Purvanchal Vidyut Vitaran Nigam Limited Tender

... More
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of etender.up.nic.in - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.

Purvanchal Vidyut Vitaran Nigam Limited - PUVVNL Tender

Works
Eprocure
Opening Date16 Aug 2023
Closing Date21 Aug 2023
Tender Amount₹ 2,84,887 
This is an estimated amount, exact amount may vary.
Notes
Download

Costs

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
ABC LT Cable (3x95+1x70+1x16)

60

-

-

... More
ACSR Weasel Conductor

60

-

-

... More
Earthing Complete

2

-

-

... More
Supply of following material/fitting complete in all respect :-

-

-

-

... More
Distribution Box with Clamp (Distribution box shall be made from 20 SWG CRCA sheet by Deep Drown method with powder coating & size of box shall be 418 mm X 300mm X 120 mm (Roof of the box shall be tapered on both sides to drain the rain water)

2

-

-

... More
Clamp for Distribution Box

2

-

-

... More
Insulated dead end clamp with I hook

4

-

-

... More
Insulated suspension clamp with I hook

4

-

-

... More
LT Insulation piereing connector for line to line jumpering in ease of Tapping

8

-

-

... More
Nuts & bolts

3

-

-

... More
XLPE PVC Insulator 1x35 sq. mm cable for energizing D.b

6

-

-

... More
LT Clamp for PCC

2

-

-

... More
LT Shackle Insulator 100x115 mm

2

-

-

... More
The excavation of 1 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of single Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/PCC clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). All work will be done as per RESPO Norms & relevent IS Specification.

2

-

-

... More
Earthing of PCC Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms.

2

-

-

... More
Laying, stringing, sagging, binding and jumpering of ABC (3X95+1X70+1X16) Sq.mm. Cable of LT Line with fixing of Distribution Box with Clamp, Insulated Dead end clamp with I hook, Suspension clamp with I hook(Insulated), LT insulated Piercing connector, XLPE 1X35 Sq.mm. Al. cable for enerzing DB, XLPE 1X16 Sq.mm.

60

-

-

... More
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.

60

-

-

... More
fo|qr uxjh; forj.k [k.M&izFke xksj[kiqj ds vUrxZr tek ;kstuk esa Lohd`r iSdst la[;k 32@2023&24 ¼Jh fot; ukFk ;kno] yglM+h] xksj[kiqj ds [ksr ds mij ls xqtj jgs 11 ds0oh0 jkex+ QhMj dks vU;= f’k¶V djus dk dk;Z½ ds dk;ksZ dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&

-

-

-

... More
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-

-

-

-

... More
PCC Pole 8.5 mtr long

12

-

-

... More
11 KV Pin Insulator with pin

30

-

-

... More
11 KV Disc insulator with fitting

12

-

-

... More
ACSR Weasel conductor

1480

-

-

... More
Earthing complete

12

-

-

... More
11 KV X-Arm

10

-

-

... More
11 KV T Off Chanel

4

-

-

... More
Stay set complete

2

-

-

... More
11 KV F bracket

10

-

-

... More
Supply of following material/fitting complete in all respect :-

-

-

-

... More
Holding Clamp with nuts & bolts

14

-

-

... More
Nuts & bolts of different sizes

5

-

-

... More
The excavation of 1 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of single Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/PCC clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). In case of STP Pole Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification.

12

-

-

... More
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for HT Line with fixing of HT Clamps/other clamps and nuts&bolts off size as per required.

1480

-

-

... More
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)

2

-

-

... More
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms.

12

-

-

... More
Dismantling of Line materials and safe loading, unloading and carraige of dismantled material from work site to departmental store (As per site requirement)

1

-

-

... More
fo|qr uxjh; forj.k [k.M&f}rh; xksj[kiqj ds vUrxZr tek ;kstuk esa Lohd`r iSdst la[;k 34@2023&24 ¼okMZ ua0 60 :Lreiqj esa iwoZ ik”kZn vkokl ds ihNs cM+k xgjk uydwi ds 15 fd0ok0 ds fo|qrhdj.k dk dk;ZZ½ ds dk;ksZ dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&

-

-

-

... More
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-

-

-

-

... More
25 KVA Transformer 11/.4 KVA

1

-

-

... More
ST Pole 11 mtr long

7

-

-

... More
11 KV Top Channel

1

-

-

... More
11 KV Droper Angle

1

-

-

... More
11 KV Substation Base Angle

2

-

-

... More
11 KV Pin with pin

15

-

-

... More
11 KV Pin Insulator

15

-

-

... More
11 KV Disc insulator

12

-

-

... More
11 KV Disc Fitting

12

-

-

... More
Guarding Angle

7

-

-

... More
ACSR Weasel conductor

660

-

-

... More
11 KV TPMO with polymeric insulator

1

-

-

... More
Stay set complete with 5 kg wire

2

-

-

... More
Earthing complete

7

-

-

... More
LT PVC Cable 4*25sq.mm

15

-

-

... More
X-Arm M.S Angle 65X65X6 mm V Type

4

-

-

... More
MS T-Off with bolt & nuts

4

-

-

... More
F-BRACKET

4

-

-

... More
Supply of following material/fitting complete in all respect :-

-

-

-

... More
Clamp for Top, dropper angle etc with nuts & bolts

25

-

-

... More
Nuts & bolts of different sizes

4

-

-

... More
AI Lugs

4

-

-

... More
GI Wire for Guarding (6mm)

115

-

-

... More
The excavation of 2 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification.

1

-

-

... More
The excavation of 1 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of single Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification.

5

-

-

... More
Painting of Pole by double coating Aluminum & Red oxide paint. Paint will be provided by contractor

7

-

-

... More
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms.

7

-

-

... More
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT/HT Line with fixing of V cross arm, F-Bracket &other clamps and nuts&bolts off size as per required.

660

-

-

... More
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)

2

-

-

... More
Fabrication, errection, commissioning & Testing of 25 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.

1

-

-

... More
Erection of TPMO

1

-

-

... More
Chemical earthing of Transformer (Body/Neutral) as per IS Code 3043 - 1987 specification (Materials will be provided by contractor)

2

-

-

... More
Guarding of HT Lines including fixing of Guarding angle & G.I. wire (6 mm)

1

-

-

... More
fo|qr uxjh; forj.k [k.M&prqFkZ xksj[kiqj ds vUrxZr tek ;kstuk esa Lohd`r iSdst la[;k 35@2023&24 ¼jkIrhuxj Qst&1] ikuh Vadh ds uhps jkIrhuxj] xksj[kiqj esa xgjs uydwi ds 15 fd0ok0 ds fo|qrhdj.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&

-

-

-

... More
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-

-

-

-

... More
25 KVA Transformer

1

-

-

... More
ST Pole 11 mtr long

2

-

-

... More
ACSR Weasel Conductor

100

-

-

... More
MS Angle (Dropper) 100X50X2028 mm

2

-

-

... More
11 KV Pin Insulator

9

-

-

... More
11 KV Pin with Nut

9

-

-

... More
11 KV Dise Insulator

6

-

-

... More
11 KV Dise Fitting

6

-

-

... More
11 KV Fuse set

1

-

-

... More
MS Top Channel (125x65x2240)mm

1

-

-

... More
MS Angle 75X75X6X2028 mm eith clamp & bolts & nut ( T/F base)

2

-

-

... More
Earthing Complete

2

-

-

... More
T-off Channel

1

-

-

... More
Stay complete (stay rod 16X1800 mm stay wire 5 kg stay clamp bolt & nuts)

2

-

-

... More
LT PVC Cable 3.5X35 sq.mm

15

-

-

... More
Supply of following material/fitting complete in all respect :-

-

-

-

... More
Holding Clamp for Top, dropper channel fuse set etc with nuts & bolts

10

-

-

... More
Nuts & bolts of different sizes

2

-

-

... More
Cu Z Clamp

4

-

-

... More
Al Lugs

4

-

-

... More
The excavation of 2 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification.

1

-

-

... More
Painting of Pole by double coating Aluminum & Red oxide paint. Paint will be provided by contractor

2

-

-

... More
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms.

2

-

-

... More
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.

100

-

-

... More
Fabrication, errection, commissioning & Testing of 25 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.

1

-

-

... More
Erection of Fuse set

1

-

-

... More
Chemical earthing of Transformer (Body/Neutral) as per IS Code 3043 - 1987 specification (Materials will be provided by contractor)

2

-

-

... More
fo|qr uxjh; forj.k [k.M&prqFkZ xksj[kiqj ds vUrxZr tek ;kstuk esa Lohd`r iSdst la[;k 36@2023&24 ¼‘kfDruxj f’kokiqje dkyksuh] ‘kkgiqj] xksj[kiqj esa xgjs uydwi ds 15 fd0ok0 ds fo|qrhdj.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&

-

-

-

... More
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-

-

-

-

... More
25 KVA Transformer

1

-

-

... More
ST Pole 11 mtr long

2

-

-

... More
ACSR Weasel Conductor

200

-

-

... More
MS Angle (Dropper) 100X50X2028 mm

2

-

-

... More
11 KV Pin Insulator

9

-

-

... More
11 KV Pin with Nut

9

-

-

... More
11 KV Disc Insulator

3

-

-

... More
11 KV Disc Fitting

3

-

-

... More
11 KV Fuse set

1

-

-

... More
MS Top Channel (125x65x2240)mm

1

-

-

... More
MS Angle 75X75X6X2028 mm eith clamp & bolts & nut ( T/F base)

2

-

-

... More
Earthing Complete

2

-

-

... More
T-off Channel

1

-

-

... More
LT PVC Cable 3.5X35 sq.mm

15

-

-

... More
Supply of following material/fitting complete in all respect :-

-

-

-

... More
Holding Clamp for Top, dropper channel, Fuse set etc with nuts & bolts

10

-

-

... More
Nuts & bolts of different sizes

2

-

-

... More
Cu Z Clamp

4

-

-

... More
Al Lugs

4

-

-

... More
The excavation of 2 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification.

1

-

-

... More
Painting of Pole by double coating Aluminum & Red oxide paint. Paint will be provided by contractor

2

-

-

... More
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms.

2

-

-

... More
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.

200

-

-

... More
Fabrication, errection, commissioning & Testing of 25 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.

1

-

-

... More
Erection of Fuse set

1

-

-

... More
Chemical earthing of Transformer (Body/Neutral) as per IS Code 3043 - 1987 specification (Materials will be provided by contractor)

2

-

-

... More
fo|qr uxjh; forj.k [k.M&prqFkZ xksj[kiqj ds vUrxZr tek ;kstuk esa Lohd`r iSdst la[;k 38@2023&24 ¼Jh uouhr dqekj] 1442] egknsoiqje~] HkSjkiqj] xksj[kiqj }kjk vkosfnr fo|qr la;kstu gsrq ,y0Vh0 ykbu ds fuekZ.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&

-

-

-

... More
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-

-

-

-

... More
ACSR Weasel Conductor

81

-

-

... More
PCC Pole 8.5 mtr

2

-

-

... More
Supply of following material/fitting complete in all respect :-

-

-

-

... More
Shackle insulator

4

-

-

... More
LT clamp

4

-

-

... More
Nuts & bolts

0.5

-

-

... More
The excavation of 2 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/PCC clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). All work will be done as per RESPO Norms & relevent IS Specification.

2

-

-

... More
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for LT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.

81

-

-

... More
fo|qr uxjh; forj.k [k.M&prqFkZ xksj[kiqj ds vUrxZr tek ;kstuk esa Lohd`r iSdst la[;k 47@2023&24 ¼okMZ ua0 43] jkeizhr pkSjkgk] dkyh efUnj] xksj[kiqj esa feuh uydwi gsrq fo|qrhdj.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&

-

-

-

... More
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-

-

-

-

... More
PCC Pole 8.5 mtr. Long

8

-

-

... More
ABC LT Cable (3x95+1x70+1x16)

450

-

-

... More
Stay complete

3

-

-

... More
11 KV Cable 3.5X35 sq mm

15

-

-

... More
Earthing Complete

3

-

-

... More
Supply of following material/fitting complete in all respect :-

-

-

-

... More
Distribution box

2

-

-

... More
Clamp for Distribution Box

2

-

-

... More
Insulated dead end clamp with I hook

3

-

-

... More
Insulated suspension clamp with I hook

8

-

-

... More
LT Insulation piereing connector for line to line jumpering in ease of Tapping

8

-

-

... More
Nuts & bolts

5

-

-

... More
XLPE PVC Insulator 1x35 sq. mm cable for energizing D.B

6

-

-

... More
LT Clamp for PCC

8

-

-

... More
LT Shackle Insulator 100x115 mm

8

-

-

... More
The excavation of 1 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of single Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/PCC clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). All work will be done as per RESPO Norms & relevent IS Specification.

8

-

-

... More
Earthing of PCC Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms.

3

-

-

... More
Laying, stringing, sagging, binding and jumpering of ABC (3X95+1X70+1X16) Sq.mm. Cable of LT Line with fixing of Distribution Box with Clamp, Insulated Dead end clamp with I hook, Suspension clamp with I hook(Insulated), LT insulated Piercing connector, XLPE 1X35 Sq.mm. Al. cable for enerzing DB, XLPE 1X16 Sq.mm.

450

-

-

... More
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)

2

-

-

... More
fo|qr uxjh; forj.k [k.M&prqFkZ xksj[kiqj ds vUrxZr tek ;kstuk esa Lohd`r iSdst la[;k 48@2023&24 ¼okMZ ua0 29] yksfg;k uxj] jkIrhuxj xksj[kiqj esa feuh uydwi ds la;kstu gsrq fo|qrhdj.k dk dk;Z½ ds dk;ksZ dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&

-

-

-

... More
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-

-

-

-

... More
25 KVA Transformer

1

-

-

... More
PCC Pole 8.5 mtr. Long

7

-

-

... More
11 KV Cross arm

4

-

-

... More
MS Top Channel (125x65x2240)mm

1

-

-

... More
MS angle (Dropper) 100X50X2028 mm

2

-

-

... More
MS angle 75X75X6X2028 mm With clamp & bolts & nut (T/F base)

2

-

-

... More
11 KV Pin Insulator with Pin

18

-

-

... More
11 KV Dise Insulator with fitting

6

-

-

... More
ACSR Weasel Conductor

230

-

-

... More
11 KV Fuse set

1

-

-

... More
Stay complete (stay rod 16X1800 mm stay wire 5 kg stay clamp bolt & nuts)

5

-

-

... More
Earthing Complete

7

-

-

... More
LT PVC Cable 3.5X35 sq.mm

15

-

-

... More
11 KV T-off Channel

1

-

-

... More
Supply of following material/fitting complete in all respect :-

-

-

-

... More
Holding Clamp for Top, dropper channel fuse set etc with nuts & bolts

17

-

-

... More
Nuts & bolts of different sizes

3

-

-

... More
AI Lugs

4

-

-

... More
The excavation of 2 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/PCC clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification.

1

-

-

... More
The excavation of 1 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of single Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor. Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor). Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that No rainwater gets accumulated on the top. All work will be done as per RESPO Norms & relevent IS Specification.

5

-

-

... More
Earthing of PCC Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO Norms.

7

-

-

... More
Laying, stringing, sagging, binding and jumpering of ACSR Weasel conductor for HT Line with fixing of V cross arm, T-off channel, other clamps and nuts&bolts off size as per required.

230

-

-

... More
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)

5

-

-

... More
Fabrication, errection, commissioning & Testing of 25 KVA T/F on Double Pole with all accessories including make its LT and HT connection. All necessary materials such as Holding clamp, Al.Lugs (Confirming to IS 8309), Z Clamp, Nuts & Bolts will be supplied by the Contractor.

1

-

-

... More
Erection of Fuse Set

1

-

-

... More
Chemical earthing of Transformer (Body/Neutral) as per IS Code 3043 - 1987 specification (Materials will be provided by contractor)

2

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.