Purvanchal Vidyut Vitaran Nigam Limited Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Purvanchal Vidyut Vitaran Nigam Limited - PUVVNL Tender
Eprocure
Opening Date5 Oct 2024
Closing Date19 Oct 2024
Tender Amount₹ 66,46,529 This is an estimated amount, exact amount may vary.
Costs
EMD
₹ 1,30,000Document Cost
₹ 5,900Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_PVVNV_963123_1Bid Award Id
ViewTender No
10/EUDC(G)/2024-25Tender Authority
Purvanchal Vidyut Vitaran Nigam Limited ViewPurchaser Address
-Website
http://http://puvvnl.up.nic.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Cable jointing kit 11 KV XLPE 3X185 sq mm
6
-
-
Cable jointing kit 11 KV XLPE 3X185 sq mm S/T
2
-
-
S.T. Pole 11 Mtr. Long
4
-
-
11 KV Dropper Channel
6
-
-
11 KV Top Channel
2
-
-
11 KV Pin Insulator
6
-
-
11 KV pin with net
6
-
-
Earthing Complete
4
-
-
Supply of following material/fitting complete in all respect :-
-
-
-
Holding clamps for top, dropper, t-off etc
12
-
-
GI Nuts & Bolts off size
2
-
-
G.I Pipe dia 150 mm
12
-
-
The excavation of 2 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor.
Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).
Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
2
-
-
Painting of Pole by double coating Aluminium & Red oxide paint. Paint will be provided by contractor
4
-
-
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
4
-
-
Laying and dressing of under ground 11 KV 3X185 sq mm XLPE Cable by Horizontal drilling method as per RESPO norms. The Depth of horizontal drilling shall be between 2 to 3 meters or as per site required.
520
-
-
Errection of 11 KV 3X185 sq mm XLPE Cable Jointing Kit with complete work
8
-
-
Making Loop alongwith dressing, Marking, Tagging and Hoisting of cable on Single/Double pole using G.I. Pipe 6"dia 3 mtr. Long with complete work.
80
-
-
fo|qr uxjh; forj.k [k.M&f}rh; xksj[kiqj ds vUrxZr fctusl Iyku esa Lohd`r u;s 250 ds0oh0,0 forj.k ifjorZdksa dh LFkkiuk ds dk;ksZ dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&
-
-
-
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
-
-
-
250 KVA Transformer
10
-
-
11 KV XLPE Cable 3X70 sq mm
1280
-
-
11 KV C/J Kit 3X70 sq mm
18
-
-
ST Pole 09 M long
12
-
-
ST Pole 11 M long
33
-
-
MS Top Channel (125x65x2240) mm
14
-
-
MS angle (Dropper) 100X50X2028 mm
37
-
-
ACSR Weasel conductor
600
-
-
ACSR Dog conductor
520
-
-
11 KV Pin Insulator with pin
99
-
-
11 KV Disc insulaor with fiitings
48
-
-
LT AB Cable (3X150+1X120+1X16) sq mm
650
-
-
LT Cable 1X35 sq mm
116
-
-
11 KV Fuse set
10
-
-
11 KV T-Off Channel
8
-
-
Stay complete (Stay rod 16X1800 mm, stay wire 5 kg, stay clamp, bolt & nuts)
22
-
-
Earthing complete
45
-
-
LT Cable 1X240 sq mm
750
-
-
Supply of following material/fitting complete in all respect :-
-
-
-
LT Three Phase Distribution box
12
-
-
Clamp for LT Three Phase DB Box
12
-
-
Suspension Clamp with I hook (Insulated)
8
-
-
Dead end Clamp with I hook (Insulated)
8
-
-
Piercing Connector (Insulated)
34
-
-
Shackle insulator
24
-
-
LT Clamps
28
-
-
Holding Clamp for top, dropper channel Fuse set etc with nuts & bolts
148
-
-
Copper Z Calmp
40
-
-
GI Nuts & bolts of different sizes
58
-
-
Al Lugs
112
-
-
G.I Pipe dia 6 inch
60
-
-
The excavation of 2 No foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of double Pole with fixing of necessary clamps & accessories (Top Channel, Dropper Angle etc.) as per required. All required materials such as Holding clamp/STP clamp, Nuts & Bolts off size etc will be provided by the contractor.
Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).
Making plinth around Pole height 300 mm above ground level with top 100 mm is kept tapered so that no rainwater gets accumulated on the top. All work will be done as per RESPO norms & relevent IS Specification.
10
-
-
The excavation of foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of PCC Pole with fixing of necessary clamps & accessories as per required. All required materials such as Holding clamp/PCC/LT clamp, F-Bracket, LT shacle insulator, Nuts & Bolts off size etc will be provided by the contractor.
Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).
All work will be done as per RESPO norms & relevent IS Specification.
25
-
-
Painting of Pole by double coating Aluminium & Red oxide paint. Paint will be provided by contractor
45
-
-
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
45
-
-
Fabrication, errection, commissioning & Testing of 250 KVA T/F on Plinth with all accessories including make its LT and HT connection. All neessary materials will be supplied by the Contractor.
10
-
-
Chemical earthing of Transformer (Body+Neutral) as per IS Code 3043 - 1987 specification (Materials will be provided by contractor)
20
-
-
Erection and grouting of stay in CC ratio 1:4:8 of Cement, Sand and Stone Ballast including cost of grouting material with nozelling and binding of stay wire (Complete work)
22
-
-
Laying of ACSR Dog/Weasel conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.
1120
-
-
Laying and dressing of under ground 11 KV 3X70 sq mm XLPE Cable by Horizontal drilling method as per RESPO norms. The Depth of horizontal drilling shall be between 2 to 3 meters or as per site required.
920
-
-
Making Loop alongwith dressing, Marking, Tagging and Hoisting of cable on Single/Double pole using G.I. Pipe 6"dia 3 mtr. Long with complete work.
360
-
-
Erection of 11 KV 3X70 Sq.mm. Cable Jointing Kit
18
-
-
Erection of 11 KV Fuse set
10
-
-
Construction of T/F plinth of size 2x2x1.2 M with the help of first class brick & 9" masonary in the ratio 1:4 cement & sand coarse. Filling the structure completely and plastering outer surface as per RESPO norms. Top of the plinth covered with 4" RCC Slab of ratio 1:1.5:3 (Cement, sand & concrete) grouting with 2 No ISMC size 125X65X6 MM (confirming to IS 808:1989) of 2000 mm long for resting. All required materials will be provided by the contractor.
10
-
-
Grill fencing of 11/0.4 KV S/S shall be made of rectangular of size & height approx 2 meter as per site requirement with fabrication 50X50X5 mm angel the frame is also have 1 No Horizontal runner of MS flat 40x5 welded in middle to support of grill, having a gate on road side must have provision of locking arrangement. The work is including painting of fencing as per norms. Work will be done as per RESPO specification.
10
-
-
Laying & sagging of ABC (3X150+1X120+1X16) Sq.mm. Cable of LT Line with fixing of Distribution Box with Clamp, Insulated Dead end clamp with I hook, Suspension clamp with I hook(Insulated), LT insulated Piercing connector, XLPE 1X35 Sq.mm. Al. cable for enerzing DB, XLPE 1X16 Sq.mm. Al. cable for giving connection to Street Light and nuts&bolts off size by the contractor.
650
-
-
Supply and Complete Installation of 2 Nos. Henley Type Tailless Unit 300 AMP in Box using LT XLPE 1X240 Sq.mm. Cable, LT Crimping Lug, GI Nuts & Bolts etc (as per site requirement) on 11/0.4 KV Distribution Transformer. (Only LT XLPE 1X240 Sq.mm. Cable will be provided by Department)
Specification of Henley Type Tailless Unit 300 AMP described as below-
1. Henley Type MS Sheet duly painted grey enameled paint- MS of 18 SWG (54X4.5 inches) with holes as per requirement
2. 6 No. Insulator- Made of White Glazed Porcelain
3. 6 No. Copper Spring Contact- 32X3.7 mm Made of Copper
4. 3 No. "L" Contact - Brass
5. 3 No. Metal Part Connector For Holding Busbar- Brass
6. 1 No. Casted Patti- M.S.
7. 1 No. Neutral- Brass
8. Iron Clip, Bolt, Nuts, Washer and Screw etc for Tightening- All Galvanized
9. Copper Bus Bar Strip- 500X50X5 mm (3 Nos.Copper Busbar Strip to be used on 2 Nos. Tailless unit)
10. Aluminium Bus Bar Strip- 500X50X5 mm (1 No)
All work will be done as per RESSPO Norms & relevent IS Specification.
10
-
-
Supply, fabrication, erection of LT Pillar Box for Tailless Unit after making Plinth of Height 300 mm above ground level LT Pillar Box Size- 1650X1050X520 mm with Gate and Proper Locking arrangement (Canopy of 15 Degree )
All work will be done as per RESSPO Norms & relevent IS Specification.
10
-
-
fo|qr uxjh; forj.k [k.M&f}rh;] xksj[kiqj ds {ks= esa fctusl Iyku esa Lohd`r vkj0,e0;w0 yxkus ds dk;Z dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&
-
-
-
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
-
-
-
3x185 mm2 XLPE 11 kV
4050
-
-
Cable jointing kit 11 kV XLPE 3X185 sq mm
72
-
-
11 kV, 630, 21 kA Ring Main Unit, 3 Way
9
-
-
Laying and dressing of under ground 11 KV 3X185 sq mm XLPE Cable by Horizontal drilling method as per RESPO norms. The Depth of horizontal drilling shall be between 2 to 3 meters or as per site required.
4050
-
-
Errection of 11 KV 3X185 sq mm XLPE Cable Jointing Kit with complete work
72
-
-
Erection of 11 kV Ring Main Unit
9
-
-
Plinth for 11 kV Ring Main Unit
9
-
-
Earthing (Pipe Type) for 11 kV Ring Main Unit
9
-
-
fo|qr uxjh; forj.k [k.M&f}rh;] xksj[kiqj ds {ks= esa fctusl Iyku esa Lohd`r ttZj ,0ch0 dsfcyksa dks ifjofrZr@mPphdj.k ds dk;Z dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&
-
-
-
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
-
-
-
LT AB Cable (3X150+1X120+1X16) sq mm
17
-
-
ST Pole 9 mtr Long
125
-
-
LT Cable 1X35 sq mm
1500
-
-
Earthing complete
125
-
-
Supply of following material/fitting complete in all respect :-
-
-
-
LT Three Phase Distribution box
125
-
-
Clamp for LT Three Phase DB Box
125
-
-
Suspension Clamp with I hook (Insulated)
325
-
-
Dead end Clamp with I hook (Insulated)
200
-
-
Piercing Connector (Insulated)
500
-
-
GI Nuts & bolts of different sizes
45
-
-
The excavation of foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of PCC Pole with fixing of necessary clamps & accessories as per required. All required materials such as Holding clamp/PCC/LT clamp, F-Bracket, LT shacle insulator, Nuts & Bolts off size etc will be provided by the contractor.
Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).
All work will be done as per RESPO norms & relevent IS Specification.
125
-
-
Painting of Pole by double coating Aluminium & Red oxide paint. Paint will be provided by contractor
125
-
-
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
125
-
-
Laying & sagging of ABC (3X150+1X120+1X16) Sq.mm. Cable of LT Line with fixing of Distribution Box with Clamp, Insulated Dead end clamp with I hook, Suspension clamp with I hook(Insulated), LT insulated Piercing connector, XLPE 1X35 Sq.mm. Al. cable for enerzing DB, XLPE 1X16 Sq.mm. Al. cable for giving connection to Street Light and nuts&bolts off size by the contractor.
17
-
-
Dismentling of old existing A.B. Cable
15.3
-
-
Dismentling of old existing ST Pole
25
-
-
Carriage of old existing conductor & Pole from work site to store centre
39
-
-
Disconnection & reconnection of consumer service cables
1275
-
-
fo|qr uxjh; forj.k [k.M&f}rh;] xksj[kiqj ds {ks= esa fctusl Iyku esa Lohd`r ttZj ,0ch0 dsfcyksa dks ifjofrZr@mPphdj.k ds dk;Z dks lseh VuZdh ds vk/kkj ij djk;s tkus gsrq dk;Z dk fooj.k %&
-
-
-
Loading, unloading and safe carriage of following materials from Store Centre, Gorakhpur to JE dump Store and JE dump Store to work site with proper stacking :-
-
-
-
ACSR Rabbit Conductor
2
-
-
ST Pole 11 mtr long
3
-
-
11 KV Pin Insulator with pin
9
-
-
11 KV Disc insulaor with fiitings
6
-
-
11 KV V cross arm
5
-
-
11 KV T-Off Channel
2
-
-
Stay complete (Stay rod 16X1800 mm, stay wire 5 kg, stay clamp, bolt & nuts)
2
-
-
Earthing complete
3
-
-
Supply of following material/fitting complete in all respect :-
-
-
-
F Bracket
5
-
-
Holding Clamp
12
-
-
Nuts & bolts of different sizes
5
-
-
The excavation of foundation pit of size 750mmX450mm and having depth of 1/6th of the full length of the pole. Fabrication & erection of PCC Pole with fixing of necessary clamps & accessories as per required. All required materials such as Holding clamp/PCC/LT clamp, F-Bracket, LT shacle insulator, Nuts & Bolts off size etc will be provided by the contractor.
Grouting of Pole in cc 1:4:8 (Cement, sand & 40 mm brick ballast), Grouting will be done in the block of size 450x450 mm x depth upto ground level and backfilling of pits with mud completely and leveling etc (Material provided by Contractor).
All work will be done as per RESPO norms & relevent IS Specification.
3
-
-
Painting of Pole by double coating Aluminium & Red oxide paint. Paint will be provided by contractor
3
-
-
Earthing of ST Pole by MS earthing Rod & 6 SWG earthing Wire as per RESPO norms.
3
-
-
Laying of ACSR Rabbit/Dog/Weasel conductor for LT/HT Line with fixing of LT Clamps/other clamps, Shackle insulator and nuts&bolts off size as per required.
2
-
-
Dismentling of old existing Line
1.8
-
-
Dismentling of old existing ST Pole
3
-
-
Carriage of old existing conductor & Pole from work site to store centre
1
-
-