Rajya Krishi Utpadan Mandi Parishad Tender
... More
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of etender.up.nic.in - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Rajya Krishi Utpadan Mandi Parishad - RKUMP Tender
Civil And Construction
Road Construction
Eprocure
Opening Date7 Mar 2025
Closing Date22 Mar 2025
Tender Amount₹ 1,21,21,909.12 This is an estimated amount, exact amount may vary.
Costs
EMD
₹ 8,45,000Document Cost
₹ 22,892Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2025_RKUMP_1012539_1Tender No
N.K./Lko/E-Nivida/2025-1989 Dated 01.03.2025Tender Authority
Rajya Krishi Utpadan Mandi Parishad ViewPurchaser Address
-Website
http://etender.up.nic.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Providing and applying tack coat with Bitumen VG-10 BULK using emulsion distributor at the rate of 0.30 kg per sqm on the prepared bituminous surface cleaned with Hydraulic broom as per Technical Specification Clause 503.
8700
15
132240
... More
Providing, laying and rolling of open graded mix carpet of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade bitumen or imulsion to required line, grade and level to serve as wearing course on apreviously prepared base , including mixing in a suitable plant, laying and rolling with a three wheeled 80-100 KN static roller capacity, finished to required level and grades to be followed by seal coat of type C as per Technical specification clause 508 (By Hot Mix Method)
8700
186
1621680
... More
Providing, and laying sealing the voids in a bituminous surface laid to the specified levels grade and cross fall using type C as per Technical specification clause 510
8700
69
600300
... More
Brick edging on both sides of the road with M-150 bricks 8 cm wide and 11.5 cm deep laid with mud mortar including cost of bricks all labour finished to be required template and in proper alignment T&P and also including dressing and ramming the excavated earth as per direction of Engineer in Charge. (SINo. 765)
2.9
88000
255200
... More
Supply & laying of 350mm dia N.P.-3 class Hume pipes in position and proper alignment including supply of all materias, labour and T&P etc. required for proper completion of work.(N.S)
30
1600
48000
... More
Providing and fixing of Recto reflective steel sign board as per drawing design including writing of details as specified by Engineer in charge. including supply of all materials, labour T&P, cartage upto site complete in all respect required for proper completion of the work and as per direction of E/I.(SOR Banda 2020-21)
1
8000
8000
... More
Maintenance cost of 1st year @ 0% cost of work on item No.1 to 9
1
-
-
... More
Maintenance cost of 2ndyear @1% cost of work on item No.1 to 9
1
70080
70080.54
... More
Maintenance cost of 3rd year @1.50% cost of work on item No.1 to 9
1
105120
105120.81
... More
Maintenance cost of 4th year @2.00% cost of work on item No.1 to 9
1
140161
140161.08
... More
Maintenance cost of 5th year @3.00% cost of work on item No.1 to 9
1
210241
210241.62
... More
Providing , laying ,spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-0100 kN static roller in stages to proper grade and camber, applying and brooming , crushable screening to fill up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405
236.25
5096
1203930
... More
Earth work in surface excavation not exceeding 30 cm in depth but exceeding 1.5 m in width as well as 10 sqm on plan including getting out and disposal of excavated earth upto 50 m and lift upto 1.5 m as directed by the E/I . All Kinds of soil..(SI )
231
135
31185
... More
First class brick work in 1:4 cement and coase sand mortar in foundation and plinth including suplly of all material, labour and T&P etc, required for proper completion.
156.17
5240
818330.8
... More
12mm thick plaster 1:4 cement and coarse sand mortar over brick workincluding supply of all materials, labour and T&P etc. required for proper completion of work. (SI 584 (i))
630
180
113400
... More
Laying C.C. on edging toewall consisting of 1:2:4 cement, coarse sand and approved 2 cm (1.5) guage stone ballast.
29.82
7185
214256.7
... More
providing and laying interlocking tiles 80 mm thick of approved quality finished to required template and in proper alingment as directed by the Engineer in charge
2100
980
2058000
... More
Construction of embankment in ordianry soil with approved material obtained from available land as permitted and approved by Engineer-in-charge and as per Technical Speciation clause 301.3.4.1 with all lifts and leads, spreading, grading to required slope and compacting to meet requirement of tables 300.1 and 300.2 as per Technical Specification clause 301.5
392
95
37240
... More
Maintenance cost of 2ndyear @1% cost of work on item No.15 to 21
1
11190
11190.86
... More
Maintenance cost of 3rd year @1.50% cost of work on item No.15 to 21
1
22381
22381.71
... More
Maintenance cost of 4th year @2.00% cost of work on item No.15 to 21
1
33572
33572.57
... More
Maintenance cost of 5th year @3.00% cost of work on item No.15 to 21
1
44763
44763.43
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements
Past BiddersThis list is curated from the bidders of the similar tenders in the past
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%