Public Works Department Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Public Works Department - PWD Tender
Road Construction
Eprocure
Opening Date27 Dec 2024
Closing Soon16 Jan 2025
Tender Amount₹ 40,22,00,000
Costs
EMD
₹ 50,00,000Document Cost
₹ 2,715Tender Fee
Refer Documents
Summary
Widening And Strengthening Of Two Lane To Four Lane Of Sh-173 Mandhana Ganga Bairaj Shuklaganj Purwa Mohanlalganj Road Km
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_CEUCZ_987527_1Tender No
4963MT/1MT-Etender-UC/2024 Dt. 18-09-2024Tender Authority
Public Works Department ViewPurchaser Address
-Website
http://http://uppwd.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table No. 300-2 (Carted up to 2km) (Including labour Cess & Excluding GST)
15200
-
-
... More
Dismantling of flexible pavements and disposal of dismantled materials up to a lead of 1000 metres, stacking serviceable and unserviceable materials separately (Including labour Cess & Excluding GST)
1587
-
-
... More
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401(B) ( Material is get after dismentaling) (Including labour Cess & Excluding GST)
1110.9
-
-
... More
Construction of granular sub-base by providing close graded Material, mixing in a mechanical mix plant at OMC, carriage of mixed Material to work site, spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to achieve the desired density, complete as per clause 401(B) (Grade 1) (Including labour Cess & Excluding GST)
20478
-
-
... More
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
(Including labour Cess & Excluding GST)
12479
-
-
... More
primer coat with SS-2 Grade bitumen Emulsion on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means. (Including labour Cess & Excluding GST)
81262
-
-
... More
Recycling pavement by cold milling of existing bituminous layers, planning the surface after cold milling, reclaiming excavated material to the extent of 30 per cent of the required quantity, hauling and stock piling the reclaimed material near the central recycling plant after carrying out necessary checks and evaluation, adding fresh material including rejuvenators as required, mixing in a hot mix plant, transporting and laying at site and compacting to the required grade, level and thickness, all as specified in clause 517. (Including labour Cess & Excluding GST)
4508
-
-
... More
Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder (VG-40) @ 4.0 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Grading-1) (Including labour Cess & Excluding GST)
5234.04
-
-
... More
Providing and laying dense graded bituminous macadam with higher capacity batch type HMP using crushed aggregates of specified grading, premixed with bituminous binder (VG-40) @ 4.5 per cent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. (Grading-2) (Including labour Cess & Excluding GST)
5730.61
-
-
... More
Providing and applying tack coat with bitumen (VG-10) using Bitumen pressure distributor at the rate of 0.20 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. (Including labour Cess & Excluding GST)
121612.29
-
-
... More
Providing and laying bituminous concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with bituminous binder (VG-40) @ 5.4 per cent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects (Grading-2) (Including labour Cess & Excluding GST)
4864.49
-
-
... More
Construction of 1.20m Median with cement concrete kerb with top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade including PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete laid manually also including white cement,putty &Two coat plastic paint all complete with detailed drawing and design as per direction by E/I.
(Including labour Cess & Excluding GST)
5860
-
-
... More
Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days. (Including labour Cess & Excluding GST)
10.5
-
-
... More
Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications.(Grade M-20) (Including labour Cess & Excluding GST)
39.5
-
-
... More
Supplying, Fitting and Placing un-coated HYSD bar Reinforcement in Foundation complete as per Drawing and Technical Specifications. (Including labour Cess & Excluding GST)
3.3
-
-
... More
Maintenance of Constructed Road for next Five Year after the actual date of completion,Total maintenace Cost 2.50% of BOQ shall be paid in the form of installment as below,The payment shall be the inclusive of cess but Excluding GST,Payment shall be done as per satisfaction of Engineer-in-Charge regarding maintenance work carried out by Contractor.
(i) From Completion of 1 Year to 2nd Year 0.25% of Bill Amount.
6.25
-
-
... More
(ii) 2nd Year to 3rd Year 0.50% of Bill Amount.
6.25
-
-
... More
(iii) 3rd Year to 4th Year 0.75% of Bill Amount.
6.25
-
-
... More
(iv) 4th Year to 5th Year 1.00% of Bill Amount.
6.25
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements
Past BiddersThis list is curated from the bidders of the similar tenders in the past
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%