Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited - UPRVUNL Tender
Electrical Generators And Transformers
Electrical and Electronics
Eprocure
Opening Date3 Nov 2022
Closing Date21 Nov 2022
Tender Amount₹ 13,67,040
Costs
EMD
₹ 26,000Document Cost
₹ 1,180Tender Fee
Refer Documents
Summary
Routine, Maintenance Up-keeping Of Ht Lt Transformers Along With Breakdown Maintenance Of Ht/lt
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2022_RVUNL_738084_2Bid Award Id
ViewTender No
T-05/OMC-IV/EMD-I/CTPS/PTPPTender Authority
Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited ViewPurchaser Address
-Website
http://https://uprvunl.org/uprvunl
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Checking of oil level in 220/400 KV bushing.
1
-
-
Proper cleaning of 220/400 KV bushing with suitable cleaning agent to restore its shining.
1
-
-
Draining of Transformer oil upto required level from the main tank of transformer in available Transformer oil barrels/Tank etc.
1
-
-
Centrifuging of Transformer oil using filtration plant provided by the Deptt. (* hrs shift)
8
-
-
Filling/topping up of Transformer oil in HT/LT transformers.
1
-
-
Opening & closing of Inspection cover of HT Transformer.
1
-
-
Removal & reconnection of 220/400 KV bushing connection with Transformer winding of GT/ST.
1
-
-
Shifting of 220/400 KV bushing from central store to G.T./S.T. Transformer yard/shifting of damaged bushing from side to the place to be intimated.
1
-
-
Removal & installation of 220/400 KV bushing.
1
-
-
Replacement of worn out/damaged gasket of marshaling box cover as per the size of original gasket by applying rubber solution after removing old worn out/damaged gasket. a. HT Transformer
1
-
-
b. LT Transformer
1
-
-
Filling of Transformer oil in 220/400 KV bushing by erecting scaffolding & removal after completion of work.
1
-
-
Arresting oil leakages from HT/LT Transformers by tightening flanges or applying M-seal / Devcon make titanium putty.
1
-
-
Checking & servicing of Magnetic oil gauge as per scope of work Sl. No. 1 to 7.
1
-
-
Overhauling of OLTC operating system of GT/ST as per scope of work Sl. No. 1 to 9.
1
-
-
Delinking & relinking Generator phase or Neutral side 16.5 KV bushing connection from IP busduct.
1
-
-
Delinking & relinking Generator transformer from IP busduct.
1
-
-
Delinking & relinking of 16.5 KV bushing of UAT from IP busduct.
1
-
-
Delinking & relinking of PTSP form IP busduct.
1
-
-
Delinking & relinking of 16.5 KV bushing connection from Transformer winding of (a) Generator Transformer
1
-
-
(b) Unit Auxiliary Transformer
1
-
-
Shifting of 16.5 KV bushing from central store to G.T./S.T. Transformer yard.
1
-
-
Removal & installation of 16.5 KV bushing.
1
-
-
Removal & Installation of rubber bellow of IP busduct after shifting of rubber bellow from CSD store to site.
1
-
-
Opening & closing of upper manhole of SP busduct of UAT/Station Transformer.
1
-
-
Opening & closing of lower manhole of SP busduct of UAT/ Station Transformer.
1
-
-
Opening & closing of upper manhole of IP busduct.
1
-
-
Opening & closing of lower manhole of IP busduct.
1
-
-
Partitioning & reconnection of SP busduct.
1
-
-
Opening & closing of rubber bellow/ring of IP busduct.
1
-
-
Opening & closing of rubber bellow of SP busduct.
1
-
-
Cleaning of 16.5 KV support insulator inside IP busduct with petrol/CTC.
1
-
-
Cleaning of 6.6 KV support insulator/seal of bushing inside SP busduct with Petrol/CTC.
1
-
-
Removal & installation of 6.6 KV bushing of UAT/Station T/F.
1
-
-
Removal & installation of 16.5 KV support insulators inside IP busduct.
1
-
-
Removal & installation of 6.6 KV support insulators inside SP busduct.
1
-
-
Removal & installation of 6.6 KV seal of bushing inside SP busduct.
1
-
-
Delinking & relinking of 6.6 KV bushing of station Transformer or UAT from SP busduct.
1
-
-
Opening & closing of upper manhole of 0.4 KV side NSP busduct of LT Transformer.
1
-
-
Opening & closing of lower manhole of 0.4 KV side SP busduct of LT Transformer.
1
-
-
Cleaning of 0.4 KV support insulator inside NSP busduct of LT Transformer.
1
-
-
Removal & installation of 6.6 KV bushing of L.T. Transformer.
1
-
-
Removal & installation of 0.4 KV bushing of L.T. Transformer.
1
-
-
Removal & installation of 0.4 KV support insulator inside busduct of L.T. Transformers
1
-
-
Cleaning & servicing of dry type transformer as per scope of work mentioned at Sl. No. 01 to 07. (a) 6.6/0.4 KV 2500 KVA Dry type Transformer
1
-
-
(b) 6.6/0.4 KV 2000 KVA Dry type Transformer
1
-
-
(c) 6.6/0.4 KV 1600 KVA Dry type Transformer
1
-
-
(d) 6.6/0.4 KV 1000 KVA Dry type Transformer
1
-
-
Drying out of LV Bushings / Seal off Bushings of Generator / GT/ ST/UAT and bring IR values upto the mark as per instruction of AE/JE.
1
-
-
Cleaning of HT Transformers after completion of centrifuging/ overhauling work. (a) Generator Transformer
1
-
-
(b) Station Transformer
1
-
-
(c) Unit Auxiliary Transformer
1
-
-
Overhauling of LT Transformer as per scope of work mentioned at Sl. No. 01 to 15. (a) 6.6/0.4 KV 1000 KVA Transformer
1
-
-
b) 6.6/0.4 KV 1600 KVA Transformer
1
-
-
(c) 6.6/0.4 KV 2000 KVA Transformer
1
-
-
(d) 6.6/0.4 KV 2500 KVA Transformer
1
-
-
Overhauling of Marshalling Boxes of HT Transformers.
1
-
-
Overhauling of Marshalling Boxes of LT Transformers.
1
-
-
Cleaning & checking of C.T. & tightening of C.T. connection inside IP Busduct.
1
-
-
Checking of space Heaters inside the SP Busduct.
1
-
-
Dismantling / remounting of PRV of Generator Transformer or station Transformer or Unit Auxiliary Transformer for its checking or replacement.
1
-
-
Dismantling & remounting of Buchholz Relay of Generator Transformer or station Transformer or Unit Auxiliary Transformer for checking or replacement.
1
-
-
Dismantling & remounting of surge Relay of Generator Transformer or station Transformer for checking or replacement.
1
-
-
Dismantling & remounting of Buchholz Relay of LT transformers.
1
-
-
Shifting of filtration plant and storage tank from transformer yard of Unit No.5 to that of Unit No. 6 or vice versa.
1
-
-
Cleaning of 10 KL capacity transformer oil tank.
1
-
-
Filling of air in the tyres of filtration plant and oil storage tank.
1
-
-
CLEANING AND PAINTING OF VARIOUS ELECTRICAL EQUIPMENTS IN TRANSFORMER YARD.
1
-
-
Cleaning/drying out of flexible links of Generator/GT /ST /UAT.
1
-
-
Removal of top cover of L.T. Transformer & installation after completing work.
1
-
-
Replacement of top cover cork sheet gasket of L.T. Transformer.
1
-
-
Cleaning, checking and tightening of electrical components and PT inside SVPT as per scope of work from Sl. No. 1 to 11.
1
-
-
Cleaning, checking and tightening of neutral grounding system of generator including Neutral grounding Transformer as per scope of work from Sl. No. 1 to 11.
1
-
-
Shifting of new transformer oil filled drums from central store/ any site within Plant to transformer yard/shifting of old Transformer oil filled drum from site to CSD store or at the assigned site.
1
-
-
Tightening of upper manhole of IP/SP busduct.
1
-
-
Tightening of lower manhole of IP/SP busduct.
1
-
-
Shifting of empty Transformer oil drums from site to CSD store.
1
-
-
Cleaning and Maintenance of Centrifuging Machine (a) Internal And external Cleaning of Centrifuging machine
1
-
-
b) Replacement of filter by new one.
1
-
-
c) Replacement of heaters
1
-
-
d) Rectification of control and instrumentation problems of starting panels of centrifuging machine.
1
-
-
e) Changing of various Gaskets.
1
-
-
Cleaning and painting of various electrical equipments in transformer yard.
1
-
-
Disconnection & reconnection of (a) Neutral Grounding Transformer of Generator.
1
-
-
(b) Neutral Grounding of Generator Transformer.
1
-
-
(c) Neutral Grounding of station Transformer.
1
-
-
(d) Neutral Grounding of UAT.
1
-
-
Removal of 3 Phase LT motor from its foundation and installation after completion of work. (a) 0.37 KW to 1.0 KW
1
-
-
(b) 1.1 KW to 1.5 KW
1
-
-
(c) 2.2 KW to 3.75 KW
1
-
-
(d) 7.5 KW
1
-
-
(e) 11 KW
1
-
-
Removal and installation of fan/coupling/ bearing from /on rotor shaft. (a) 0.37 KW to 1.0 KW
1
-
-
(b) 1.1 KW to 1.5 KW
1
-
-
(c) 2.2 KW to 3.75 KW
1
-
-
(d) 7.5 KW
1
-
-
(e) 11 KW
1
-
-
O/H of 3 Phase LT motor by shifting, dismantling, assembling & reshifting to its foundations for installation. (a) 0.37 KW to 1.0 KW
1
-
-
(b) 1.1 KW to 1.5 KW
1
-
-
(c) 2.2 KW to 3.75 KW
1
-
-
(d) 7.5 KW
1
-
-
(e) 11 KW
1
-
-
Rewinding of 3 Phase LT motor with new copper wire exactly similar to original winding. (a) 0.37 KW to 1.0 KW
1
-
-
(b) 1.1 KW to 1.5 KW
1
-
-
(c) 2.2 KW to 3.75 KW
1
-
-
(d) 7.5 KW
1
-
-
(e) 11 KW
1
-
-
Repairing of DE/NDE side bearing housing by remetallizing & machining to original size. (a) 0.37 KW to 1.0 KW
1
-
-
(b) 1.1 KW to 1.5 KW
1
-
-
(c) 2.2 KW to 3.75 KW
1
-
-
(d) 7.5 KW
1
-
-
(e) 11 KW
1
-
-
Repairing of DE or NDE side bearing sheet by remetallizing & machining to original size. (a) 0.37 KW to 1.0 KW
1
-
-
(b) 1.1 KW to 1.5 KW
1
-
-
(c) 2.2 KW to 3.75 KW
1
-
-
(d) 7.5 KW
1
-
-
(e) 11 KW
1
-
-