
S.I.T.C. of Centrifugal Pumping Plant with Accessories for IPS (Stage-2nd)
-
-
-
Supply of High head multistage horizontal Centrifugal pumping plant capable to deliver 180 LPM at 260Mts. Head.
Supply of Induction motor T.E.F.C 2900 RPM operating at 415± 10% volts 3 phase 50C/S A.C. supply Suitable for above pump.
Supply of M.S. fabricated base plate for above pump and motor set, coupling and coupling guard.
2
-
-
Supply of Fully automatic Auto Transformer starter as per Specification.
2
-
-
Supply of Control Panel as Per Specification
1
-
-
POWER WIRING & JOINTING MATERAIAL - 1 Set
(a) 10 mm2 3 core submersible cable - 80Mtr. (b)35mm2 3.5 core Aluminium Armoured cable - 50Mtr. (c) Jointing material i.e. lugs, tapes etc. - 1 Set (d)Earthing Material - Complete double earthing materials such as earth plate, earth strips. coal salt etc. required as per IE rules
1
-
-
Supply of Main piping and valves as per specification.
1
-
-
Supply of pressure Gauges and compound gauge with fittings as per specification
1
-
-
Supply of Tools.
1
-
-
Supply of Rubber Insulation sheet 1mt. x 2mt.x 0.025
2
-
-
Supply of 63Amp. TPN Main Switch
1
-
-
Supply of of 50 KVA 3 phase 415Volt 50 Hz AC cu. Wound automatic voltage regulator (compact) servo controlled stablizer (380- 440 V) with all accessories as per spacification .
1
-
-
Installation, Commissioning & Testing of pumping plant.
1
-
-
Testing of pumps at manufacture works and site
1
-
-
Painting
1
-
-
Trial Run & Maintenance for six Months
6
-
-
Carting of pumping plant upto site Stage-2nd.
1
-
-
INTERNAL & EXTERNAL ELECTRIFICATION WORKS STAGE 2nd
1
-
-