Kanpur Electricity Supply Company Limited Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Kanpur Electricity Supply Company Limited - KESCO Tender
Software and IT Solutions
Eprocure
Opening Date6 Nov 2024
Closing Date20 Dec 2024
Tender Amount₹ 2,36,59,00,000
Costs
EMD
₹ 4,73,20,000Document Cost
₹ 29,500Tender Fee
Refer Documents
Summary
Scada And Smart Technolgy Supply/integration Under Revamped Distribution Sector Scheme (rdss)
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_KESCO_971224_1Tender No
01/RDSS/SCADA AND SMART TECH/KESCo/2024-25Tender Authority
Kanpur Electricity Supply Company Limited ViewPurchaser Address
-Website
http://https://kesco.co.in/wss/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Workstation with dual TFT Monitors ( S/S monitoring)
5
-
-
Workstation with dual TFT Monitors (Network monitoring)
3
-
-
Remote VDUs with one TFT Monitors
4
-
-
Developmental console with one TFT
1
-
-
Storage & Backup Devices
-
-
-
SAN STORAGE 12 TB
2
-
-
Exteranl DAT drive
2
-
-
Routers
-
-
-
Router at remote VDU
4
-
-
Security system (DMZ)
-
-
-
Router
2
-
-
Firewall & network IDS/IPS
2
-
-
Layer III switch
2
-
-
Mandatory Spare @ 5% of hardware part for control cneter
1
-
-
IT Hardware for SCADA/ADMS for backup Control Centre
-
-
-
ISR server
2
-
-
SMS gateway
2
-
-
Workstation with dual TFT Monitors ( S/S monitoring)
5
-
-
Workstation with dual TFT Monitors (Network monitoring)
3
-
-
Developmental console with one TFT
1
-
-
Storage & Backup Devices
-
-
-
Exteranl DAT drive
2
-
-
SAN STORAGE 12 TB
1
-
-
Security system (DMZ)
-
-
-
Router
2
-
-
Firewall & network IDS/IPS
2
-
-
Layer III switch
2
-
-
Mandatory Spare @ 5% of hardware part for backup center
1
-
-
Software required for SCADA/ADMS at MCC
-
-
-
ISR Software
1
-
-
Integration with National SCADA Resource Center
1
-
-
Network Management Software
1
-
-
Any other software to meet functional/performance requierments to achieve SCADA system as per RFP
1
-
-
Software required for SCADA/ADMS at BCC
-
-
-
Any other software to meet functional/performance requierments to achieve SCADA system as per RFP
1
-
-
ISR Software
1
-
-
Remote terminal Unit (RTU)
-
-
-
RTU base equipment comprising panels, racks, sub-racks, Power Supply modules, CPU, interfacing equipment, required converters & all other required items/accessories including complete wiring for all modules
92
-
-
Layer II Switch for integration of Numerical Relay with RTU ( 24 Port) ( Industrial grade ) IEC 61850
92
-
-
Multifunctuions transducers
365
-
-
Contact Multiplying Relays (CMRs)
13206
-
-
Heavy duty relays for Control
2300
-
-
Transformer Transducers
444
-
-
Dummy Breaker Latching Relays
92
-
-
Single TFT PC for LDMS
106
-
-
LDMS software
106
-
-
Mandatory Spare @5% of hardware part for RTU
1
-
-
TEST Software/Hardware Tools for RTU
-
-
-
RTU Database Configuration & Maintenance Software tool
6
-
-
Master Station cum RTU Simulator & Protocol analyser software tool
6
-
-
Laptop for the installation of above software tools along with interfacing hardware including Hub
6
-
-
Feeder Remote terminal Unit (FRTU)
-
-
-
Mini pole mounted FRTU base equipment along with enclosure suitable to work in open environment (Adequate protection from water & dust) , racks, sub-racks, Power Supply modules with power backup , I/o modules, CPU, interfacing equipment, required converters & all other required items/accessories including complete wiring for all modules.
1238
-
-
FRTU Database Configuration & Maintenance Software tool
14
-
-
Master Station cum FRTU Simulator & Protocol analyser software tool
14
-
-
Laptop PC for above software tools along with interfacing hardware including Hub
14
-
-
Mandatory Spare @5% of hardware part of FRTU
1
-
-
Communication System
-
-
-
2 year Charges for 10 Mbps Links with RTUs from date of project go live
92
-
-
MPLS/SDWAN Router
98
-
-
2 year Charges for 2 Mbps Links with FRTUs /FPI from date of project go live
1238
-
-
Modems
1238
-
-
Mandatory Spare @ 5% of hardware for communication system
1
-
-
Power Supply
-
-
-
24V DC Power Supply (DCPS) system based on SMPS for RTU / Data Concentrator / Communication Equipment
92
-
-
24 V DC Power Supply (DCPS) system based on SMPS for FRTU
1238
-
-
UPS (2 kVA )
4
-
-
Mandatory Spare @5% of hardware for power supply item
1
-
-
RMU
-
-
-
11 KV 3W RMU
655
-
-
11 KV 4W RMU
118
-
-
33KV 4W RMU
45
-
-
11 KV Auto recloser
257
-
-
Numerical relay /BCPU(SCADA compatible)
660
-
-
11 KV Sectionalizer
163
-
-
Mandatory Spare @5% of hardware for RMU, sectinaliser, auto recloser and bpcu
1
-
-
Project Management Cost
-
-
-
Installation, Testing and Commissioning Cost to Integrate Entire SCADA & IT (relevant to SCADA) Infrastructure
1
-
-
Integration with legacy applications & Data Migration
1
-
-
Training for the Employees
1
-
-
FMS Charges
-
-
-
FMS SERVICES FOR 5 YEARS AFTER GO-L IVE
1
-
-
DT Health Management(DTHM)
-
-
-
Lug Temprature Sensor
5200
-
-
Oil Temparature Sensor
1300
-
-
Oil Level Sensor
2600
-
-
5G Gateway
1300
-
-
DCU
1300
-
-
Software as a Service(SaaS) Base web dashboard(12 Month)
2
-
-
Annual Maintenance (12 Month)
2
-
-
Voltage Regulations & Harmonic Management-Power Quality meters, Active Harmonic Filter and Smart Inverters
-
-
-
Power Quality Meter/ Analyzer
106
-
-
Active Harmonic Filter
106
-
-
Smart Inverters
106
-
-
Reconductoring and Development of Ring Main System
-
-
-
Cable H.T.XLPE 11 KV 3x185 SQ.M.M
155.75
-
-
Cable Termination Kits O/D 11 KV 3x185 XLPE
2437
-
-
Cable Termination Kits I/D 11 KV 3x185 XLPE
2437
-
-
Cable H.T.XLPE 33 KV 3x300 SQ.M.M
9
-
-
Cable Termination Kits O/D 33 KV 3x300 SQ.M.M
180
-
-
Cable Termination Kits I/D 33 KV 3x300 SQ.M.M
180
-
-
11 Mtr STP Pole (SP-55)
900
-
-
9.5 Mtr STP Pole (SP-33)
300
-
-
MS Items such as Clamp, MS Channel, MS Angle
9
-
-
MS Pipe 160 mm dia 3 metre long
1636
-
-
Sundries Items such as earthing set, stay set, Danger plate, Pin Insulator, Barbed wire, Nut bolts, disc insulators, etc.
1
-
-
Control/power cable for RTUs from outdoor switchgear,if any at S/S and numerical relays
-
-
-
Control /Power cable
19
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements
Past BiddersThis list is curated from the bidders of the similar tenders in the past
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user