Moradabad Development Authority Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Moradabad Development Authority Tender
Eprocure
Opening Date26 Sep 2019
Closing Date15 Oct 2019
Tender AmountRefer Documents
Costs
EMD
₹ 37,000Document Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2019_MDA_384916_4Bid Award Id
ViewTender No
74IV/MDA/UDDHAN/2019Tender Authority
Moradabad Development Authority ViewPurchaser Address
-Website
http://etender.up.nic.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
M-150 brick work in Superstructure 1:4 (one cement and four coarse sand) including necessary cutting and moulding of brick and rewuried thickness of walls not to be less than 1.0 brick. SI 307+309+310 2017-18
82
419840
5120
Cleaning jungle including up rooting of rank vegetation grass, bush, wood tree annd sopling girth up to 30 Cms measured at the hight of 1 m above groune lavel and removed of rubbish upto a distance of 50 m outside the periphery of area cleared. S.i.No -259- SOR 2017-18
3650
10037
2.75
Concrete with 2cm. Guage stone ballast fine sand of 1.2:5 :M. and cement in proportion of 1:2:4 in foundation and under floors including supply of all meterials, labour and T&P etc. required for proper completion of work. SI No. 279-A 2017-18
4
24800
6200
12mm thick plaster with (1:4) One part of cement and Four part of approved fine sand including supply of alla material labour and completion of work . SI.No.- 584A 2017-18
1050
147000
140
Finishing wall with three coat of water proof cement paint snowecem of approved make and quality of new work with three coat to give and even shade inculding priparing surface by the throughly cleaning and send preparing and supply of all material laber and t&p etc. required for proper completion of the work. SI.No.(660 + 661) 2017-18
1050
69300
66
40 mm thick fine dressed stone flooring over 20 mm (average) thick base of cement mortar 1:5 (1 cement : 5 coarse sand), With joints finished .DSR No. 11.28.1/2018
395
351135
888.95
Supply and fixing benches made out 1" dia from tubler pipe 50X12 mm pipe and beautifully painted (A.R.)
24
98400
4100
Earth work filling including supply of all necessary quality good earth also including 8 Km. from the site of work. 2.5,2.6,2.7,2.8,2.9-86
1092
313404
287
Rough dressing the trenched ground including breaking clods.DSR 2.5-2018
3639
4730
1.3
Uprooting weeds from the trenched area after 10 to 15 days of its floodingwith water including disposal of uprooted vegetation .DSR 2.6-2016-18
3639
15647
4.3
Fine dressing of the ground..DSR 2.7-2018
3639
11826
3.25
Supply & stacking of wormi composed of good quality approved by the horticulture officer or his representative. (A.R.)
54.58
76412
1400
Supply of anti termite (methgl para thian) & used as per disection in charge of the work.
364
9100
25
Spreading of sludge, dump manure and/or good earth in required thickness as per direction of officer-in-charge (cost of sludge, dump manure and/ or good earth to be paid separately)..DSR 2.8-2018
363.9
16793
46.15
Mixing earth and sludge or manure in the required proportion specified or directed by the Officer-in-charge .DSR 2.9-2018
364
11684
32.1
Supplying & Stacking of Selection No. 1/ grass at site fresh & free from weeds having proper roots in green including loading, unloading, carriage and all taxes paid etc. and as per direction of officer in charge. item No. 2.35 DSR 2018
803
40792
50.8
Grassing with selection No. 1 grass including watering and maintenance of the lawn for 30 day or more till the grass forms a thick lawn, free from weeds and fit for mowing including supplyng good earth, if needed (the grass and good earth shall be paid for separately).DSR 2.10.1/2018
3639
56586
15.55
Providing and Stacking of inerme (Clerodendrum) having ht. 25 cm to 30 cm multi branched in 20 cm size of earthen pot/plastic pot & as per direction of the officer-in-charge.item No. 6.6 DSR 2018
3000
30750
10.25
Complete maintenance of the entire garden features having as per yard stick in the garden area i.e. lawn trees, shrubs, herbs, hedge, flower beds, foliages, creepers etc. For one Year including hoeing, weeding pruning replacement of plants, gap filling, watering, mowing of lawn, grass cutting by lawn mover and brush cutter , removal of garden waste, applying insecticide, pesticide & fertilizers(whenever required) top dressing of lawn with good earth and manure and maintenance of other garden related works as directed by office-in-charge (Cost of Good Earth, Manure, Fertilizer, Insecticide , Pesticide will be provided by the Department & lawn mover and brush cutter with fuel, other T & P material / articles shall be provided by the contractor.) and as per direction of officer in charge.Item No. 2.40.5 DSR 2018
3639
98253
27