Uttar Pradesh Power Transmission Corporation Limited Tender

If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search &amp; bid for etender UP.

Uttar Pradesh Power Transmission Corporation Limited - UPPTCL Tender

Works
Civil And Construction
Building Construction
Eprocure
Opening Date13 Dec 2024
Closing Date3 Jan 2025
Tender Amount₹ 21,87,428 
Notes
Download

Costs

Summary

Increasing Capacity At Vaishali Sub-station

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Dismantling of 132 KV Bus/Tendom Isolator

4

-

-

... More
Dismantling of 120 KV L.A

6

-

-

... More
Dismantling of 132/33 KV C&R Panel with control cable

2

-

-

... More
Dismantling of 33 KV Circuit Breaker

2

-

-

... More
Dismantling of 30 KV L.A

6

-

-

... More
Erection of following bay equipment as per instruction manual of various equipment’s and technical specification including shifting of material / equipment from store to erection site including all other associated works to complete the job satisfactorily.

-

-

-

... More
Erection & Commissioning of 145KV, 2000A, 40KA, SF6 Circuit Breaker with timing test and report

1

-

-

... More
Erection of 145 Kv CT Ratio 400-200-100-01 A ,0.2 Class, 3 Core With Terminal Connector & installation of junction box.

6

-

-

... More
Erection of 120 Kv, 10 KA, Surge Arresters

6

-

-

... More
Erection of 145 Kv, 1250 A, 31.5 KA,Motorised Isolator (BI).

2

-

-

... More
Erection of 145 Kv, 1250 A, 31.5 KA ,Motorised Isolator (TI).

2

-

-

... More
Erection & Commissioning of VCB,36KV,2000A,31.5KA/3SEC

2

-

-

... More
Erection of 30 Kv Surge Arresters

6

-

-

... More
Erection of 33 Kv CT Ratio 2000-1250/01 A ,0.2 Class, 3 Core With Terminal Connector & installation of junction box.

6

-

-

... More
Erection of following control and relay Panels as per instruction manual/Hydra and technical specification including shifting of panel from store to erection site First Floor on Control Room including all other associated works to complete the job satisfactorily.

-

-

-

... More
Installation, Commissioning & Testing of 132/33 KV control Relay panel for 63 MVA Transformer.

2

-

-

... More
Bay wise interconnection of equipment with specified conductor of various 132 KV & 33 KV Equipment with Main /Transfer / jack Bus bar of ACSR Zebra /Panther conductor. The work Includes cutting of conductor. Bending in proper shape clamping with the help of clamp and all other associated work to complete job.

-

-

-

... More
132 KV Side Jumper with 132 KV Equipments.

80

-

-

... More
33 KV side jumper with 33KV Equipments.

70

-

-

... More
Laying and Termination of following size control cable in trench/cable trays from different control room equipment to 132&33 KV Isolator, circuit breakers CT/PT & their junction boxes. Transformer marshaling box. Isolator box & other outdoor equipment’s installed in 132/33 KV switch yard as per cable schedule with ferruls and lugs . Including carriage of cable drum from store and all other associated work.

-

-

-

... More
Control cable of size 2 core x 2.5 mm2

612

-

-

... More
Control cable of size 4 core x 2.5 mm2

990

-

-

... More
Control cable of size 6 core x 2.5 mm2

920

-

-

... More
Control cable of size 10 core x 2.5 mm2

960

-

-

... More
Termination of control cable

536

-

-

... More
Painting & Earthing of equipment’s by cutting straightening, bending, laying 700mm below ground and above ground of following size of MS flat for earthing of main and auxiliary structure, equipment’s structure. Transformer body and its neutral point including welding with main earthmat and with object to be earthed excavation of trenches its back filling. All other associated work as required to complete the work(MS flat will be provided by UPPTCL).

-

-

-

... More
Laying of MS Flat of size 75x10 mm

100

-

-

... More
Laying of MS Flat of size 50x6 mm

100

-

-

... More
Erection of 63 MVA Transformers

-

-

-

... More
Shifting of 63MVA Transformer main tank from unloading site to transformer plinth at 132KV S/S Vaishali approx. distance 20mtrs

2

-

-

... More
Complete, erection of new 63 MVA T/F work includes erection of radiator, conservator tank, bushing with its turrets (if available) connecting of all oil pipe line, erection of cooling fans, making control cables connection, buchholz relay etc. for completing the work, topping of T /F oil and final oil filling in tank, radiator, conservator tank and all other associated work for completion of job satisfactorialy.

2

-

-

... More
Earthing of main tank of new 63 MVA T /F by using M.S. flat 50X6 / 75X10 mm size, it’s jointing with already laid earth mat / Deltas. Neutral bushing support for its earthing work.

2

-

-

... More
Erection of new RTCC panel of this new 63 MVA T /F in control room at 132KV S/S VAISHALI

2

-

-

... More
Centrifuging of complete T/F oil in T/F by connecting centrifuging pipes circulating the T/F oil through PVT. centrifuging machine and taking the BDV/Water Content (PPM) value of the oil periodically till the required value is achieved .Approx. 22KL per T/F

44

-

-

... More
Pre charging testing of Transformer with duly calibrated instruments along with proper submission of test reports including but not limited to following tests: 1. WRM 2. Turns ratio measurement 3. Tan Delta 4. SFRA 5. PIR tests

2

-

-

... More
Dismantling of 40 MVA Transformers

-

-

-

... More
Dismantling of 132/33KV, 40MVA Transformer at 132KV Substation Vaishali by dismantling the accessories, radiator, marshaling box etc

2

-

-

... More
Partly drain out Transformer oil from tank, opening of Electrical connections etc

2

-

-

... More
Shifting of 40MVA Transformer main tank from unloading site to transformer plinth at 132KV S/S Vaishali approx. distance 20mtrs

2

-

-

... More
Additional Shifting 80M @ 5M per job

16

-

-

... More
Packing of HV/LV/Neutral bushings into empty wooden crates

2

-

-

... More
Loading, Carriage and Unloading for 63 MVA Transformers

-

-

-

... More
Loading of 63 MVA T/F main tank along with accessories, making the wooden sleeper plate from jacking the T/F tank up to trailer height placing the rail under T/F tank and shifted up on trailer, removed the rail under T/F tank and proper tightening the main tank with trailer bad with the help of steel rope and turn buckle.

2

-

-

... More
Carriage of 63 MVA T/F tank from 220 KV Sub-station Sec-129 Noida to 132 KV Sub Station Vashali & carriage of all accessories by Pvt. Truck / Multi Axle Trailer . Distance about 30 Km.

2

-

-

... More
Opening of latching of main tank of 63 MVA Transformer loaded on Trailer jacking the tank for packing the rail under the T/F tank and shifting it of wooden to plate form, Removing the rail under the T/F tank on wooden sleeper, lowering the tank towards ground by slowly and removing the wooden sleeper under the tank and unloading of various Transformer accessories of above 63 MVA T/F like oil filled drums, bushing conservator tank, cooling fan etc. from Track/ Trailer at site 132 KV S/S Vaishali.

2

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements

Past Bidders
This list is curated from the bidders of the similar tenders in the past

Unlock the Tender details for free
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
  • Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
  • Awarded Ratexx%
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.