Minor Irrigation Department Tender

If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search &amp; bid for etender UP.

Minor Irrigation Department Tender

Works
Civil And Construction
Excavation
Eprocure
Opening Date23 Aug 2024
Closing DateCancelled
Tender Amount₹ 47,50,000 
Notes
Download

Costs

Summary

Deeping And Rennovation Of Pond Wait Wala Talab Block Simbhawali, Hapur

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
Digging of Pond upto 3.00m deep By Excavator Machine (Poclain) and Including Shifting of excavated soil to Bund of Pond by Tractor Trolley.

13840

-

-

... More
Earth work in manual dressing & Profile making of bund including remming and dressing the surface to required levels and slopes.(15.0% Earth actual qty for Bund) As per IDS. Chapter-V Item no 4

2076

-

-

... More
Dewatering Before and during the digging earth work, by diesel pumpset.

620

-

-

... More
Construction work of Inlet 3 nos :-

-

-

-

... More
E/W in digging in foundation in ordinery soil.

34.8

-

-

... More
C.C.1:4:8 in Foundation with cement, Fine sand and 40 mm gauge Brick ballast, including all.

14.94

-

-

... More
(i) Supply of RCC Hume pipe 900mm dia, NP-3 ISI mark including cartage, loading & Unloading and all tax etc. supply at work site.

37.5

-

-

... More
(ii) Laying and jointing of 900mm dia Hume pipe in position, jointed with jute and stiff mixture of cement morter in 1:2 cement and fine sand including testing of joints complete, labour and T&P etc. required for proper completion of work.

37.5

-

-

... More
First class Brick work in 1:4 Cement, Sand mortar including all.

20.07

-

-

... More
C.C.1:2:4 in cement, coarse sand and 10 to 20 mm stone grit, including all.

1.71

-

-

... More
Cement plaster 1:4 cement, Sand, mortar including all material & labour etc.

75

-

-

... More
Construction work of Outlet :-

-

-

-

... More
E/W in digging in foundation in ordinery soil.

24.62

-

-

... More
C.C.1:4:8 in Foundation with cement, Fine sand and 40 mm gauge Brick ballast, including all.

4.08

-

-

... More
(i) Supply of RCC Hume pipe 900mm dia, NP-3 ISI mark including cartage, loading & Unloading and all tax etc. supply at work site.

12.5

-

-

... More
(ii) Laying and jointing of 900mm dia Hume pipe in position, jointed with jute and stiff mixture of cement morter in 1:2 cement and fine sand including testing of joints complete, labour and T&P etc. required for proper completion of work.

12.5

-

-

... More
First class Brick work in 1:4 Cement, Sand mortar including all.

6.58

-

-

... More
C.C.1:2:4 in cement, coarse sand and 10 to 20 mm stone grit, including all.

0.32

-

-

... More
Cement plaster 1:4 cement, Sand, mortar including all material & labour etc.

25.85

-

-

... More
Construction work of Ramp :-

-

-

-

... More
E/W in digging in foundation in ordinery soil.

60.14

-

-

... More
C.C.1:4:8 in Foundation with cement, Fine sand and 40 mm gauge Brick ballast, including all.

13.79

-

-

... More
First class Brick work in 1:4 Cement, Sand mortar including all.

14.07

-

-

... More
C.C.1:2:4 in cement, coarse sand and 10 to 20 mm stone grit, including all.

5.68

-

-

... More
Cement plaster 1:4 cement, Sand, mortar including all material & labour etc.

17.75

-

-

... More
Construction work of Ghat :-

-

-

-

... More
E/W in digging in foundation in ordinery soil.

30.22

-

-

... More
C.C.1:4:8 in Foundation with cement, Fine sand and 40 mm gauge Brick ballast, including all.

12.42

-

-

... More
First class Brick work in 1:4 Cement, Sand mortar including all.

20.29

-

-

... More
C.C.1:2:4 in cement, coarse sand and 10 to 20 mm stone grit, including all.

3.58

-

-

... More
Cement plaster 1:4 cement, Sand, mortar including all material & labour etc.

55.25

-

-

... More
Construction work of Pacca Benches and other work in pond:-

-

-

-

... More
E/W in digging in foundation in ordinery soil.

3.78

-

-

... More
C.C.1:4:8 in Foundation with cement, Fine sand and 40 mm gauge Brick ballast, including all.

3.49

-

-

... More
First class Brick work in 1:4 Cement, Sand mortar including all.

13.12

-

-

... More
Brick on edge 1:6 cement, sand morter .

250

-

-

... More
C.C.1:2:4 in cement, coarse sand and 10 to 20 mm stone grit, including all.

0.63

-

-

... More
Cement plaster 1:4 cement, Sand, mortar including all material & labour etc.

52.56

-

-



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.