Roads And Buildings Department Tender
For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.
Roads And Buildings Department Tender
Civil And Construction
Building Construction
Opening Date9 Feb 2024
Closing Date16 Feb 2024
Tender Amount₹ 2,10,21,577
Costs
EMD
Refer DocumentsDocument Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
496353Tender No
Chief Engineer (R&B), D&P,LWE, RSW,QC& Admn NIT No.2050/156/5th call/B36/CE (D&P, LWE, RSW, QC, Admn.&RR)/ LWE/EE/DEE/AEE2/2023-24, Dt:05.02.2024Tender Authority
Roads And Buildings Department ViewPurchaser Address
-Website
http://http://www.rnbgujarat.org/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
Bridge Approaches;Construction of shoulders by providing selected earth having minimum CBR of 10 % ,MDD not less than 1.85 g/cc with LL & PI not more than 40% and 20 respectively and spreading in uniform layers with tractor grader on prepared surface , and compacted at OMC with Vibratory roller 80-100 KN to meet requirement of Table 300.2 with as per Technical Specification clause 303 MORD/305 MORTH, by using machinery including contractors profit & Over head charges,excluding Seigniorage charges and GST etc., complete.
158
304
48032
Bridge Approaches;Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in sub-base/base course on a well prepared sub-base and compacting with Vibratory Roller 80-100 kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406 MORD/MORTH, including contractors profit & Over head charges ,excluding Seigniorage charges and GST etc.,Complete .
368
3450
1269600
Bridge Approaches;Providing and applying prime coat with bitumen emulsion (SS-2) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.85 kg/sqm using mechanical means as per Technical Specification Clause 502 MORD (for use on Wet mix macadam) ,including contractors profit & Over head charges but excluding Seigniorage charges, GST Complete .
1470
45
66885
Bridge Approaches;Providing and applying tack coat with bitumen VG 10 Grade (Bulk) using Bitumen pressure distributor at the rate of 0.20 Kgs per sqm on the prepared bituminous/granular surface cleaned with mechanical broom for finished item of work as per MoRT&H Specification 503 (5th revision) and as directed by the Engineer-in-Charge and including contractors profit & Over head charges but excluding Seigniorage charges, GST Complete .
1470
17
25946
Bridge Approaches;Providing and laying Bituminous Concrete with 100-120 TPH Batch Type hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified Grading, premixed with bituminous binder @ 5.4 to 5.6 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRT&H Specification clause No :509 complete in all respects, including contractors profit & Over head charges excluding Seigniorage charges and GST., Complete
44.1
11701
516014
Bridge Approaches;Providing and laying reinforced cement concrete Hume pipes of 1000mm dia NP3 class for pipe culverts including cost and conveyance of pipes etc., complete and labour charges for laying, jointing of 1000mm dia RCC Hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (5th Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work.
30
4161
124830
Bridge Proper;Earthwork excavation for structures as per drawing and technical specifications clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50m, dressing sides of bottom and back filling in treanches with excavated suitable material as per technical specification 305 MORD/304 MORTH, including contractor profit & overhead charges excluding seigniorage charges and GST etc.,complete in ordinary soils up to SDR up to 3m depth
2918
120
350160
Bridge Proper;Providing concrete for plain concrete M10 grade in open foundations using 40mm nominal size graded hard stone aggregate (HBG),mechanically mixed ,placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clauses 802,803,805,806,807 ,1202 and 1204 MORD and 1500,1700 & 2200 MORTH, including contractor profit & overhead charges ,excluding seigniorage charges and GST etc.,complete for levelling course
65
5971
388115
Bridge Proper;Providing concrete for plain concrete M15 grade for cutoff walls and rigid aprons using 40mm graded hard stone aggregate (HBG),mechanically mixed , placed in foundation and compacted by vibration including curing for 14 days complete as per drawings and technical specifications Clauses 802,803,1202 and 1203 MORD and 1500,1700 & 2100 MORTH, including contractor profit & overhead charges,excluding seigniorage charges and GST
229
6191
1417739
Bridge Proper;Reinforced cement concrete M25 grade (Design Mix) using 25 &10 mm metal (HBG) mechanically mixed in foundation complete as per drawings and technical specification Clauses 802,804,805,806,807 , 1202 and 1204 MORD and 1500,1700 & 2200 MORTH, including contractor profit & overhead charges , excluding seigniorage charges and GST etc.,complete for finished item of work
331
8295
2745645
Bridge Proper;Plain cement concrete M20 grade using 40, 20 & 10mm metal (HBG) mechanically mixed in foundation complete as per drawings and technical specification Clauses 802,804,805,806,807 ,1202 and 1204 MORD and 1500,1700 & 2200 MORTH, including contractor profit & overhead charges , excluding seigniorage charges and GST etc.,complete for foundations
68
6867
466956
Bridge Proper;Plain cement concrete M20 grade using 40, 20 & 10mm metal (HBG) mechanically mixed in sub structure complete as per drawings and technical specification Clauses 802,804,805,806,807 ,1202 and 1204 MORD and 1500,1700 & 2200 MORTH, including contractor profit & overhead charges , excluding seigniorage charges and GST etc.,complete for sub structure of piers, abutments and wing walls. Height Upto 5.0m
397
7264
2883808
Bridge Proper;Plain cement concrete M20 grade using 40, 20 & 10mm metal (HBG) mechanically mixed in sub structure complete as per drawings and technical specification Clauses 802,804,805,806,807 ,1202 and 1204 MORD and 1500,1700 & 2200 MORTH, including contractor profit & overhead charges , excluding seigniorage charges and GST etc.,complete for sub structure of piers, abutments and wing walls. Height above 5.0m
130
7924
1030120
Bridge Proper;Reinforced cement concrete M 25 grade(Design Mix) using 20 & 10mm metal mechanically mixed in sub structure as per drawings and technical specifications Clauses 800 ,1205.4 MORD sections 1500, 1600 & 1700 MORTH, including contractor profit & overhead charges, excluding seigniorage charges , cost of steel etc., complete for Bed Blocks / Backing walls
14
8773
122822
Bridge Proper;Providing and laying Reinforced cement concrete M 25 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in Super structure as per drawing and technical specifications Clauses 800, 1205.4 and 1205.5 MORD sections 1500, 1600 & 1700 MORTH, including contractor profit & overhead charges ,excluding seigniorage charges and GST up to 5m height - For super structure (Deck Slab)
208
9571
1990768
Bridge Proper;P.C.C M15 ordinary grade leveling course below approach slab complete as drawing and technical specifications clauses 800 and 1211 MORD & 2700 MoRTH including overhead charges & contractors profit , excluding Seigniorage charges, and GST charges., complete Under Approach slabs
8
7040
56320
Bridge Proper;Vibrated reinforced cement concrete M 30 grade (Design Mix)using 20mm & 10mm metal mechanically mixed for approach slab as per drawing and technical specifications clauses 800 and 1211 MORD sections 1500,1600 & 1700 & 2704 MORTH including overhead charges & contractors profit , excluding Seigniorage charges, and GST charges but excluding cost of steel ., complete For Approach slabs
18
7555
135990
Bridge Proper;Providing and laying cement concrete wearing course M 30 (Design Mix) grade using 20 & 10mm metal mechanically mixed excluding reinforcement complete as per drawing and technical specifications Clauses 800 & 1206.3 MORD and 2702 MORTH including overhead charges & contractors profit , excluding Seigniorage charges, and GST charges but excluding cost of steel .,complete
30
8331
249930
Bridge Proper;Vibrated reinforced cement concrete M 40 grade using 20mm & 10mm hard broken graded granite crushed metal (SS-5) including cost, conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P and all water leads etc., complete as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 809,1500,1600,1700 & 2200 (5th revision ) and as directed by the Engineer-in-Charge for Crash barrier, excluding Reinforcement.
28
9163
256564
Bridge Proper;Cost,Supply and fixing of Bituminous Mastic Pad 25.4mm including cost & conveyance and all labour charges and including contractors profit & overhead charges, excluding seigniorage charges and GST charges etc. complete.
61
839
51179
Bridge Proper;Supplying, fitting, and placing HYSD bar reinforcement Fe 500 in foundation complete as per drawing and technical specifications Clauses 1000 and 1202 MORD / 1100, 1600 MORTH, for Bars below 36 mm dia including over laps and wastage, where they are not welded including overhead charges & contractors profit excluding seigniorage charges and GST charges etc. complete.
19
81134
1541546
Bridge Proper;Supplying, fitting, and placing HYSD bar reinforcement Fe500 in sub structure complete as per drawing and technical specifications Clauses 1000 and 1202 MORD / 1100, 1600 MORTH, for Bars below 36 mm dia including over laps and wastage, where they are not welded including overhead charges & contractors profit excluding seigniorage charges and GST charges etc. complete.
9.3
81393
756955
Bridge Proper;Supplying, fitting, and placing HYSD bar reinforcement Fe500 in super structure complete as per drawing and technical specifications Clauses 1002, 1010 and 1202 MORD / 1600 MORTH, for Bars below 36 mm dia including over laps and wastage, where they are not welded including overhead charges & contractors profit and etc. complete.
19.3
83140
1604602
Bridge Proper;Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia PVC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing and technical specification Clauses 614, 709, 1204.3.7 MORD/2706 & 2200 MoRTH including contractors profit & Over head charges,excluding Seigniorage charges, GST etc., Complete .
298
379
112942
Bridge Proper;Providing and laying filter media with granular crushed aggregates as per specification to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and providing over the entire surface behind abutment, wing wall, return wall to the full height, compacted to firm condition complete as per drawing and technical specification Clause 1204.3.8/ 710.1.4 of IRC:78 and 2200 MoRTH including Over head charges & contractors profit excluding Seigniorage charges and GST charges etc., Complete
109
2120
231080
Bridge Proper;Backfilling behind abutment, wing wall and return wall complete as per drawings & technical specification Clause 1204.3.8 MORD/ 710.1.4 of IRC, 78 & 2200 MORTH, includingOver head charges & contractors profit , excluding Seigniorage charges and GST charges.,Complete
334
698
233132
Bridge Proper;Jeddy Stone Dry Packing for Aprons and Revetments section 1300 MORD including cost and conveyance of all materials and all labour charges etc., complete including contractors profit & Over head charges ,excluding Seigniorage charges and GST etc., complete.
178
1294
230332
Bridge Proper;Supplying and fixing of drainage spouts complete as per drawing and Technical Specification No.2705 (As per Data communicated vide Circular Memo No. D&P/Bridge work estimates/Non SSR Items/rates/2009-1 Dt 13-08-09 of the Chief Engineer (R&B), Designs & Planning wing,) including Over head charges & contractors profit ,excluding Seigniorage charges and GST etc., complete.
12
2685
32220
Bridge Proper;Providing and filling joint sealing compound as per drawings and technical specifications with coarse sand 6 percent bitumen by weight including Over head charges & contractors profit ,excluding Seigniorage charges and GST etc., complete.
34
38
1292
Bridge Proper;Construction of RCC guide posts of 250mm dia M20 grade cast-in-situ with 20mm nominal size agrregate (HBG) true to line and grade tolerance of vertical RCC posts not to exceed 1 in 500 as i per drawing and Technical Specification Clause 1608.2 including contractors profit &Over head charges, but excluding Seignorage& GST, but excluding Seignorage& GST
120
777
93240
Bridge Proper;Providing Grouted Revetment with rough stone (HBG) of not less than 300 mm size grouted with 0.20 cum of CC (1:4:8) including cost and conveyance of materials to site and including labour charges for packing the stones for revetment etc., complete for finished item of work as per MoRT&H specification 2504 (5th revision ) and as directed by the Engineer-in-Charge for quadrential revetment.
71
2290
162590
Bridge Proper;Providing and laying filter material with gravel underneath pitching in slopes including cost and conveyance of materials to site including labour charges etc., complete for finished item of work as per MoRT&H Specification 2504 (5th Revision) and as directed by the Engineer-in-Charge under Revetment.
36
317
11412
Bridge Proper;Pitching with 300 mm size rough stone including cost and conveyance of materials to site and including labour charges for packing the stones for revetment etc., complete for finished item of work as per MoRT&H specification 2504 (5th revision ) and as directed by the Engineer-in-Charge for Embankment slopes/ Toe walls.
18
1157
20826
Bridge Proper;Painting two coats including primer coat after filling the surface with synthetic enamel paint in all shades on new plastered concrete surfaces as per drawing and Technical Specification Clause 1701 MoRD, including Over head charges & contractors profit ,excluding Seigniorage charges and GST etc., complete.
202
146
29492