Moradabad Development Authority Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Moradabad Development Authority Tender
Civil And Construction
Road Construction
Eprocure
Opening Date8 Apr 2022
Closing Date29 Apr 2022
Tender Amount₹ 3,53,70,739
Costs
EMD
₹ 7,07,500Document Cost
₹ 5,900Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2022_MDA_685979_1Bid Award Id
ViewTender No
45/MDA/CE/2022-23Tender Authority
Moradabad Development Authority ViewPurchaser Address
-Website
http://etender.up.nic.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Providing and laying Bituminous Concrete with higher capacity batch type hot mix plant using crushed aggregates of specified grading, premixed with 60/70 (VG-30) bituminous binder @ 5 % of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORT&H specification clause No. 507 complete in all respects
1770
-
12615
Supply & Laying of 80 mm thick precast cement concrete paver block with a top layer of minimum 8mm thickness having plan dimension 200 x(160+120) of O.P. cement, smooth high gloss finish, skid reditant, Manufactured from rubber moulds threw vibro - compression machanism. The compressive strength of concrete paver blocks shall not be less than 30 MPa & weight 5 kg/no. confirming to IS: 15658-2006 with a 4cm thick layer of fine sand including cost of all materials, labour T&P etc. required for proper completion of the work as per direction of E/I. Item No. 5(i) From page No. 50/PWD SOR 2020
(A) Grey Colour
2300
-
900
Cleaning Jungle including uprooting of Rank, vegitation, grass, bush, wood, trees, and sapling girth up to 30 cm measured at aheight of 1 m above ground level and Rmoval of rubbishup to adistance of 50 M OUTSIDE THE PERIPHERY OF AREA cleared. (S.I. No. 259)
21340
-
4
M-150 brick work in 1:4 (one cement and four coarse sand of 2.25 F.M. mortar) in foundation and including supply of all material and T &P etc. required for proper completion of work. (S.I. 307A)
552
-
4800
Dismantling existing plaster including disposal of refuse a with in a distance of 60 M. (S.I. 706/2020
7000
-
30
12 mm. thick plaster with 1 : 4 (one part cement & Four parts of coarse sand of 2.75 F.M.) over brick work minimum thickness not to be less than 1 cms. Including supply of all material , labour , T & P etc. required for proper completion of the work. ( S.I.No.584)
14000
-
180
Cement Concrete with 2cm, guage approved stone ballast coarse sand and cement in proportion of 4:2:1 including supply of all materials, labour and T&P etc. required for proper completion of work. ( S.I.No.279A)
92
-
6300
Painting two coat over priming coat (including cost of priming coat) on new wood or plastered surface with superior synthetic enamel paint of standered make brushing to give an even shade and finished and including cleaning the surface all durt and other foreing metter sand paparing and stripping including cost matter and scoured with wire brushed fine steel/wood scrappers sand paparing and knotting including coat of all and supply of all materials, labour tools and plants etc. required for proper completion of the work. New item 1b+2+4(iii)
4060
-
82
Earth work in cutting or in embankment in foul condition, & disposel of 1 km. distance excavation to be in the form of regular pits not exceeding 1/2 meter depth and earth work in embankment to be in 20cm layers including ramming and dressing the surface to be required levels and 30M lead. the earth from cutting to be used in making embankment or ito be deposited as spoil banks with in 30M distance as directed by the Engg-in-Charge. S.I.No-253(a)
3750
-
210.7
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements