Public Health And Municipal Engineering Department Tender
For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.
Costs
EMD
Refer DocumentsDocument Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
519978Bid Award Id
ViewTender No
05/21/DB/D4/HSNBD/park/TUFIDC/2024, Dt: 11.06.2024Tender Authority
Public Health And Municipal Engineering Department ViewPurchaser Address
-Website
http://http://www.appublichealth.gov.in/
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
Documents
BOQ Items
... More
development of park;Filling with Gravel/ excavated soils with initial lead in layers not exceeding 15 cm thick, consolidating each deposited layer by watering and rolling with 2 Tonns roller including cost and conveyance of water to work site and all operational, incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
6300
199
1259559
... More
development of park;BLD-Amendment Sl No. 5: Providing High Yield Strength Deformed (HYSD) (Fe 500/550/550D) of different diameters for RCC works , including labour charges for straightening, cutting, bending to required sizes and shapes, placing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting, bending, placing in position, tying including all charges on all materials etc., complete for finished item of work in all floors.( APSS No.126)
8121.4
77
628677.57
... More
development of park;BLD-CSTN-12-3-(170) & amendment; Painting to walls with two coats of acrylic emulsion paint exterior grade having VOC (Volatile Organic Compound) content less than 50 grams/ liter and shade over existing base coat of water based primer of exterior grade-2 of approved brand, making 3 coats in all to give an even shade after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials, including cost and conveyance of all materials to work site and all operational, incidental, labour charges etc. complete and cost of overheads & contractors profit for finished item of work as per SS 912 for external walls.
1050.54
191
201388.52
... More
development of park;BLD-CSTN-12-2-(169) : Painting, Priming Coat on New Plastered Surface with Cement Primer Water base Exterior Gr-2 after thoroughly brushing the surface to remove all dirt and remains of loose powdered materials including cost of all materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished item of work.
1050.54
83
88140.31
... More
development of park;BLD-CSTN-8-9-(84) : Plastering 20mm thick two coats with base coat of 16mm thick in C.M. (1:6) and top coat of 4mm thick in C.M. (1:4) with dubara sponge finishing including cost & conveyance of all materials like cement, Sand , Water, etc., to site, , all operational, including charges, labour charges for mixing mortar, finishing, scaffolding, lift charges, curing , including cutting grooves where ever necessary etc., complete for finished item of work of uneven surfaces of walls. (For External walls).
1050.54
517
543349.79
... More
development of park;BLD-CSTN-5-17-(55): Brick Masonry work in CM (1:6) prop with Flyash Cement solid blocks of size 290 x 225 x 140 mm for manufacturing of flyash solid blocks using flyash of 80 kgs, cement of 15 kgs. Gypsum of 5 kgs. and stone dust including cost and conveyance of all materials, labour charges, scaffolding and curing etc., complete with a compresive strength not lessthan 50 kg/sqm for walls for Superstructure Walls.
110.54
7031
777243.22
... More
development of park;BLD-CSTN-6-6-(61) : Construction of CRS Masonary 2nd Sort in Cement Mortor ( 1:6 ) Prop using hard granite stone including cost & Conveyance of all materials like Cement, Sand , Water, Granite Stones, including ,labour charges for cutting Stones to required size and shape, mixing of Cement Mortor, Construction, Scaffolding Charges curing etc., complete for finished item of Work .
54.68
4519
247112.04
... More
development of park;BLD-CSTN-6-12-(67) : Construction of RR Masonary in Cement Mortor ( 1:6 ) Prop using hard granite stone including cost & Conveyance of all materials like Cement, Sand , Water, Granite Stones, including labour charges for cutting Stones to required size and shape, mixing of Cement Mortor ,Construction, Scaffolding Charges curing etc., complete for finished item of Work .
97.2
4050
393660.97
... More
development of park;BLD-CSTN-3-15- ( 31 ) -B: Supply and placing of the M-25 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate , coarse aggregate, water etc., to site , including all operational, incidental and labour charges such as weigh batching, machine mixing, laying concrete, vibrating, curing, centering and suttering charges etc.,complete , cost of steel and its fabrication charges for finished item of work (APSS No. 402) with minimum cement content as per IS code for COLUMNS,
23.6
13150
310353.69
... More
development of park;BLD-CSTN-3-14-(31) - A : Supply and placing of M25 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including all operational, incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code from standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication charges for finished item of work. ForPlinth Beams
18.42
12754
234932.18
... More
development of park;BLD-CSTN-3-14-(31) - A : Supply and placing of M25 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER / MIXER with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water etc., to site and including all operational, incidental and labour charges such as weigh batching, machine mixing, laying concrete, curing etc.,complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)with minimum cement content as per IS code from standard suppliers approved by the department including pumping, centering, shuttering, laying concrete, vibrating, curing etc. complete but excluding cost of steel and its fabrication charges for finished item of work. For FOOTINGS,
38.88
10004
388983.12
... More
development of park;Plain Cement concrete M10 using 20 mm metal with hand mixing upto Plinth level including cost and conveyance of all materials like cement, sand, coarse aggregate water etc., to site , labour charges , for mixing , laying, concrete , curing etc., complete for finished item of work
20.25
4709
95361.71
... More
development of park;BLD-CSTN-2-1 (9): Earth work excavation in Ordinary Soil by Manual Means-Upto 3 m depth for foundations and depositing on bank for all lifts and with an initial lead of 10m including all operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complete for finished item of work excluding dewatering charges etc as per SS - 20 B (APSS 308).
303.75
270
82155.26