Irrigation Department Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Irrigation Department Tender
Civil And Construction
Civil Works Others
Excavation
Irrigation Work
Water Storage And Supply
Eprocure
Opening Date2 Mar 2024
Closing DateCancelled
Tender AmountRefer Documents
Costs
EMD
₹ 7,48,000Document Cost
₹ 6,094Tender Fee
Refer Documents
Summary
Restoration Of Kushinagar Distributary From Km. 0.000 To Km. 16.100
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_UPIDC_909441_3Tender No
05/SE/2023-24Tender Authority
Irrigation Department ViewPurchaser Address
-Website
http://http://idup.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
1st class brick work in 1:4 cement mortar with class brick M-150, sonbhadra coarse sand of FM. Not less then 2.00, including all cost of materials,T&P and labours and other accessories required for proper completion of work
306.22
-
-
Providing and laying Steel Reinforcement including cost of steel shaping, cutting, bending, placing in position, binding with steel binding wire etc. including cost of all materials, labour and T&P with all leads and lift for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
3.79
-
-
Supply and Fixing of 110 mm P.V.C. Pipe for Drainage spout and weep hole including cost of all material ,labour, t&p etc. required for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
2.1
-
-
Supply and laying of 18 MM thick joint filler board in construction joint including cost of all material, labour, T&P required for proper completion of work. As per ID specification
12.03
-
-
Reinforced cement concrete in 1:1:2(M-25) in all RCC work with Coarse sand having F.M. Not less than 2.5, Crushed Stone Aggregate of nominal size 12.5 mm to 20 mm, Mechanically mixed and properly compacted by Vibrator including cost of all materials but excluding cost of steel, labour and T&P with all leads and lift/down for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
50.97
-
-
Struck deep Cement Pointing in 1:2 cement mortar in approved cement and coarse sand (Sonbhadra) with all lead & lift including all material, labour, T&P etc all complete.
1296.19
-
-
First class Brick soling on ramp including cost of all matterials. T&P and labours and other accessories required for proper completion of work.as directed by Engineer-in-Charge as per I.D. specification.
17016
-
-
Dismantling of Cement Concrete work with lime/cement mortar and its proper disposal within an initial lead of 60m with cost of labour, T&P for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
36.54
-
-
Supplying and Fixing wheel guard stone including cost of all material ,labour, t&p etc. required for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
12
-
-
Sign board at site for notice both side including cost of all material ,labour, t&p etc. required for proper completion of work. as directed by Engineer-in-Charge as per I.D. specification.
6
-
-
Earth work for back filling, making Ramp for Diversion and making jeepable service road including all cost of materials,T&P and labours and other accessories required for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
664.56
-
-
Finishing wall with Premium Acrylic Smooth exterior paint of required shade: New work (2 or more coat applied @1.67 ltr/10 sqm. over and including primimg coat of exterior primer applied @2.20kg/10 Sqm) (apex Ultima all weather coat) Asian, Berger. including supply of all materials, labour, T&P etc. for proper completion of work.
1174.74
-
-
Reinforced cement concrete in 1:1.5:3 in all RCC work with Coarse sand having F.M. Not less than 2.5, Crushed Stone Aggregate of nominal size 12.5 mm to 20 mm, Mechanically mixed and properly compacted by Vibrator including cost of all materials but excluding cost of steel, labour and T&P with all leads and lift/down for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
6.91
-
-
Laying C.C. work in 1:2:4 (M15) sonbhadra coarse sand of FM. Not less then 2.00 and dala grit (12.5mm to 20mm.) including all cost of materials,T&P and labours and other accessories required for proper completion of work. As per direction of direction of Engineer in Charge.
784.46
-
-
Providing and Laying of LDPE Film on footing box including cost of all materials, labour and T&P etc. required for proper completion of work as per direction of Engineer-in-Charge.
158.1
-
-
Fixing of RCC Precast Boundry piller including cost of all materials, labour and T&P etc. required for proper completion of work as per direction of Engineer-in-Charge.
170
-
-
Painting of RCC Precast boundry piller size 150x150x1650 (mm) including cost of material, labour, T&Petc. proper completion of work as per direction of Engineer-in-charge.
170
-
-
Laying Local Sand fill in 300 mm thick for making base of concrete including cost of all materials, labour and T&P with all leads and lift for proper completion of work as directed by Engineer-in-charge as per drawing and I.D. specification.
2175.73
-
-
Filling of Joints with Bitumen including cost of all materials, labour and T&P with all leads and lift for proper completion of work as directed by Engineer-in-charge as per drawing and I.D. specification.
2485.63
-
-
Providing and Laying sepration membrane of impermeable plastic sheeting 125 micron thick for below cc lining work incl cost of material, labour, T&Petc. proper completion of work
7252.46
-
-
Plain Cement Concrete in 1:3:6 in foundation with Coarse sand having F.M. Not less than 2.5, Crushed Stone Aggregate of nominal size of 20 mm to 40 mm, Mechanically mixed, placed in foundation and properly compacted including cost of all materials, labour and T&P with all leads and lift/down for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
57.73
-
-
Jungle clearance on branch below 30 cumec distributries ,minors and drain with service road as directed by Engineer-in-Charge as per drawing and I.D. specification.
100821
-
-
Dismantling of old and damaged Gate and Gate parts.as directed by Engineer-in-Charge.
16.8
-
-
Supply and fixing M.S. Channel section 100x50x8 mm for gate as per specification Weight of Channel @ 12.10 Kg/Mtr
776.29
-
-
Supply and fixing M.S. Angle 65x65x8 mm for gate as per specification Weight of Angle iron @ 7.70 Kg/Mtr
672.09
-
-
Supply and fixing M.S. Flat sheet 10 mm thick for gate as per specification Weight of M.S. Flat sheet @ 78.50 Kg/Sqm
490.6
-
-
Supply and fixing M.S. Black pipe 3" dia. for gate as per specification
18.7
-
-
Providing two coat enamel paint over one coat primer on gate including all materials, labour, T&P etc complete.
502.91
-
-
Greesing & oiling of Head regulator including cost of all material, labour& T&P etc. complete (unit=01 no.)
27.4
-
-
Erection of fabrication charges of gate and gate parts. (Material and labour.)
23.52
-
-
Erection of Refabricated Gate / Repaired Gate. Including cost of labour t&p etc
23.52
-
-
Providing an fixing of Bearing for gate as per specification
14
-
-
Providing an fixing Housing for gate as per specification
14
-
-
Providing an fixing Rubber Sheet 12mm for gate as per specification
21.4
-
-
110 mm dia HDPE rigid pressure pipe 6 kg/m2 etc. required for proper completion of work as per direction of Engineer-in-Charge.
67.74
-
-
160 mm dia HDPE rigid pressure pipe 6 kg/m2 etc. required for proper completion of work as per direction of Engineer-in-Charge.
92.61
-
-
Earth work in filling for restoration of the canal and tail gul section complete with proper compaction and dressing including cost of materials,labour, T&P etc
61995.5
-
-
Earth work in excavation in foundation for toe wall/top wall and for sleepers including digging and refilling the trenches with its proper disposal within 30 meter lead & all lift with cost of labour and T&P for proper completion of work as directd by Engineer-in-charge as per drawing and I.D. specification.
9164.5
-
-
Writing each letter upto 30 cm size including all cost of materials,T&P and labours and other accessories required for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
402
-
-