If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Public Works Department - PWD Tender
Civil And Construction
Road Construction
Eprocure
Opening Date23 Dec 2024
Closing Date13 Jan 2025
Tender Amount₹ 16,70,000
Costs
EMD
₹ 1,67,000Document Cost
₹ 854Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_CEAGR_985016_5Bid Award Id
ViewTender No
3995/9A-PD/2024 Dated 14/10/2024Tender Authority
Public Works Department ViewPurchaser Address
-Website
http://http://uppwd.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Excavation in foundation in ordinary soil (Loam, Clay or Sand) Including lift upto 1.50 m and lead upto 30m and including filling watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer In-charge upto a distance of 30m from the foundation trenches. (Small work) Ch-4 SI No- 1
58
150
8700
... More
Providing and laying cement concrete in 1:4:8 (1 Cement : 4 Coarse sand : 8 graded stone aggregate 40 mm nominal size) and curing complete, Including cost of form work. in Foundation and floors. Ch- 5 SI No- 4.1.8 including cost of all materials, T&P, labour, cess, cartage for proper completion of work as per direction of Engineer-in-Charges
15
5625
84375
... More
Class-150 (Non Modular) brick work in 1:4 cement and Coarse sand mortar in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of the work. SI No- 6.1.1 including cost of all materials, T&P, labour, cess, cartage for proper completion of work as per direction of Engineer-in-Charges
26
5650
146900
... More
Providing and laying cement concrete in 1:2:4 (1 Cement : 2 coarse sand : 4 graded stone aggregate 40 mm nominal size) and curing complete, Including cost of form work. In Foundation and floors.Ch-5 SI No-4.1.4 including cost of all materials, T&P, labour, cess, cartage for proper completion of work as per direction of Engineer-in-Charges
4
6600
26400
... More
12mm Cement plaster with cement mortar in proportion of 1:4 cement & coarse sand of single coat for interior plastering upto floor two level including internal rounded angles chamfers, and rounded angles not exceeding 80mm. In girth and finished even and smooth. Ch- 13 SI No- 13.4.1
120
200
24000
... More
Supply and Fixing of RCC hume pipe NP-3 (Socket Hume Pipe) 350mm Pipe including cost of all materials, T&P, labour, cartage for proper completion of work as per direction of Enginee-in-Charges.
10
2050
20500
... More
Note - 1- Rates are inclusive of all taxes but excluding GST which shall be paid extra as applicable 2- Labour cess @ 1% will be deducted from contractor's bill at the time of payment
-
-
-