Uttar Pradesh Power Transmission Corporation Limited Tender
... More
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of etender.up.nic.in - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Uttar Pradesh Power Transmission Corporation Limited - UPPTCL Tender
Eprocure
Opening Date29 Aug 2019
Closing Date30 Sep 2019
Tender Amount₹ 3,65,270 This is an estimated amount, exact amount may vary.
Costs
EMD
₹ 4,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2019_UPTCL_376343_1Bid Award Id
ViewTender No
78-ETC-I(A)/ 2019-20Tender Authority
Uttar Pradesh Power Transmission Corporation Limited ViewPurchaser Address
-Website
http://https://upenergy.in/upptcl
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Up to 20 Meters
1
-
-
... More
Additional shifting of T/F (01Job for every 5 meter).
6
-
-
... More
Dismantling of 132KV LA by opening of jumpers and cutting of earthing etc. Then erection of same 132 KV LA after shifting of 63 MVA Transformer and associated work to complete the job.
1
-
-
... More
Dismantling of 33 KV LA by opening of jumpers and cutting of earthing etc. Then erection of same 33 KV LA after shifting of 63 MVA Transformer and associaated work to complete the job.
1
-
-
... More
Shifting of main tank of new 63MVA transformer from unloaded platform to plinth of dismantled 40MVA T/F-I including turning of tank if required, including men, T&P and all other associated works also if required to complete the job satisfactorily at 132 KV Substation Soraon, Prayagraj.
-
-
-
... More
Up to 20 Meters
1
-
-
... More
Additional shifting of T/F (01Job for every 5 meter).
8
-
-
... More
Complete erection of 63MVA transformer by erection of its radiators, conservator tank, all bushings, their turrets connecting oil pipe lines, cooling fans, motor drive mechanism of tap changer, oil pumps and associated oil pipe lines etc to complete the job satisfactorily including first filling of oil and topping up of transformer oil (Not circulation) in tank radiators oil pipe lines conservator tank etc and attending the oil leakage, if any, and all other associated works for satisfactory completion of work at 132KV S/S Soraon contractor shall provide all assistance in getting the transformer successfully commissioned by providing qualified manpower till commissioning including the cost of all men, T&P and associated arrangements.
1
-
-
... More
Centrifuging of complete transformer oil of 01 No 63MVA transformer in transformer tank or oil tanker by connecting centrifuging pipes, circulating the transformer oil through centrifuging machine to be provided by the contractor and taking the BDV values of the oil periodically till the required value of the oil is achieved as per direction of supervising Engineer. All T&P, labor, centrifuging machine & other associated arrangements shall be provided by the contractor at his own cost.
22000
-
-
... More
Connection of the control cable as per the new cable schedule of new 63 MVA T/F and its OLTC/RTCC panel, C&R panel, cooling fans & pumps, marshalling box etc. using existing cable including laying, dressing & binding of additional cable. If required as per site requiement and termination alongwith fixing of glands and ferruling as per technical specification.
1
-
-
... More
Earthing of main tank of 63MVA transformer by using M.S.flat of size 75x12 mm , its jointing with already laid earth mat/deltas. Preparing neutral bushing support excavation of trenches for earthing work, its back filling etc.M.S.flat will be provided by contractor at his own cost.
30
-
-
... More
Delta earthing of 63 MVA Transformer HV/LV neutral bushing by using M.S. flat 75x10 mm and earthing electrodes including its painting of MS flat with one coat of red oxide primer and two coat of bus green enameled paint.
2
-
-
... More
Jumpering of new 63 MVA Transformer at HV and LV side with Moose/Zebra conductor.
1
-
-
... More
Proper packing of HV/LV bushing of 40 MVA Transformer including proper wrapping with polythene paper sheet in the wooden crate.