Pashchimanchal Vidyut Vitran Nigam Limited Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Pashchimanchal Vidyut Vitran Nigam Limited - PVVNL Tender
Finance And Insurance Sectors
Eprocure
Opening Date31 Jan 2024
Closing Date9 Feb 2024
Tender AmountRefer Documents
Costs
EMD
₹ 11,100Document Cost
₹ 1,180Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_PVVNL_888011_1Bid Award Id
ViewTender No
E-TENDER NO-169/2023-24Tender Authority
Pashchimanchal Vidyut Vitran Nigam Limited ViewPurchaser Address
-Website
http://http://pvvnl.org/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
Work of deposit Scheme against passed estimate under jurisdiction of EDD-4, shamli under EDC,Shamli
Work of deposit Scheme against passed estimate under jurisdiction of EDD-4, shamli under EDC,Shamli
BOQ Items
Dismantling of Existing ( 5 MVA-1 Nos) Transformer Kept at suitable place outside switchyard. a. Disconnecting HT cable connection from 33 KV side & 11 KV side of 05 MVA Power transformer for removing power transformer form plinth after proper shutdown. Dismantling of 11 KV cable support structure, copper bus bar structure. M.S. Frame etc.
1
-
-
b.Disconnecting copper flexible /Earthing strip from Power transformer neutral & Dismantling neutral earthing system to facilitate removal of Power transformer from plinth.
1
-
-
c. Disconnecting Earthing strip from body of 05 MVA Power transformer.
1
-
-
d. Draining of transformer oil from conservator, radiators of existing 05 MVA T/F, at 33/11 KV S/S into the dry & clean drums and stacking at the safe place in substaion outside of switchyard.
1
-
-
e. Removal of conservator, radiators and other accessories from existing 05 MVA Power tranformer.
1
-
-
f. Safe shifting of 05 MVA Power transformer main body and other accessories from the substation switchyard to outside the switchyard at suitable place assigned by concern J.E/SDO (distribution)
1
-
-
g. Re- assembling of conservator, radiators and other accessories to existing 05 MVA Power transformer.
1
-
-
h. Re-filling the transformer oil ( old &used in existing 5 MVA T/F)
1
-
-
Installation of 33/11 KV, 10 MVA Transformer :- a. Shifting of available 10 MVA 33/11 KV, Transformer to transformer plinth in Switch Yard.
1
-
-
b. Erection of shifted Tranformer at plinth by fixing all accessories like readiators, conservator tank, filling the transformer oil to desired level and ensuring that there is no leakage, complete job in all respect.
1
-
-
Water level earthing by Boring an lowering of G.I. pipe size 40 mm dia & thickness 2mm into the ground at 20 mtr depth or upto the water level with the lower end of solid copper cone approx 225 mm long and 750 gm in weight shall be provided and screwed in pipe as well as bringing out a continuous copper wire 6 SWG from the cone up to the ground surface where it will be bolted to the G.I. earth strip for transformer neutral connections, the earth strip will be welded to the G.I. pipe and neutral earthing support.
3
-
-
b. Fabrication and erection of neutral earthing I. type support made of M.S. Channel size 100x50 mm. Structure shall be 4 mtr. Long with 1 mtr. Arms and 0.75mtr bracing. Structure shall be grouted in ratio 1:3:6 in block size 300x300x1000mm including plinth and painted with one coat of Ready Mixed primer and two coat of enamel Aluminium paint work includes connectingf neutral bushing rod of power Transformer and M.S. Earhing strip with the help of flexible copper bond, M.S. Bolt and washer with stone pad of size (300x300x75mm)
1
-
-
Power Tranformer Plinth Repair.
1
-
-
Erection of metering room 8x6x10 mtr for metering cubical at S/S Yard.
1
-
-
Fabrication and erection of cable support made of two piecces of M.S. channel (100x50x6)mm' 2.75 meter long, joined to each other by means of 5 nos. M.S. Angle (50x50x6) mm pieces of size 0.75 mtr long each by welding at equal intervals and grouting in a block of size (300x1000x1000) mm in C.C. 1:3:6 complete with one coat of reay mixed primer an tow coats of Al.Paint. works includs providing of three Nos. M.S. clamps made of (50x6) mm M.S. Flat for holding the cable including nus and bolts with stone Pad of size (300x300x75mm)
1
-
-
Fixing 110 mm dia 2mm thick 2 M long G.I.Pipe over 11 KV, 3x300 sq mm XLPE cable before mounting the 2 No. Cable on cable support structure. Work includes fixing of clamp, sealing of top and bottom end of the G.I.Pipe. One ends of G.I.Pipe is to buried under earth about 500 mm.
1
-
-
Fabrication of copper bus bar of size (2500x50x6) mm in L.V side of 10 MVA 33/11 KV , power tranformer .Work includes connection of outside bus bar in L.V. side busing rod of Power Transformer and other side with outdoor 11 KV cable box as well as providing empire tape and H.T. tape etc. for proper insulation work.
3
-
-
Preparation of 11 KV Power Cable ends:- Making of cable end termination by Heat shrinkable out door jointing kits suitable for 11 KV , 3x300sq.mm XLPE cable, Providing, fixing and crimping of proper size good quality lugs comple in all respect.
3
-
-
Making of cable end termination by Heat shrinkable indoor jointing kits suitable for 11 KV , 3x300sq.mm XLPE cable, Providing, fixing and crimping of proper size good quality lugs comple in all respect.
3
-
-
Installation of 33 KV Isolators with Structure: - Assembling and installatin of line Isolator on the isolator structure. Adjusting of peeratin mechanism in proper alignment so as to ensure smooth operation of the same. In case of line Isolator proper operation of earth links shall also be ensured. The work includes fabrication for proper fixing if required.
1
-
-
Cable laging with sand & bricks
60
-
-