If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search &amp; bid for etender UP.

Municipal Corporation Tender

Works
Civil And Construction
Drainage Work
Eprocure
Opening Date25 Jan 2024
Closing DateCancelled
Tender Amount₹ 9,28,941 
Notes
Download

Costs

Summary

Laying Of Sewer Line 130m Length Dia250mmnp3 Sewer Line From Chhamuhani Chauraha J28 1 To J28 16a Aayat Creation Aagaganj Bageshwari Ward In Jaitpura

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Bailing out or pumping out water / liquid mud during trench excavation. This includes providing necessary fuel, labour T&P etc. required for proper running of well point equipment of required capacity for lowering the water table during excavation and laying of sewers. Excavation of trenches only.

20

17600

880

... More
Cartage of 250mm dia RCC pipe NP3 class and specials from store to the site of work. laying of the same pipe in to the trenches in depth as required below the ground level, true to alignment chocking the point laying sewer pipe with jointing materials including excavation of the below invert level of pipe and testing of laid pipe line complete excluding the cost of excavation of earth and refilling of trenches from ground level to invert level of pipe. 250 mm dia pipe (Depth 00.00-01.50 m BGL)

130

58020

446.31

... More
Providing and erecting temporary baricading at site as per drawing/ direction of Engineer-in-Charge which includes writing and painting, arrangement for traffic diversion such as traffic signals during construction at site for day and night, reflective signs, marking, flags, caution tape as directed by the Engineer-in-Charge.

260

2600

10

... More
Providing and laying Granular(GSB) bedding with carefully compacted graded hard crusher broken stone of 100% passing through 20mm sieve, 20-50% passing through 10mm sieve and 100% retained on 6mm sieve. 0.00 – 01.50m

13

36931

2840.88

... More
BRICK: CIRCULAR/RECTANGULAR/PRECAST Construction of brick masonry manhole in first class brick of following types and sizes in cement mortar 1:4, P.C.C. top slab with 1:2:4, foundation concrete 1:2:4, inside & outside plastering 12mm thick with cement mortar 1:3 finished with floating coat of neat cement and making channels in cement concrete with 1:2:4, finished with floating coat of neat cement complete with including CI steps (PVC encapsulated) staggered at 0.3 m interval, RCC arch above pipe including excavation, reinforcement and form work, RCC frame and cover. Depth=1.21 to 1.65 and Type-A

13

215267

16559

... More
R.C.C. PIPES: NP-3 CLASS Providing and conveying to site RCC pipes with sulphate resistant cement of following class (with s/s ends) and diameter as per IS: 458 - 2003 (Amended up to date) including all taxes (Central and Local) with Rubber gaskets as per (EPDM/SBR) for sewer lines as per IS: 5382-1985 or (Amended up to date), including cost of Rubber gaskets, labour required, transportation, loading, unloading & stacking etc.(excluding cost of laying, jointing, testing and commissioning). The pipe shall be ISI marked. 250 mm internal diameter.

130

111800

860

... More
Provide and fix open timbering (covering 1/3rd of surface area by plank in trenches for the following depths below G.L. consisting of 40mm thick approved country wood plank for poling board 125x75mm Indian Sal wood wallers and 100mm diameter Sal wood ballies for shuttering at 1.50m c/c including removal after laying (will be taken as one side for the purpose of payment and measurement i.e. area equals to length x depth of trenches). dismantled timbering material will be the property of the contractor. 00.00m – 03.00m B.G.L.

60

23704

395.08

... More
Provision for inter connection in between proposed sewer line and existing sewer line & RTS disposal point including cost of all labour material and special T&P required for connection and re-instate the same complete in all respect. 300mm Internal diameter.

4

20000

5000

... More
SHIFTING/REPAIRING WORK: - Repairing of water service connection damaged during laying of sewer line with material, labour, T&P, etc., all complete.

30

42319

1410.65

... More
Repairing of sewer service connection damaged during laying of sewer line with material, labour, T&P, etc., all complete.

30

67155

2238.5

... More
Repairing of water supply pipe line different size damage during laying of sewer line with all labor, material T&P etc complete work.

8

64000

8000

... More
Lighting during laying of sewer line at site with all labor, material T&P etc complete. work.

120

6720

56

... More
Road restoration work of chauka stone/Interlocking at site with all labor, material, T&P etc complete.

130

40293

309.95

... More
Site Clearance work after completion work with all labor, T&P, loading-unloading, transportation etc complete work.

130

2340

18



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.