If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Hapur Pilakhua Development Authority - HPDA Tender
Civil And Construction
Civil Works Others
Eprocure
Opening Date7 Sep 2022
Closing Date21 Sep 2022
Tender Amount₹ 46,72,318
Costs
EMD
₹ 2,33,700Document Cost
₹ 2,360Tender Fee
Refer Documents
Summary
Construction Of Boundarywall And Pathway Of Park No. 02 And 03 At G Block Anand Vihar Scheme Part-b Hapur Hpda
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2022_HPDA_726530_1Bid Award Id
ViewTender No
221/CE/HPDA/2022Tender Authority
Hapur Pilakhua Development Authority ViewPurchaser Address
-Website
http://https://hpdaonline.com/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Cement concrete with 2cm gauge approved stone grit, coarse sand & cement in the proportion of 4:2:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work.
9
-
7000
12mm thick plaster with cement and coarse sand in 1:4 over brick work minimum thickness not to be less than 10mm thick including supply of all materials, labour and T & P etc. required for proper completion of the work.
812
-
165
Finishing walls with Water Proofing cement paint of approved make and quality on new wood with two coat to give an even shade including supply of all materials, labour, T&P etc reqd for proper completion of work.
812
-
44
Providing wall putty on new surface with approved quality material of Berger/JK/Birla or similar making 2 coats
812
-
63
Earthwork in cutting or in embankment in ordinary soil, excavation to be done from regular pits not exceeding 1/2 M. in depth and work embankment to be in 20 cm layer including ramming and dressing the surface to required levels and slopes and also including 1.5M lifts and lead up to 6 km . The earth from cutting to be used in making embankment or to be deposited as spoil banks within 30M distance as directed by the Engineer-in-charge, Including the cost of royalty of earth.
4500
-
299.4
M-150 brick work in 1:4 cement and coarse sand of 1.25 F.M.mortar in superstruture including necesssary thickness of brick as reqruired cutting & moulding of brick as equried thickness of walls not to be less than one brick including supply of all materieals labour tools& plants etc. reqruired for proper completion of the work.
75
-
5540
Cement concrete with 2cm gauge approved stone grit, coarse sand & cement in the proportion of 4:2:1 including supply of all materials, labour, Tools & plants etc. required for proper completion of the work.
13
-
7000
12mm thick plaster with cement and coarse sand in 1:4 over brick work minimum thickness not to be less than 10mm thick including supply of all materials, labour and T & P etc. required for proper completion of the work.
1500
-
165
Finishing walls with Water Proofing cement paint of approved make and quality on new wood with two coat to give an even shade including supply of all materials, labour, T&P etc reqd for proper completion of work.
1500
-
44
Providing wall putty on new surface with approved quality material of Berger/JK/Birla or similar making 2 coats
1500
-
63
Painting or varnishing work in small aras or new wood work with one coat (upto one square metre of ready mixed priming paint and two coat of approved superior quality ready mixed paint or varnish including supply of all materials, labour, tools & plants etc. required for proper completion of the work. Paint to be used should confirm the ISI no. 103-1950.
32
-
80
M.S or iron work of small size and section such as holding down bolts, hold fast tie rods, grating etc. wrought to required from including supply of steel and its wastage including cost of bolts, nuts it required for and welding, grinding and making holes as required of completion of the work. (Based on S.I No. 502)
6.5
-
5600
Supply & Fixing of R.C.C.Grill work ( Jali ) of approved pattern & make at site of work in cement concrete consisting of cement, approved coarse sand and 6 mm nominal size stone grit in the proportion of 1;2:4 & reinforced with 6 mm dia M.S. wire / bar including cutting & finishing with 1;3 cement & fine sand of 1.25 fineness modulus mortar including including supply of material, labour, T&P required for proper completion of work (1) 5.00 cm thick
500
-
735
Concrete with 4cm. gauge brick ballast, fine sand of 1.25 FM & cement in the proportion 12:6:1 in foundation & under floors including supply of all materials labour T&P etc. required for proper completion of the work.
81
-
3250
Providing & laying 60mm thick factory made cement concrete interlocking paver block of M-30 grade made by block making machine with strong vibratory compaction of approved size, design & shape, laid in required colour and pattern over and including 50mm thick compacted bed of coarse sand, filling the joints with lime sand etc. all complete as per the direction of Engineer-in-charge
606
-
719.1