For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.

Roads And Buildings Department Tender

Works
Civil And Construction
Bridge Construction
Opening Date9 Feb 2024
Closing Date17 Feb 2024
Tender Amount₹ 3,01,18,359 
Notes
Download

Description

Unlock the Tender details for free
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user

Contact

Unlock the Tender details for free
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost

BOQ Items

... More
DO_NOT_SHOW

-

-

-

View all details for FREE
... More
HLB across Chalivagu between Tekumatla and Ra;Supplying, fitting and fixing in position true to line and level elastomeric neoprene bearing conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications complete including all accessories as per drawing and Technical Specifications and as per MoRT&H Specification No.2000 & 2200. Bearing size 500mmx360mmx96mm

32

12552

401664

... More
HLB across Chalivagu between Tekumatla and Ra;Supplying and fixing of GI drainage spouts complete as per MoRT&H Specification No.2705 and as per drawing SD / 205.

16

1416

22656

... More
HLB across Chalivagu between Tekumatla and Ra;Providing Steel Liner of 6 mm thick for Piles including Fabricating and Setting out as per Detailed Drawings and technical specifications as directed by the Engineer -In-Charge (under the abutments A1,A2 & Piers P1, P2, P7 to 24 including fabricating and settingout complete as per Drawing and Technical Specification.)

30

109216

3276480

... More
HLB across Chalivagu between Tekumatla and Ra;Providing HYSD bars (Fe-500) primary producers like TATA,SAIL,VSP,JINDAL etc., of different diameters, wrought and put up bars of all diameters including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all handling charges and operational charges etc., and including over lapping welding if required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for foundations of R.C.C items.

62

89974

5578388

... More
HLB across Chalivagu between Tekumatla and Ra;Providing HYSD bars (Fe-500) primary producers like TATA,SAIL,VSP,JINDAL etc.,of different diameters, wrought and put up bars of all diameters including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all handling charges and operational charges etc., and including over lapping welding if required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for Sub structure of R.C.C items.

15

90288

1354320

... More
HLB across Chalivagu between Tekumatla and Ra;Providing HYSD bars (Fe-500) primary producers like TATA,SAIL,VSP,JINDAL etc., of different diameters, wrought and put up bars of all diameters including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all handling charges and operational charges etc., and including over lapping welding if required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for Super structure of R.C.C items.

73

92440

6748120

... More
HLB across Chalivagu between Tekumatla and Ra;Vibrated reinforced cement concrete M 40 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P etc., complete as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700&2100 for Crash Barriers

39

7501

292539

... More
HLB across Chalivagu between Tekumatla and Ra;Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of work as per drawing SD/205 but excluding cost of steel and its fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2702 (5th Revision) and as directed by the Engineer-in-Charge for wearing coat over Deck slab.

46

6528

300288

... More
HLB across Chalivagu between Tekumatla and Ra;VRCC M35 grade Deck slab as per drawing and Technical Specification and MoRT&H Specification No.1500, 1600 & 1700 excluding cost of steel & its fabrication charges for Super Structure Solid Slab from 5m to 10 Mht

196

8350

1636600

... More
HLB across Chalivagu between Tekumatla and Ra;Precast Girders in Vibrated reinforced cement concrete M35 grade Providing, precasting, transportation and placing in position precast longitudinal girders as per the drawing and technical specifications 1800 & 2300 of MoRTH. from 5 to 10m

194

13988

2713672

... More
HLB across Chalivagu between Tekumatla and Ra;Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (5th revision ) and as directed by the Engineer-in-Charge for Bearing pedestals

3

7049

21147

... More
HLB across Chalivagu between Tekumatla and Ra;Bored cast-in-situ M35 grade RCC pile 1.2Mtr dia excluding reinforcement complete as per Drawing and Technical Specifications and removal of excavated earth with all lifts and lead upto 1000 m as per MoRTHspecification Nos. 1100 & 1700 for piles in Hard Rock

44

20502

902088

... More
HLB across Chalivagu between Tekumatla and Ra;Bored cast-in-situ M35 grade RCC pile 1.2Mtrs dia excluding reinforcement complete as per Drawing and Technical Specifications and removal of excavated earth with all lifts and lead upto 1000 m as per MoRTHspecification Nos. 1100 & 1700 for piles in Soil

168

14566

2447088

... More
HLB across Chalivagu between Tekumatla and Ra;Vibrated reinforced cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, . conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (5th revision ) and as directed by the Engineer-in-Charge for pile cap

141

6875

969375

... More
HLB across Chalivagu between Tekumatla and Ra;Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (5th revision ) and as directed by the Engineer-in-Charge for Piers sub structure - from 5m to 10m height

83

7251

601833

... More
HLB across Chalivagu between Tekumatla and Ra;Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (5th revision ) and as directed by the Engineer-in-Charge for Piers sub structure - Up to 5m height

53

7021

372113

... More
HLB across Chalivagu between Tekumatla and Ra;Plain cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, and conveyance of all materials to site and all labour charges for machine mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (5th revision) for Levelling course below Pile caps

12

5901

70812

... More
HLB across Chalivagu between Tekumatla and Ra;Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and technical specification including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc., complete for finished item of work as per MoRT&H specification 304(5th revision) and as directed by the Engineer-in-Charge In ordinary soils upto SDR soils using Machinery including dewatering charges up to 3.0m depth Removing soil up to pile cap bottom level

192

143

27456



Evaluation Notes How It Works ?

Potential Partner

Select Your Requirements
Disclaimer: BidAssist has made every reasonable effort to ensure that the information is accurate and authentic however it cannot be held liable for any third-party claims or losses of any damages. BidAssist makes no warranty, expressed or implied, as to the results obtained from the use of the information. If you think you may have noticed any error or omission, please let us know by contacting contact@bidassist.com.