Purvanchal Vidyut Vitaran Nigam Limited Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Purvanchal Vidyut Vitaran Nigam Limited - PUVVNL Tender
Electrical and Electronics
Eprocure
Opening Date21 Jun 2024
Closing Date3 Jul 2024
Tender Amount₹ 35,32,042
Costs
EMD
₹ 35,300Document Cost
₹ 3,540Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_PVVNV_919063_2Tender No
95/EDC(M)/23-24Tender Authority
Purvanchal Vidyut Vitaran Nigam Limited ViewPurchaser Address
-Website
http://http://puvvnl.up.nic.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
F-bracket with bolts & nuts for ST/PCC poles (Provided by Contractor)
343
-
-
Al. binding wire (Provided by Contractor)
68.75
-
-
M.S clamp for Top, T-off channel with bolts & nuts for ST/PCC poles (Provided by Contractor)
60
-
-
Guarding Angle Clamps for ST/PCC poles (Provided by Contractor)
52
-
-
P.G clamps for weasel conductor (Provided by Contractor)
186
-
-
Danger board with clamp & bolts for ST/PCC poles (Provided by Contractor)
302
-
-
Barbed wire GI (Provided by Contractor)
38
-
-
E-bracket with bolts & nuts (Provided by Contractor)
57
-
-
All lugs 70/120 mm2 (Provided by Contractor)
100
-
-
MS clamp for Stay set with bolt and nuts for ST/PCC poles (Provided by Contractor)
145
-
-
24 Volt Battery and Battery Charger with Cabinate (Provided by Contractor)
4
-
-
Cartage of following materials from ESC, Mirzapur to work site including loading & unloading charge.
-
-
-
ST Poles 11 mtr long (Provided by Department)
47
-
-
PCC Poles 8.5 mtr long (Provided by Department)
274
-
-
Line materials with ACSR Weasel Conductor (Provided by Department)
16.37
-
-
11 KV VCB O/G, 200/100/5A (Provided by Department)
6
-
-
33 KV VCB with single/double T/F control pannel and CT 200/100/1 A with structure, 33 KV VCB, Control pannel I/C for 33 KV single/double T/F, CT 200/100/1-1A and Steel Structure (Provided by Department)
9
-
-
11 KV XLPE Cable size 3x185 mm2 (Provided by Department)
200
-
-
Transformer 63 KVA, (Provided by Department)
20
-
-
Transformer 100 KVA, (Provided by Department)
5
-
-
Erection
-
-
-
Erection of single support ST/PCC pole for construction of 11 KV/LT line including digging of pit, fitting of all accessories, back filling of earth & others required work.
283
-
-
Grouting of pole with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms. (cement sand & brick ballast will be supplied by the constractor on his own his own cost)
283
-
-
Grouting of stay sets including digging of pit with 1:4:8 ratio of cement sand & brick ballast as per RESSPO norms, fixing binding and nuzzling of stay wire. (cement sand & brick ballast will be supplied by the constractor on his own his own cost)
31
-
-
Earthing of Poles
283
-
-
Stringing & sagging of 3 phase HT/LT line upto proper sag including laying of ACSR Weasel Conductor, binding with insulators & jumpering.
15.2
-
-
Stringing & sagging of 2 phase 2 wire to 3 phase 3 wire of 11 KV line upto proper sag including laying of ACSR Weasel Conductor, binding with insulators & jumpering.
3.5
-
-
Erection of Sectional Double Pole Structure of ST pole including digging of pit, fitting of all accessories, back filling of earth, grouting of each pole & stay sets as per RESSPO norms (cement sand & brick ballast will be supplied by the constractor on his own his own cost)
9
-
-
Erection of Sectional Double Pole Structure of PCC pole including digging of pit, fitting of all accessories, back filling of earth, grouting of each pole & stay sets as per RESSPO norms (cement sand & brick ballast will be supplied by the constractor on his own his own cost)
10
-
-
Gaurding of 11 KV line as per RESSPO norms
1.4
-
-
Drill/cut of stone in hilly area for erection of pole
164
-
-
Mounting of 63 KVA Transformer as per RESSPO norms
20
-
-
Mounting of 100 KVA Transformer as per RESSPO norms
5
-
-
Laying of U/G 11 KV XLPE cable size 3x185 mm2 including cost of sand & bricks as per RESSPO norms
160
-
-
Filling of I/D/O/D 11 KV cable jointing kit size 3x185 mm2 as per RESSPO norms
4
-
-
Installation of 11 KV VCB pannel (O/G), 200/100/5A as per RESSPO norms
6
-
-
Testing & commissioning of O/G 11 KV swichgear as per RESSPO norms
6
-
-
Installation of 33 KV VCB with single/double T/F control pannel and CT 200/100/1 A with structure, 33 KV VCB, Control pannel I/C for 33 KV single/double T/F, CT 200/100/1-1A and Steel Structure (Provided by Department)
9
-
-
Testing & commissioning of 33 KV VCB with single/double T/F control pannel and CT 200/100/1 A with structure, 33 KV VCB, Control pannel I/C for 33 KV single/double T/F, CT 200/100/1-1A and Steel Structure (Provided by Department)
9
-
-
Earthing for Indoor structure including 11 KV VCB pannel etc through boring till the water level with G.I Pipe & G.I strip and connect of all structure as per RESSPO norms (All materials will be supplied by the constractor on his own his own cost)
1
-
-
Cartage of received back 25 KVA Transformer from work site to ESC, Mirzapur including loading & unloading charge
20
-
-
Cartage of received back 63 KVA Transformer from work site to ESC, Mirzapur including loading & unloading charge
5
-
-
Dismantalling of Existing 33 KV /11 KV V.C.B.
14
-
-
Cartage of old 33 KV /11 KV V.C.B from work site to ESC, Mirzapur including loading & unloading charge