If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Uttar Pradesh Power Transmission Corporation Limited - UPPTCL Tender
Eprocure
Opening Date28 Mar 2019
Closing Date4 Apr 2019
Tender Amount₹ 4,66,320 This is an estimated amount, exact amount may vary.
Costs
EMD
₹ 6,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2019_UPTCL_340844_1Bid Award Id
ViewTender No
246-ETC-I(A)/2018-2019Tender Authority
Uttar Pradesh Power Transmission Corporation Limited ViewPurchaser Address
-Website
http://https://upenergy.in/upptcl
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Affitional shifting of 40 MVA Transformer for 60 meters @ 05 mtr./job.
12
-
-
... More
Dismantling of 132 KV LA Opening of jumpers, cutting of earthing etc. then erection of same 132 KV LA after shifting of 63 MVA Transformer and related associated work to complete the job.
1
-
-
... More
Dismantling of 33 KV LA by opening of jumpers and cutting of earthing etc. then erection of same 33 KV LA after shifting of 63 MVA Transformer & related associated work to complete the job.
1
-
-
... More
Shifting of main tank of new 63 MVA Transformer from unloading place upto plinth including turning of tank if required upto 20 meters with all T&P and work required to complete the job.
1
-
-
... More
Additional shifting of 63 MVA Transformer for 80 meters @ 05 meter/job
16
-
-
... More
Complete erection of new 63 MVA transformer by erection of radiators, conservator tank, all bushing, with their turrets connecting oil pipe lines, cooling fans, motor drive mechanism of tap changer, RTCC panels etc. to complete the job satisfactorily including first filling of oil and topping up of transformer oil in tank, radiators, oil pipe lines, conservator tank etc. and all other associated works for satisfactory completion of work including all arrangement of T&P and man power.
1
-
-
... More
Centrifuging of complete new transformer oil of 63 MVA transformer in transformer tank by connecting centrifuging pipes, circulating the transformer oil through centrifuging machine, to be provided by the contractor and taking the BDV values of the oil periodically till the required value is achieved as per direction of supervising Engineer. All T&P, labor, centrifuging machine shall be provided by the contractor at his own cost during the work.
22000
-
-
... More
Connection of the control cables as per the new cable schedule of new 63 MVA Transformer & its OLTC/RTCC panel, C&R panel, cololing fans & pumps, marshalling box etc. using existing cables including laying, dressing & binding of additional cables, if required as per site requirement and termination alongwith fixing of glands and ferruling as per technical specification.
1
-
-
... More
Earthing of new 63 MVA Transformer main body at two points by using M.S. Flat 75x10 mm and connected with marshalling box and drive mechanism OLTpanel, providing the wheel stopper, making the delta points for neutral and connection with MS Flat as per site reqiurement. (M.S. flat will be provided by UPPTCL).
1
-
-
... More
Delta earthing of 63 MVA Transformer HV/LV neutral bushing by using M.S. flat 75x10 mm MS flat and earthing electrodes including its painting of MS flat with one coat of red oxide primer and two coats of bus green enameled paint.
2
-
-
... More
Jumpering of new 63 MVA Transformer at HV and LV side with Moose/Zebra conductor.
1
-
-
... More
Proper packing of HV/LV bushing of 40 MVA Transformer including proper wrapping with polythene/paper sheets in the wooden crate got emptied after taking out bushing of 63 MVA Transformer.
1
-
-
... More
Dismantling of 33 KV old CTs (800-400/1Amp) and erection of new 33 KV CT (200-12500/1Amp) with cable termination including earthing if the CTs shifting of dismantled CTs from site to store and other associated work.
1
-
-
... More
Commissioning and testing of 63 MVA Transformer by arranging appropriate equpments for following testing ; - BDV, PPM, DGA, TAN DELTA.
1
-
-