If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Public Works Department - PWD Tender
Civil And Construction
Road Construction
Eprocure
Opening Date14 Nov 2024
Closing Date21 Nov 2024
Tender Amount₹ 27,00,000
Costs
EMD
₹ 2,70,000Document Cost
₹ 854Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_CEUVZ_973621_1Tender No
Ref No 2217/10A Date 15.10.2024Tender Authority
Public Works Department ViewPurchaser Address
-Website
http://etender.up.nic.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
W.B.M (Grade-3) Providing, laying, spreading and compacting stone aggregates of specific sizes 53mm to 22.4mm to water bound macadam (G-3) specification including spreading in uniform loose thickness hand packing, rolling with smooth wheel roller 80-100 KN in stages to proper grade and camber, applying and brooming, Stone dust to fill-up the interstices of coarse aggregate, watering and compacting 7.50 cm thickness to the required density Grading 3 as per Technical Specification Clause 405.( Including all material & T&P etc. complete. & Excluding cost of GST)
154.69
3420
529031.25
Brick edging 7.00 cm. wide on both sides of the road by M-150 bricks complete as per PWD detailed specification No. 20.15 as per Technical Specification clause .( Including all material & T&P etc. complete. & Excluding cost of GST)
0.55
78000
42900
Providing and applying Primer coat with bitumen emulsion using bitumen emulsion distributor at the rate of 0.70 kg per sqm on the prepared bituminous surface cleaned with hydraulic broom as per Technical Specification Clause 502.( Including all material & T&P etc. complete. & Excluding cost of GST)
2062.5
36
74250
Providing and applying tack coat with bitumen VG-10 using bitumen distributor at the rate of 0.30 kg per sqm on the prepared bituminous surface cleaned with hydraulic broom as per Technical Specification Clause 503.( Including all material & T&P etc. complete. & Excluding cost of GST)
2062.5
15
30937.5
Providing, laying and rolling of open graded premix carpet of 20 mm thickness composed of 13.2 mm to 5.6 (13.2mm & 11.20mm in 2:1) mm aggregates either using penetration grade bitumen VG-10 to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of Type C as per Technical Specification Clause 508.( Including all material & T&P etc. complete. & Excluding cost of GST)
2062.5
184
379500
Providing and laying seal coat sealing 6.7mm stone grit @0.009 cum per sqm the voids in a bituminous grade VG-10 @0.65kg per sqm surface laid to the specified levels, grade and cross fall using Type C as per Technical Specification Clause 510( Including all material & T&P etc. complete. & Excluding cost of GST)
2062.5
65
134062.5
Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with approved material obtained from ROW with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1.
443
61
27023
Earth work in excation in foundation in ordinary soil . As per MORD Specification ( Including all material & T&P etc. complete. & Excluding cost of GST)
16.75
19
318.25
C.C. With 6:3:1 cement fine sand and 40 mm stone ballast in foundation as per SIN NO 280 ( Including all material & T&P etc. complete. & Excluding cost of GST)
2.31
5700
13167
C.C. With 4:2:1 cement fine sand and 40 mm stone ballast in foundation as per SI NO 279 ( Including all material & T&P etc. complete. & Excluding cost of GST)
0.56
6000
3360
Providing and laying of 600 mm dia NP-3 hume pipe medium duty confirm to IS 458:2003 including collars/spigot jointed with dtiff mixture of cement in the proportion of 1:2 (1cement:2 fine sand) including testing of joints, all taxes, transportation charges & contractor's profit etc complete SI NO 026. ( Including all material & T&P etc. complete. & Excluding cost of GST)
7.5
3200
24000
Providing and laying of 350 mm dia NP-3 hume pipe medium duty confirm to IS 458:2003 including collars/spigot jointed with dtiff mixture of cement in the proportion of 1:2 (1cement:2 fine sand) including testing of joints, all taxes, transportation charges & contractor's profit etc complete. ( Including all material & T&P etc. complete. & Excluding cost of GST)
7.5
1600
12000
First class brick work with 1:6 cement and coarse sand mortar in foundation as per S.I.No.305 b ( Including all material & T&P etc. complete. & Excluding cost of GST)
6.22
5300
32966
Struct cement pointing with 1:2 cement & Fine sand mortar as per S.I.No. 574. ( Including all material & T&P etc. complete. & Excluding cost of GST)
18.17
185
3361.45
15mm thick plaster with cement mortor consinting of 1 part cement and 4 part of apporved coarse sand Minimum thickness not be less than 10 mm including supply of all materials babour and T&P etc SI NO 580
1.19
200
238
Maintainance cost :- Maintainance cost will be paid year wise as per Government order No. 17/2024/SA.-113/23-1-2024-23-1099/113/2023 Date 16.01.2024 and HQ UPPWD,Lucknow order No. 3689COPRMC/Mul-23-24 Date 17.02.2024
-
-
-
1st year- maintainance cost 0% on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
0.55
-
-
2nd year- maintainance cost 0.75% on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
0.55
33414
18378.06
3rd year- maintainance cost 1.50 % on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
0.55
66829
36756.11
4th year- maintainance cost 2.25% on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
0.55
100243
55134.17
5th year- maintainance cost 3.00 % on Bituminous Work (Including labour Material T&P etc. complete as per direction of E/I & also including all taxes. Labour cess but excluding GST)
0.55
133658
73512.23