Irrigation Department Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Irrigation Department Tender
Irrigation Work
Eprocure
Opening Date2 Jan 2025
Closing Soon16 Jan 2025
Tender AmountRefer Documents
Costs
EMD
₹ 40,00,000Document Cost
₹ 7,354Tender Fee
Refer Documents
Summary
Rehabilitation Work Of Lining Of The Damaged Part Of The Inner Slope Of Left And Right Bank Of The Main Western Gandak Canal From Km 18.900
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2025_UPIDC_989176_2Tender No
10/SE/2024-25Tender Authority
Irrigation Department ViewPurchaser Address
-Website
http://http://idup.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
Plain Cement Concrete in 1:4:8 in base of toe wall with Coarse Sand F.M. Not less than 2.0, old dismantled brick ballast of nominal size of 25 mm to 40 mm, placed in position and properly compacted including cost of all materials, labour and T&P with all leads and lift/down for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
194.4
-
-
... More
Cement Concrete in 1:2:4 in Toe Wall, Sleepers and Top/Cut-off Wall with Coarse Sand having F.M. Not less than 2.0, Crushed Stone grit of nominal size of 12.5 mm to 20 mm, Mechanically mixed, placed in proper position and properly compacted including cost of all materials, labour and T&P etc. for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification......per cum.
5880.74
-
-
... More
Supplying and laying of Water stopper at transverse sleepers including cost of all materials, labour and T&P etc proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
9484.94
-
-
... More
Cement Concrete in M-20 (1:1.5:3 ) in Lining with Coarse Sand having F.M. Not less than 2.0, Crushed Stone grit of nominal size of 12.5 mm to 20 mm, Mechanically mixed, placed in proper position by paver machine and properly compacted including cost of all materials, labour and T&P etc. for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification......per Sqm.
37768.8
-
-
... More
Supplying and laying Coarse Sand (FM not less then 2.00) in filter including cost of all materials, labour and T&P with all leads and lift/delift for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
1467.23
-
-
... More
Supplying and laying crushed Stone Grit (12.5-20)mm in filter material including cost of all materials, labour and T&P with all leads and lift/delift for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
1467.75
-
-
... More
Supply & Laying LDPE film 200 micron thick first grade on slope below lining including cost of all materials, labour, T&P etc required for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
39482
-
-
... More
Centering and shuttering for CC work including cost of all materials, labour and T&P with all leads and lift/delift for proper completion of work as directed by Engineer-in-Charge as per I.D. specification.
33727.74
-
-
... More
Supplying and fixing Pressure Relief Valve including cost of all materials, labour and T&P with all leads and lift/delift for proper completion of work as directed by Engineer-in-Charge as per drawing and I.D. specification.
1082
-
-
... More
Running of 5 H.P. generator set pump for dewatering including arrangement of Pump suction and delivery pipes and other accessories at site including cost of all materials, labour and T&P etc.for complete work as directed by Engineer-in-Charge as per I.D.specification.
17716
-
-
... More
Providing and fixing sealing compound in between panel joints including cost of all materials, labour and T&P with all leads and lift for proper completion of work as directed by engineer -in-charge as per drawing and I.D. Specification
9511.28
-
-
... More
Supplying and laying 25 mm dia CPVC Pipe in Sleepers including cost of all material, labour & T&P etc., complete work directed by Engineer-in-charge.
3916.8
-
-
... More
Brick on edge soling with old dismantled lining brick/tile including preparation of sub-grade to prescribed camber, filling joint with Local sand/earth including cost of all material, labour and T&P etc., for proper completion of work as directed by Engineer-in-Charge and as per I.D. specification.
2136.44
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements
Past BiddersThis list is curated from the bidders of the similar tenders in the past
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%
- Bidder NameThis Information is for unsubscribed user This Information is for unsubscribed user
- Awarded Ratexx%