If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Public Works Department - PWD Tender
Civil And Construction
Road Construction
Eprocure
Opening Date24 Dec 2024
Closing Soon17 Jan 2025
Tender Amount₹ 68,00,000
Costs
EMD
₹ 5,40,000Document Cost
₹ 2,714Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_CEUVZ_986527_1Tender No
SE Ref No 4854/183 com-Va.Vritt/24-25 Dt 12.12.2024Tender Authority
Public Works Department ViewPurchaser Address
-Website
http://http://uppwd.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
... More
Providing, laying, spreading and compacting of sukrut stone stone aggregates of specific sizes(45.0-63mm) to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber,applying and brooming ,binding materials to fill-up the interstices of coars aggrigate,watering and compacting to the required density Grading-2 as per Technical Specification clause 405. (Including all taxes, labour cess but Excluding GST)
187.5
2060
386250
... More
Providing, laying, spreading and compacting of sukrut stone stone aggregates of specific sizes(22.4-53mm) to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and camber,applying and brooming ,binding materials to fill-up the interstices of coars aggrigate,watering and compacting to the required density Grading-3 as per Technical Specification clause 405. (Including all taxes, labour cess but Excluding GST)
206.85
2250
465412.5
... More
Providing and applying primer coat with bitumen emulsion (SS-II) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg per sqm using mechanical means as per Technical Specification Clause 502. (Including all taxes, labour cess but Excluding GST)
2150
37
79550
... More
Providing and applying tack coat with Bitumen (VG-10) using bitumen distributor at the rate of 0.30 kg per sqm on the prepared bituminous surface cleaned with Air compresser as per Technical Specification Clause 503. (Including all taxes, labour cess but Excluding GST)
4730
16
75680
... More
Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.2 mm -11.2 mm aggregates using penetration grade bitumen VG-10 to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant,laying and rolling with three wheel static roller 80-100 KN capacity ,finished to required level and grades to be follwed by seal coat of Type -C as per Technical Specification Clause 508. (Including all taxes, labour cess but Excluding GST)
4730
169
799370
... More
Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type C as per Technical Specification Clause 510. (Including all taxes, labour cess but Excluding GST)
4730
62
293260
... More
Construction of Subgrade and earthen shoulders with approved material obtained from borrow pits with all lift and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 with a lead upto 3000 m as per Technical Specification Clause 303.1 (Including all taxes, labour cess but Excluding GST)
875
190
166250
... More
Brick edging on both side of road with first class brick 8 cm. (3") wide 12 cm. (4.50") deep laid with mud mortar including all materials,
labour, T&P etc. complete. As direction by the E/I (Including all taxes, labour cess but Excluding GST)
0.86
78000
67080
... More
Construction of un reinforced plain cement concrete pavement, thickness as per design over a prepared sub base with 43 grade cement or any other type as per Clause 1501.2.2 M30(Grade) coarde and fine aggregates confoming to IS:383 maximum size of coarse aggreagate not exceeding 25 mm mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design laid in approved fixed side formwork (steel channel laying and fixing of 125 micron thick polythene film wedges steel plates including levelling the formwork as per drawing) spreading the concrete with shovels rakes compacted using needle screed and plate vibrators and finished in continuous operation including provision of contraction and expansion construction joints applying debonding strips primer sealant near aapproaches and construction joints admixtures as approved curing of concrete slabs for 14-days using curing compound (where specified) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501. As direction by the E/I. (Including all taxes, labour cess but Excluding GST)
52.5
7500
393750
... More
Excavation in foundation in ordinary soil (loamclay or sand) including lift up to 1.5m and lead up to 30m. and including filling watering and ramming of excavated earth into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth ad directed by the Engineer in charge up to a distance of 30m. from the foundation trenches including all T&P phowarah and basket etc.As per SOR SI No-251 complete. (Including all taxes, labour cess but Excluding GST)
350
130
45500
... More
Concrete with 4cm. gauge approved stone ballast, approved coarse sand and cement in the proportion of 6:3:1 including supply of all materials labour and tools and plants etc. required for proper completion for the work. (Including all taxes, labour cess but Excluding GST)
54.91
4950
271804.5
... More
Providing and laying Reinforced Cement Concrete (M-20) in foundation as per drawing and techanical specification clauses 800 (Excluding cost of Reinforcement) (Including all taxes, labour cess but Excluding GST)
88.22
6800
599896
... More
Supplying fitting and placing TMT bar reinforcement in superstructure complete as per drawing and specification Clausees 1002,1010 & 1202. (Including all taxes, labour cess but Excluding GST)
75
6350
476250
... More
Providing and laying 600 mm dia N.P-3 H.P. jointing with coller in proper position including cost of cement , jute etc. required for proper completion of work. but excluding cost of collor (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
10
3200
32000
... More
R.C.R with cement and coarse sand mortar in proportion of 1 and 4 respectively in sub structure including cost of all material labour T&P etc. required for proper completion of work. ( Excluding GST) (Including all taxes, labour cess but Excluding GST)
72.57
4250
308422.5
... More
R.C.R with cement and coarse sand mortar in proportion of 1 and 4 respectively in sub structure including cost of all material labour T&P etc. required for proper completion of work. (Including all taxes, labour cess but Excluding GST)
31.38
4450
139641
... More
Struck pointing with cement mortar consisting of 1 part cement and 2 parts of sand of 1.25 FM including Supply of all material , labour T&P etc required for proper completion of work. (Including all taxes, labour cess but Excluding GST)
10.4
185
1924
... More
Wearing coat in 1:1.5:3 on top of slab including all matireal, labour,tools and plants etc. required for proper completion for the work . (Including all taxes, labour cess but Excluding GST)
1.07
7150
7650.5
... More
P.C.C. work in 1:2:4 with cement approved coarse sand and 2cm Gauge approved stone ballast including all matireal labour,tools and plants etc. required for proper completion for the work. (Including all taxes, labour cess but Excluding GST)
2.19
6600
14454
... More
RCC Grade M 25 Furnishing and Placing Reinforced/ Prestressed cement concrete in sup-structure as per drawing and Technical Specification for Box Culvert (Including all taxes, labour cess, T&P and material but Excluding GST)
8.3
8300
68890
... More
PART B
Maintainance cost :- Maintainance cost will be paid year wise as per Government order No. 17/2024/SA.-113/23-1-2024-23-1099/113/2023 Date 16.01.2024 and HQ UPPWD,Lucknow order No. 36890C/RMC/Mul-23-24 Date 17.02.2024 . Maintainance cost will adjusted as per final cost of construction and will be paid accordingly.
1
-
-
... More
1st year - maintainance cost 0% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST.
1
-
-
... More
2nd year - maintainance cost 0.75% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST.
1
42948
42948.59
... More
3rd year - maintainance cost 1.5% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST.
1
85897
85897.17
... More
4th year - maintainance cost 2.25% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST.
1
128845
128845.75
... More
5th year - maintainance cost 3% (including labour material T&P etc. complete as per direction of E/I & also including all taxes Labour cess but excluding GST.
1
171794
171794.34
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements
Past BiddersThis list is curated from the bidders of the similar tenders in the past
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%