Uttar Pradesh Power Transmission Corporation Limited Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Uttar Pradesh Power Transmission Corporation Limited - UPPTCL Tender
Electrical Generators And Transformers
Electrical and Electronics
Eprocure
Opening Date26 Nov 2024
Closing Date17 Dec 2024
Tender Amount₹ 4,00,000
Costs
EMD
₹ 4,000Document Cost
₹ 590Tender Fee
Refer Documents
Summary
Installation, Erection,testing, Commissioning Of 132/33 Kv 100 Mva Transformer In Place Of 63 Mva T/f-i (tal Make) Against Restoration From De-rated Capacity Including All Other Associated Works At 220 Kv S/s Sector-129 Noida Under Etd-i Noida.
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_UPTCL_977372_1Tender No
E-T-11/ETCN/2024-25Tender Authority
Uttar Pradesh Power Transmission Corporation Limited ViewPurchaser Address
-Website
http://https://upenergy.in/upptcl
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
a) Upto 20 Mtrs distance
1
-
-
Shifting/Dragging of Main Tank of 100 MVA , 132/33kV T/F from road to T/F Plinth as per the direction of site incharge at 220 kV Sub-Station Sec-129, Noida
-
-
-
a) Upto 20 Mtrs distance
1
-
-
Complete safe erection of New 100 MVA , 132/33kV T/F including all Bushings & their Turrets, A-Frames with headers (incuiding alignments), Radiator banks, Conservator Tank, connecting oil pipe lines, motor driven mechanism of Tap Changer, Marshalling Box and associated pipe line etc. to complete the job satisfactorily.
1
-
-
Hot Oil Circulation of T/F oil of New 100 MVA , 132/33kV T/F in Main Tank, Radiators or Oil Tanker by connecting 6/12 KL Centrifuging Machine with New Filters for dehydration of oil, Windings etc. and taking & recording BDV values of oil and IR values of transformer windings periodically till the required value is reached including filling & topping up of oil in Main Tank, Radiators, Conservator Tank, OLTCs etc. as per direction of Supervising Engineer/standard practices.
26
-
-
Earthing with 75x10/50x6mm M.S flat of 100 MVA , 132/33kV T/F Main tank at two points, Neutral 'Bushings, Drive mechanism etc. of T/F and connection with existing Earth Mat / Delta along with necessary modification , jointing/ welding are required including painting by green paint in two coats. (MS Flat shall be arranged by the Department.)
1
-
-
Connecting of jumpers of 132 kV & 33 kV side of connectors and clamps /PG clamps including changing of jumpers if required etc. along with necessary modification in LA support structure and all other associated works to complete the job.
6
-
-
Erection of RTCC Panel of New 100 MVA , 132/33kV T/F ( TAL make) including its earthing & connection of existing Control Cables already identified along with shifting from store to control room. Laying of additional control cables is also to be done as per site requirement if required.
Note: Making of Cable schedule will be under contractors' scope.
1
-
-
Connection & necessary additional laying of control cables including glanding & termination between Turrets WTI, OTI, Buchholtz relays, PRV, Cooling fans, oil pumps, OLTC, Marshaling box, RTCC etc. with proper ferruling as per drawing/ site requirement.
Note: Making of Cable schedule will be under contractors' scope.
1
-
-
Pre-Charging testing of transformer, if required, as per standard technical specifications with duly calibrated testing instrument, as required by the transformer manufacture along with prepration and submission of test-reports, including but not limited to following test: 1. Winding Resistance Measurement 2. Turns Ratio Measurement 3. Tan-Delta Measurement of Winding and Bushings 4. SFRA Testing of Transformer
1
-
-
Sampling and testing of transformer, if required, oil at CPRI or any other NABL accredited testing lab including cost of transportation of each sample in standard sampling bottles (adequate number of bottles to be arranged by contractor). Samples to be taken at required intervals (as per actual requirement)-Following tests are to be conducted for eaeh sample-1.Breakdown voltage 2. Moisture Content, 3. Dissolved Gas Analysis.
2
-
-
Submission of inspection charges for Electrical Safety Clearance from Directorate of Electricat Safety, Lucknow, Uttar Pradesh for carrying out inspection of above 100MVA TF Transfromer and obtaining charging clearance as per statutory norms (Amount to be reimbursed on actual basis)
1
-
-
4. SFRA Testing of Transformer
-
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements
Past BiddersThis list is curated from the bidders of the similar tenders in the past
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%