Greater Noida Industrial Development Authority Tender
If you're a registered bidder for etender UP and want to inquire about any e-tender UP government has posted, this is your stop. No need to enter every detail on the website of <a href="https://etender.up.nic.in">etender.up.nic.in</a> - BidAssist filters will help you find the exact UP etender you're looking for. Read to learn how to search & bid for etender UP.
Greater Noida Industrial Development Authority - GNIDA Tender
Civil And Construction
Drainage Work
Eprocure
Opening Date30 Jan 2024
Closing DateCancelled
Tender Amount₹ 2,09,31,393
Costs
EMD
₹ 4,19,000Document Cost
₹ 3,870Tender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
2024_GNIDA_886790_12Bid Award Id
ViewTender No
SM/(E-TENDER CELL)/2024/493 DATE-24.01.2024Tender Authority
Greater Noida Industrial Development Authority ViewPurchaser Address
-Website
http://https://www.greaternoidaauthority.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
Supply of centrifugal water pump for Dewatering. (Morth-20/T&P/129)
960
412473
429.66
Exacvation in foundation in ordinary soil (Loam, clay or sand) including lift upto 1.50 M and lead upto 30M and including filling watering and remming of excavated earth into trenches and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30M from the foundation trenches. (Where machine can not reach/ move). For building work only.
Depth 0.00 m to 1.50 m below G.L
(UPPWD/SOR-20/4.01/251(a))
1918.24
182232
95
Carriage of earth/material by mechanical transport including loading, unloading and stacking.Earth (i)Lead upto 1.00 km
1438.68
64740
45
Cement concrete with 4cm gauge approved stone ballast, coarse sand & cement in proportion of 8:4:1 including supply of all material, labour, tools & plant etc, required for proper completion of the work. (UPPWD/SOR-20/5.08/281)
97.9
569778
5820
Case-II RCC Grade M-25 using batching plant transit mixer & manual placing. (MORTH-20/15.11/E/P-657)
641.66
5161487
8043.96
Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete. Up to plinth level Thermo-Mechanically Treated bars./cold twisted bars. (SAIL)
50370.31
4653209
92.38
Providing & Fixing on wall face U V stablized unplasticised -PVC pipe uPVC pipes (working pressure 4 kg / cm2 ) Single socketed pipe ( single socketed having 3.2 mm wall thickness confirming to I S 13592 (4 Kg/sqcm including joint with seal ring confirming to I S : 5382 leaving 10 mm gap for thermal expansions uPVC pipes (working pressure 4 kg / cm2 ) Single socketed pipe
110 mm dia (UPPWD/SOR-20/5.08/281)
52.8
6864
130
M-150 brick work in 1:4 (1 cement : 4 coarse sand) of 2.20 F.M. mortar in foundation and plinth including supply of all materials, labour and T&P etc. required for proper completion of work.
73.6
364320
4950
12 mm cement palster of mix: 1:4 (1 cement : 4 coarse sand) (DSR-2018/13.4.1/AR)
457
75318
164.81
Cement concrete with 2 cm gauge approved stone ballast, coarse sand & cement in proportion of 4:2:1 including supply of all material, labour, tools & plant etc, required for proper completion of the work. (UPPWD/SOR-20/5.07/279(a))
12.61
88270
7000
Labour Cess will be paid extra as per applicable
-
-
-
GST will be paid extra as per applicable
-
-
-
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements