Municipality Tender
... More
For getting the details of etenders, if you are looking for information about them from the cumbersome government websites but are tired of doing so, Bidassist comes up with a one stop solution. It collates every Eproc telangana tender on Bidassist. One can approach it for the bidding process, registration process, etc., are explained below.
Costs
EMD
Refer DocumentsDocument Cost
Refer DocumentsTender Fee
Refer Documents
Description
Scription for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user this is tender description for unregistered user
Contact
Tender Id
459573Bid Award Id
ViewTender No
E1/327/MCN/2023Tender Authority
Municipality ViewPurchaser Address
-Website
http://tender.telangana.gov.in
GEM & Bid Advisory Services
Get portal registration, tender bidding, product/service listing or vendor/MSME certification services at a nominal cost
BOQ Items
... More
Construction of storm water drain walls;BLD-CSTN-3-6(23) - Plain Cement concrete nominal mix (1:5:10) prop (Cement : fine aggregate: coarse aggregate ) using 40mm size Hard Granite Machine Crushed Metal including cost and conveyance of all materials like cement, sand, coarse aggregate water etc., to site , seigniorage charges on all materials, labour charges , for mixing , laying, concrete , ramming in 15 cm layers, finishing top surface to the required level curing etc., complete for finished item of work.for foundation and under flooring bed.
3.6
4184
15064.45
... More
Construction of storm water drain walls;RBR-FNDN-1: A i: Earthwork excavation in ordinary soil by manual means up to 3 mts depth for structures as per drawing and technical specifications Clause 305.1 including disposal upto a lead of 50 m, dressing of sides and bottom as per Technical Specification 305 MORD / 304 MORTH
25.2
451
11385.61
Evaluation Notes How It Works ?
Potential Partner
Select Your Requirements